CN106193685A - Prefabricated assembled communications equipment room structure - Google Patents
Prefabricated assembled communications equipment room structure Download PDFInfo
- Publication number
- CN106193685A CN106193685A CN201610756554.3A CN201610756554A CN106193685A CN 106193685 A CN106193685 A CN 106193685A CN 201610756554 A CN201610756554 A CN 201610756554A CN 106193685 A CN106193685 A CN 106193685A
- Authority
- CN
- China
- Prior art keywords
- communications equipment
- prefabricated assembled
- equipment room
- plate
- room structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H5/00—Buildings or groups of buildings for industrial or agricultural purposes
- E04H5/02—Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Building Environments (AREA)
Abstract
The present invention provides a kind of prefabricated assembled communications equipment room structure, including spliced machine room;Described spliced machine room includes top board, wallboard, base plate and base;Described base plate is laid on described base, and the bottom of described wallboard is perpendicularly fixed on described base plate;Described top board is perpendicularly fixed at the top of described wallboard, and parallel with described base plate;Described wallboard includes four pieces of warming plates, and one of warming plate is provided with door-plate.The computer room structure of the present invention, top board, wallboard etc. all use precast construction, actually used during, can the most quickly splice, substantially increase the efficiency of construction of machine room, and do not affected by extraneous construction environment.
Description
Technical field
The present invention relates to prefabricated machine room manufacturing technology, particularly relate to a kind of prefabricated assembled communications equipment room structure, belong to logical
News infrastructure manufacturing technology field.
Background technology
Tradition be civil engineering structure communications equipment room exist in building course pollution environment, disturb residents, construction period length, by weather
The unfavorable factors such as impact is big.Due to the fast development of communication career, in the face of Ge great operator requirement more and more higher, hand over
Pay that the cycle is shorter and shorter and the common people to number one protective awareness increasingly stronger in the case of, in the urgent need to making reform, be full
Foot communication infrastructure base station construction cycle modularity shorter, more environmentally-friendly, more standardized, quality be higher and more cost effective need
, prior art needs a kind of prefabricated assembled communications equipment room of research and development badly.
Summary of the invention
The present invention provide a kind of can the prefabricated assembled communications equipment room structure of quick assembling, to solve civil engineering in prior art
Construction period length that communication machine room exists, affected greatly by weather, noise is big and the technical problem of pollution environment.
The prefabricated assembled communications equipment room structure of the present invention, including: spliced machine room;
Described spliced machine room includes top board, wallboard, base plate and base;Described base plate is laid on described base, described
The bottom of wallboard is perpendicularly fixed on described base plate;Described top board is perpendicularly fixed at the top of described wallboard, and with described base plate
Parallel;
Described wallboard includes four pieces of warming plates, and one of warming plate is provided with door-plate.
Prefabricated assembled communications equipment room structure as above, wherein, described top board includes that three pieces are generally aligned in the same plane and depend on
Secondary connected concrete face-board for room;It is provided with waterproof roll on described concrete slab;The edge of described concrete slab is provided with
Snap-in groove, adjacent two pieces of described concrete slabs form S-shaped seam by described snap-in groove, are provided with rubber in described seam
Glue sealing strip and PE filler rod.
Prefabricated assembled communications equipment room structure as above, wherein, the side of described warming plate is provided with U row reinforcing bar and connects
Head, the U-shaped opening of described U-shaped splice is arranged inwardly;It is additionally provided with vertical joint bar, institute between adjacent two described warming plates
State vertical joint bar for inserting the U row splice of connected two described warming plate sides.
Prefabricated assembled communications equipment room structure as above, wherein, described base includes laying the most successively
Blotter, plain concrete cushion layer and seat pulp layer;Described base plate paving is on described seat pulp layer.
Prefabricated assembled communications equipment room structure as above, wherein, described steel tower is arranged with cushion cap;Described spliced
Machine room is outside equipped with marks time, described in mark time and be positioned at below described door-plate, and corresponding with described door-plate.
Prefabricated assembled communications equipment room structure as above, wherein, is provided with prefabricated penetration pipe, connects in described warming plate
Ground lead-in wire and rosette.
Prefabricated assembled communications equipment room structure as above, wherein, described base plate is equipped with floor tile.
Prefabricated assembled communications equipment room structure as above, wherein, described top board, base plate and wallboard is provided with and hangs
Loading nut.
Prefabricated assembled communications equipment room structure as above, wherein, described base plate includes two block concrete precoated plates, institute
It is provided with bar-mat reinforcement in stating concrete prefabricated board.
Prefabricated assembled communications equipment room structure as above, wherein, described spliced machine room is outside equipped with hands well;Described
Spliced machine room bottom outside is additionally provided with a circle aproll plate.
The computer room structure of the present invention, top board, wallboard etc. all use precast construction, the classifying rationally weight of every block of prefabricated panels
Amount and structure, it is possible to just by good for the designed in advance such as pre-buried, spool when prefabricated;During actually used, can carry out fast at the scene
Speed Pinyin connects, and substantially increases the efficiency of construction of machine room, and is not affected by extraneous construction environment.
Accompanying drawing explanation
Fig. 1 is the overall schematic of the prefabricated assembled communications equipment room structure of the embodiment of the present invention;
Fig. 2 is the front view of the prefabricated assembled communications equipment room structure of the embodiment of the present invention;
Fig. 3 is the rearview of the prefabricated assembled communications equipment room structure of the embodiment of the present invention;
Fig. 4 is the sectional view of Fig. 3;
Fig. 5 is the top cross-sectional view of Fig. 2;
Fig. 6 is the parts enlarged drawing of Fig. 5;
Fig. 7 is enlarged drawing at A in Fig. 4;
Fig. 8 is enlarged drawing at B in Fig. 6;
Fig. 9 is enlarged drawing at C in Fig. 5.
Detailed description of the invention
As shown in Figure 1, Figure 2 and Fig. 3, and with reference to Fig. 4;The prefabricated assembled communications equipment room structure of the present embodiment, including: spliced
Machine room 100;The most also include that steel tower, spliced machine room 100 and steel tower are connected by outdoor feeder shelf;Outdoor feeder shelf is general
It is arranged at the top of spliced machine room.
Spliced machine room 100 includes top board 1, wallboard 2, base plate 3 and base 4;Base plate 3 is laid on base 4, wallboard 2
Bottom is perpendicularly fixed on base plate 3;Top board 1 is perpendicularly fixed at the top of wallboard 2, and parallel with base plate 3;Wallboard 2 includes four pieces
Warming plate 20, one of warming plate 20 is provided with door-plate 26.
Generally, wherein, steel tower is arranged with cushion cap;Cushion cap is generally concreting, for carrying steel tower
Weight.Spliced machine room 100 is outside equipped with marks time 25, and marking time 25 is positioned at below door-plate 26, and corresponding with door-plate 26.Mark time 25
Use prefabricated marking time, after base plate 3 grade completes, be directly arranged at outside spliced machine room by concrete cushion.
The main body of the whole spliced computer room structure of the present embodiment is assembled by different piece;General top board is divided into three
Block, wallboard is divided into four pieces, and base plate is divided into two pieces;Every moiety by weight controls within 6t, it is simple to lifting operation.Every part
Insulation, exterior, built-in pipe, line box, door etc. waterproof, interior complete in factory substantially, and assembled in situ has only to simple process after completing
Cabling, mounted lamp and inner veneer, and the making up a deficiency of outward appearance.The prefabricated assembled communications equipment room structure of the present embodiment, on-the-spot
Installation rate is fast, and joining quality is high.
The prefabricated assembled communications equipment room structure of the present embodiment, as shown in figs. 4 and 7, top board 1 includes that three pieces are positioned at same
Plane is sequentially connected concrete face-board for room 10;Waterproof roll 15 it is provided with on concrete slab 10;The edge of concrete slab 10
Being provided with snap-in groove, adjacent two pieces of described concrete slabs form S-shaped seam, S-shaped seam by described snap-in groove, help
In waterproof and increase seal.Rubber weather strip 17 and PE filler rod 18 it is provided with in this seam.Rubber weather strip 17 and PE is filled out
Fill after rod 18 inserts seam, the floating seam of Reperfu-sion concrete mortar, simultaneously the rainwater gradient is set on top board, so can ensure
Water proofing property that seam crossing is good and sealing;And, rubber weather strip 17 and PE filler rod 18 is elastic construction, also functions to close
Close the effect of shrinkage joint.
The prefabricated assembled communications equipment room structure of the present embodiment, such as Fig. 5 and Fig. 6, and with reference to shown in Fig. 8 and Fig. 9;Warming plate
The thick thermal insulation board 201 of 50mm, generally styrofoam or polyurethane sheet it is provided with in 20.The side of warming plate 20 is provided with U row steel
Muscle joint 202, the U-shaped opening of described U-shaped splice 202 is arranged inwardly;The i.e. side of warming plate 20 is provided with multiple semicircle
The reinforced steel bar ring structure of shape.Being additionally provided with vertical joint bar 203 between adjacent two warming plates 20, vertical joint bar 203 is used for inserting phase
The even U row splice 202 of two warming plate 20 sides.After vertical joint bar inserts, can be by the side of two pieces of adjacent warming plates
While be connected firmly, and this structure is highly susceptible to installing, it is possible to be quickly stitched together by metope.
As it is shown on figure 3, described base 4 includes blotter 41, plain concrete cushion layer 42 and laid the most successively
Sit pulp layer 43;Base plate 3 is layed on seat pulp layer 43;Typically floor tile also it is equipped with on base plate 3.
The prefabricated assembled communications equipment room structure of the present embodiment, is provided with prefabricated penetration pipe, ground lead in warming plate 20
And rosette, as required can be with prefabricated air-conditioning penetration pipe etc..
The prefabricated assembled communications equipment room structure of the present embodiment, base plate 3 includes two block concrete precoated plates 30, described coagulation
It is provided with bar-mat reinforcement in soil precoated plate 30.Between two block concrete precoated plates 30, there is vertical seam 301;In vertical seam 301
Being perfused with mortar, vertical seam 301 can also use U row splice to coordinate the attachment structure of vertical joint bar, with fast and easy
Concatenation construction.
It addition, for the ease of installing, the prefabricated assembled communications equipment room structure of the present embodiment, wherein, top board 1, base plate 3 and
It is provided with lifting nut on wallboard 2, so can conveniently lift.Spliced machine room 100 is outside equipped with hands well 35;Spliced machine
Room 100 bottom outside is additionally provided with a circle aproll plate.
The machine room of the present embodiment can resist the earthquake intensity of 6 degree of district 0.05g, and the blast of the 0.45KN/ met for 50 years,
The design working load of floor plate is 6KN/, and the live load of roof boarding is 2KN/, and the machine room after assembling always weighs about 40t.
The prefabricated assembled communications equipment room structure of the present embodiment has techniques below advantage.
1) cost angle is saved: novel machine room build process can more save material, thus it is whole to be finally reached saving
Witnessing of body cost;The prefabricated assembled communications equipment room of the present embodiment is structurally characterized in that light body, and the gross weight of every square metre is only
The 60% of " brick mix structure machine room ", about the 80% of " cast-in-place framework machine room ", therefore, same area and the machine room base of height
Plinth materials can save more than 10%.
2) reduction of erection time angle: novel machine room build process completes more to accelerate than traditional machine room from design to installation
Prompt;The prefabricated assembled preposition research and development of communications equipment room structure of the present embodiment and design, after the output of digitized drawing, utilize the fastest
Speed accurately produces and has tentatively assembled, and greatly reduces Contraction in Site face and time;And the prefabricated post produced, beam,
Wall, plate, all use nonexpondable punching block without a mold materials, can save man-hour 30% for every cubic metre, based on once damaging
Calculating, formwork fee of material is 3% one 5%.
3) adaptable angle of environment: novel machine room build process can be without being that rainy season, winter, summer etc. are extreme in opinion
Normal construction under climatic condition;" tradition machine room " is affected by natural environment such as heat, rainy season, frozen soil, is likely to result in and executes
The indefinite duration of duration extends, and causes machine room to pay time delay, the whole project progress of final impact;And the communications equipment room knot of the present embodiment
Structure does not has field operation substantially, few to space enrironment disturbance, and the impact on nearby residents is little.Number is it was demonstrated that cash field wet trade
For prefabrication assembling work, significantly reduce the discharge of waste water,waste gas and industrial residue, be effectively improved to water, energy, material, etc. joint
About, it is achieved the green idea of " four joint one environmental protection ", and the communications equipment room structure of the present embodiment by series of products to various fields
Ground landform, weather conditions have stronger adaptability, and can move flexibly, combine, and recycle.
4) quality point of machine room: novel machine room build process can break traditions the machine room at set intervals of machine room
The big continuous shortcoming of indisposition, has higher quality, higher standard;Owing to traditional civil engineering machine room mostly is manual work,
Cracking, hollowing, come off, the common fault such as seepage often occurs.The quality of construction is uneven;And the communications equipment room structure of the present embodiment
Take into full account structural safety, run safety, insulation, waterproof fireproofing performance.The full prefabricated components of factory, main body preassembling,
On-the-spot specialty lifting puts in place, it is ensured that component parts and the good quality of combination product and performance, it is to avoid cracking, hollowing, de-
Fall, the common common fault such as seepage.Situ wet operation is zero, short construction period, and on-the-spot weather and environment in season are to construction infection not
Greatly.AS and the materials such as long-range monitoring, BA, high-performance insulation material can also be constantly integrated in actual application according to demand
Material, improves machine room performance further.
5) disturb residents angle: novel machine room build process can be more quick, does not affect the living environment of the periphery common people;Root
Showing according to investigations, sending the administrative department of environmental conservation in one's power middle significant portion of putting on record is that resident cannot stand periphery construction site pair
The impact of their daily life, about 40 days " traditional brick mixes machine room " site operation cycles, and the communications equipment room structure of the present embodiment
On-site construction time be only two and half.
6) protection environmental: novel machine room build process can not pollute surrounding enviroment in building course, produces
Less building waste;The air-borne dusts produced in the prefabricated assembled communications equipment room structure manufacturing process of the present embodiment etc. pollute
All seldom (the 20% of air-borne dust only " traditional brick mixes machine room ", the building waste of generation is only " traditional brick mixes machine room "
30%), and " traditional brick mixes machine room " can cause substantial amounts of dust in process of construction, and leaves the house refuse of workmen.
7) machine room standardization, modularity angle: novel machine room build process can make the instrument that novel machine room picture is accurate
Production the most more standardized, modular, reduces the probability of defect ware;The communications equipment room structure the most same portion essence of the present embodiment
True equipment, changes the looks of tradition civil engineering operation, will not cause the instability of quality because of anthropic factor, and product is to be
Rowization, and have quality standard, each product can collateral use handbook, instruct transport, install and routine use is safeguarded, permissible
Saying that traditional machine room is the house of receiving equipment, the communications equipment room structure of a present embodiment inherently equipment, it is with internal
Equipment be an organic whole and establish modulus basis and modular system, have downwards miniaturization, light weight
Change, the light version considered integrated by detachable, equipment and civil engineering machine room, fully integrated, comprise what device context operation completed the same day
Minimum version, upwards can form the growth money that standard money combines, to adapt to different use demands.
8) energy consumption angle is reduced: novel machine room build process is being built and during the use in later stage, it is necessary to possess more
Low energy consumption;The prefabricated assembled communications equipment room structure manufacturing process of the present embodiment can save the energy of 15%, uses process
The middle saving energy about 25%~35%.
9) from water resource angle: the minimizing that novel machine room build process can be tried one's best building course is not even sacrificed
The water resource environment of periphery;The prefabricated assembled communications equipment room structure manufacturing process of the present embodiment can save the water of more than 36%
Resource and the water resource of periphery will not be polluted, and " tradition machine room " in process of construction can near water environment impact
And pollution.
10) noise pollution angle: novel machine room build process can not produce noise pollution in building course;This reality
Prefabricated assembled communications equipment room structure manufacture noise ratio " traditional type brick mixes machine room " the construction noise executing example is low 15 decibels, this enforcement
The prefabricated assembled communications equipment room structure soundproof effect of example is better than traditional type brick and mixes machine room ", the lowest 8 points by ambient noise interference
Shellfish.
11) country's implementation policy angle is met: novel machine room build process need to meet the existing joint carried out energetically of country
The policy of energy environmental protection;Inside and outside the prefabricated assembled communications equipment room structure of the present embodiment, light cement combined wall is used in factory
Mould produces, and smooth surface is smooth, need not do bottom surface layer again, and decorative cover can be directly done in gap after processing, save surface material
About 25%.Research and develop for China's national situation, comply with building industrialization and housing industrialization direction, meet national energy-saving, environmental protection, low
Carbon, save land, requirement of economizing on water, it is achieved building synthesis energy saving more than 65%, safety, anti-seismic performance are superior: building weight reduction
More than 30%.Construction unit, user, unit in charge of construction all there is great advantage.
12) convenience for construction angle: novel machine room build process need to improve the construction environment of field worker;The present embodiment
The manufacture of prefabricated assembled communications equipment room structure install for unit in charge of construction, reduce construction area area, decrease existing
Wet trade face, sound pollution, beneficially safety construction scene plane builds and manages.Easy construction, it is easy to operation, can have
Effect improves the working environment of builder, alleviates labor intensity, reduces the skill set requirements to operation element.Construction period contracts
Short, decrease the expense such as plant equipment, circulation material lease expenditure.
Last it is noted that various embodiments above is only in order to illustrate technical scheme, it is not intended to limit;To the greatest extent
The present invention has been described in detail by pipe with reference to foregoing embodiments, it will be understood by those within the art that: it depends on
So the technical scheme described in foregoing embodiments can be modified, or the most some or all of technical characteristic is entered
Row equivalent;And these amendments or replacement, do not make the essence of appropriate technical solution depart from various embodiments of the present invention technology
The scope of scheme.
Claims (10)
1. a prefabricated assembled communications equipment room structure, it is characterised in that include spliced machine room;
Described spliced machine room includes top board, wallboard, base plate and base;Described base plate is laid on described base, described wallboard
Bottom be perpendicularly fixed on described base plate;Described top board is perpendicularly fixed at the top of described wallboard, and parallel with described base plate;
Described wallboard includes four pieces of warming plates, and one of warming plate is provided with door-plate.
Prefabricated assembled communications equipment room structure the most according to claim 1, it is characterised in that described top board includes three pieces of positions
It is sequentially connected concrete face-board for room in same plane;It is provided with waterproof roll on described concrete slab;Described concrete slab
Edge be provided with snap-in groove, adjacent two pieces of described concrete slabs by described snap-in groove formed S-shaped seam, described in connect
Rubber weather strip and PE filler rod it is provided with in seam.
Prefabricated assembled communications equipment room structure the most according to claim 1, it is characterised in that the side of described warming plate sets
Being equipped with U row splice, the U-shaped opening of described U-shaped splice is arranged inwardly;Also set up between adjacent two described warming plates
Having vertical joint bar, described vertical joint bar is for inserting the U row splice of connected two described warming plate sides.
Prefabricated assembled communications equipment room structure the most according to claim 1, it is characterised in that described base include from lower and
On blotter, plain concrete cushion layer and the seat pulp layer laid successively;Described base plate paving is on described seat pulp layer.
5. according to the arbitrary described prefabricated assembled communications equipment room structure of claim 1-4, it is characterised in that described steel tower is divided into
It is equipped with cushion cap;Described spliced machine room is outside equipped with marks time, described in mark time and be positioned at below described door-plate, and relative with described door-plate
Should.
6. according to the arbitrary described prefabricated assembled communications equipment room structure of claim 1-4, it is characterised in that in described warming plate
It is provided with prefabricated penetration pipe, ground lead and rosette.
7. according to the arbitrary described prefabricated assembled communications equipment room structure of claim 1-4, it is characterised in that described base plate upper berth
It is provided with floor tile.
8. according to the arbitrary described prefabricated assembled communications equipment room structure of claim 1-4, it is characterised in that described top board, the end
Lifting nut it is provided with on plate and wallboard.
9. according to the arbitrary described prefabricated assembled communications equipment room structure of claim 1-4, it is characterised in that described base plate includes
Two block concrete precoated plates, are provided with bar-mat reinforcement in described concrete prefabricated board.
10. according to the arbitrary described prefabricated assembled communications equipment room structure of claim 1-4, it is characterised in that described spliced
Machine room is outside equipped with hands well;Described spliced machine room bottom outside is additionally provided with a circle aproll plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610756554.3A CN106193685B (en) | 2016-08-26 | 2016-08-26 | Prefabricated assembled communications equipment room structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610756554.3A CN106193685B (en) | 2016-08-26 | 2016-08-26 | Prefabricated assembled communications equipment room structure |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106193685A true CN106193685A (en) | 2016-12-07 |
CN106193685B CN106193685B (en) | 2019-07-30 |
Family
ID=58088117
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610756554.3A Active CN106193685B (en) | 2016-08-26 | 2016-08-26 | Prefabricated assembled communications equipment room structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106193685B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106836468A (en) * | 2016-12-22 | 2017-06-13 | 清华大学建筑设计研究院有限公司 | A kind of low multilayer assembled heat insulation energy saving building |
CN112982813A (en) * | 2021-03-19 | 2021-06-18 | 深圳市海多嘉新建材有限公司 | Self-heat-preservation quick-mounting plate and house heat preservation method |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO1998039537A1 (en) * | 1997-02-25 | 1998-09-11 | Monosite, Inc. | Integrated communications equipment enclosure and antenna tower |
US20020023394A1 (en) * | 2000-08-24 | 2002-02-28 | Mcginnis Henry J. | Prefabricated-building tower foundation |
WO2002056411A2 (en) * | 2001-01-11 | 2002-07-18 | Udo Paul Topka | Installations for wireless communication |
FR2839591B1 (en) * | 2002-05-10 | 2008-07-11 | Girardot Video Comm | TELECOMMUNICATION STATION FOR DESERT AND / OR ISOLATED AREAS |
CN102071818A (en) * | 2009-11-25 | 2011-05-25 | 中国移动通信集团广东有限公司深圳分公司 | Anti-theft communication machine room with spliced concrete interlayer |
CN103243945A (en) * | 2013-05-29 | 2013-08-14 | 江苏健德铁塔有限公司 | Integrated energy-saving base station |
CN203188657U (en) * | 2013-03-05 | 2013-09-11 | 江阴市阪纳奇自动化机械设备有限公司 | Built-in type integrated tower room communication base station |
CN203594247U (en) * | 2013-11-28 | 2014-05-14 | 梁峰 | Prefabricated assembly type integrated roof self-supporting communication base station |
CN105464283A (en) * | 2016-01-05 | 2016-04-06 | 博思集团股份有限公司 | Fabricated wallboard and fabricated station building |
CN206158255U (en) * | 2016-08-26 | 2017-05-10 | 南京掌澜通信科技有限公司 | Prefabricated assembled communication machinery room |
-
2016
- 2016-08-26 CN CN201610756554.3A patent/CN106193685B/en active Active
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO1998039537A1 (en) * | 1997-02-25 | 1998-09-11 | Monosite, Inc. | Integrated communications equipment enclosure and antenna tower |
US20020023394A1 (en) * | 2000-08-24 | 2002-02-28 | Mcginnis Henry J. | Prefabricated-building tower foundation |
WO2002056411A2 (en) * | 2001-01-11 | 2002-07-18 | Udo Paul Topka | Installations for wireless communication |
FR2839591B1 (en) * | 2002-05-10 | 2008-07-11 | Girardot Video Comm | TELECOMMUNICATION STATION FOR DESERT AND / OR ISOLATED AREAS |
CN102071818A (en) * | 2009-11-25 | 2011-05-25 | 中国移动通信集团广东有限公司深圳分公司 | Anti-theft communication machine room with spliced concrete interlayer |
CN203188657U (en) * | 2013-03-05 | 2013-09-11 | 江阴市阪纳奇自动化机械设备有限公司 | Built-in type integrated tower room communication base station |
CN103243945A (en) * | 2013-05-29 | 2013-08-14 | 江苏健德铁塔有限公司 | Integrated energy-saving base station |
CN203594247U (en) * | 2013-11-28 | 2014-05-14 | 梁峰 | Prefabricated assembly type integrated roof self-supporting communication base station |
CN105464283A (en) * | 2016-01-05 | 2016-04-06 | 博思集团股份有限公司 | Fabricated wallboard and fabricated station building |
CN206158255U (en) * | 2016-08-26 | 2017-05-10 | 南京掌澜通信科技有限公司 | Prefabricated assembled communication machinery room |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106836468A (en) * | 2016-12-22 | 2017-06-13 | 清华大学建筑设计研究院有限公司 | A kind of low multilayer assembled heat insulation energy saving building |
CN106854942A (en) * | 2016-12-22 | 2017-06-16 | 清华大学建筑设计研究院有限公司 | A kind of assembled energy-saving communication base station room |
CN112982813A (en) * | 2021-03-19 | 2021-06-18 | 深圳市海多嘉新建材有限公司 | Self-heat-preservation quick-mounting plate and house heat preservation method |
Also Published As
Publication number | Publication date |
---|---|
CN106193685B (en) | 2019-07-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10808396B2 (en) | Building based on large-space structure and freestanding external envelope as well as construction method | |
CN106013811B (en) | A kind of installation method of assembled architecture | |
CN205444458U (en) | Integrated assembled steel construction building | |
CN100513717C (en) | Steel structure assisted layered installation and construction method for superhigh PRC partition plate | |
CN106522359B (en) | Fully-assembled village and town dwelling type composite wall structure system and construction method thereof | |
CN108798059A (en) | A kind of old masonry seismic reinforcing structure and construction method | |
CN103352569A (en) | Construction method of integrally-poured architecture building | |
CN204491984U (en) | Stone facing precast wall panel and external wall system | |
CN112227759B (en) | Repair, reinforcement and migration method for historic building clean water wall | |
CN105672664A (en) | Integral heat insulation wallboard building system | |
CN210178013U (en) | Fully-prefabricated assembled house | |
CN111058576A (en) | Construction method of assembled roof | |
CN206158255U (en) | Prefabricated assembled communication machinery room | |
CN106193685A (en) | Prefabricated assembled communications equipment room structure | |
CN106088316A (en) | A kind of overlapping assembled integral basement of hollow building cover post and lintel system | |
CN103362235B (en) | Integrally-poured building house with wallboards integrating thermal insulating and templates | |
CN108729692A (en) | A kind of method of construction of assembled Low-rise Lightweight system of steel residential structure | |
CN101469559B (en) | Composite heat insulating walling and mounting method thereof | |
CN203412143U (en) | Wall body structure of integrally poured building house | |
CN111101594A (en) | Cold-formed thin-wall light steel structure building | |
CN203412312U (en) | Thermal-insulating integrated template wallboard construction building | |
CN203684522U (en) | Lightweight composite prefabricated wall plate for house | |
CN206205140U (en) | A kind of full assembled villages and small towns local-style dwelling houses class composite wall structure system | |
CN207419699U (en) | A kind of energy-saving and environment-friendly industrialization prefabricated buildings structure | |
CN210713208U (en) | Transformer substation's assembled integration guard room |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |