CN204851287U - Big section moving as a whole formula formwork support - Google Patents
Big section moving as a whole formula formwork support Download PDFInfo
- Publication number
- CN204851287U CN204851287U CN201520553496.5U CN201520553496U CN204851287U CN 204851287 U CN204851287 U CN 204851287U CN 201520553496 U CN201520553496 U CN 201520553496U CN 204851287 U CN204851287 U CN 204851287U
- Authority
- CN
- China
- Prior art keywords
- steel
- portal frame
- formwork support
- frame
- door
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
本实用新型公开了一种大断面整体移动式模板支架,包括至少一组门型车架以及沿门型车架外侧设置的脚手架;门型车架包括设于两侧的支撑组件和横向钢梁,每侧支撑组件均包括底部横梁、设于底部横梁上的若干根立柱、连接相邻立柱的槽钢以及设于底部横梁两端下方的行走车轮,横向钢梁设置在两侧相应立柱的顶端并通过斜支撑加以固定;脚手架包括沿纵向设置的立杆和沿横向设置的横管,立杆与横管形成的十字连接处设有支撑钢管;脚手架通过焊接与门型车架相连,并通过钢铰链与门型车架的横、纵断面拉结。本实用新型省去脱模之后的满堂架拆除和下一工作面的再次搭设满堂架,节约人工、节省工期、避免不必要的材料损耗,同时保证了施工质量。
The utility model discloses a large-section integral mobile formwork support, which comprises at least one group of door-shaped vehicle frames and scaffolds arranged along the outside of the door-shaped vehicle frame; the door-shaped vehicle frame includes supporting components and transverse steel beams arranged on both sides , each side support assembly includes a bottom beam, several uprights on the bottom beam, channel steel connecting adjacent uprights, and walking wheels under both ends of the bottom beam, and the transverse steel beams are set on top of the corresponding uprights on both sides And it is fixed by oblique support; the scaffolding includes vertical rods arranged in the longitudinal direction and horizontal tubes arranged in the horizontal direction, and the cross connection formed by the vertical rods and the horizontal tubes is provided with supporting steel pipes; The horizontal and vertical sections of the steel hinge and the door frame are tied. The utility model omits the dismantling of the full frame after demoulding and the re-installation of the full frame on the next working face, saves labor, saves construction time, avoids unnecessary material loss, and ensures the construction quality at the same time.
Description
技术领域 technical field
本实用新型涉及路桥施工机械领域,具体涉及一种大断面整体移动式模板支架。 The utility model relates to the field of road and bridge construction machinery, in particular to a large-section integral movable formwork support.
背景技术 Background technique
在路桥施工机械领域,一些主通道隧道人防改造段的衬砌断面相对标准断面属于加宽段衬砌,如70米的衬砌断面相对于标准断面加宽约4米,此时标准断面的液压衬砌台车不能有效的使用,若重新加工定制模板衬砌台车花费时间太久成本代价太高,而采用满堂脚手架施工又会截断施工通道,影响洞内其余工作面正常作业,因此考虑利用现有材料、以门型车架为骨架配合钢管脚手架为支撑,组合成新的支撑体系,以满足施工需求,如此施工相对满堂脚手架更契合现场施工需求,但每模施工完成后钢管脚手架拆除、重新搭设依旧要耗费大量的时间、人力。 In the field of road and bridge construction machinery, the lining section of the civil air defense reconstruction section of some main passage tunnels is a widening section lining relative to the standard section. For example, the lining section of 70 meters is about 4 meters wider than the standard section. At this time, the hydraulic lining trolley of the standard section It cannot be used effectively. If it takes too long to reprocess the custom-made formwork lining trolley, the cost is too high, and the construction of full hall scaffolding will cut off the construction passage and affect the normal operation of the rest of the working face in the cave. Therefore, consider using existing materials and The door-shaped frame is the skeleton and the steel pipe scaffolding is used as the support to form a new support system to meet the construction needs. Compared with the full house scaffolding, the construction is more suitable for the construction needs of the site. However, after the construction of each mold is completed, the steel pipe scaffolding is still expensive to dismantle and re-build. A lot of time and manpower.
发明内容 Contents of the invention
发明目的:针对现有技术的不足,本实用新型提供一种大断面整体移动式模板支架,搭建过程简单,施工方便,提高作业过程安全性。 Purpose of the invention: Aiming at the deficiencies of the prior art, the utility model provides a large-section integral movable formwork support, which has a simple construction process, convenient construction, and improves the safety of the operation process.
技术方案:本实用新型所述的大断面整体移动式模板支架,包括至少一组门型车架以及沿门型车架外侧设置的脚手架;所述门型车架包括设于两侧的支撑组件和横向钢梁,每侧支撑组件均包括底部横梁、设于底部横梁上的若干根立柱、连接相邻立柱的槽钢以及设于底部横梁两端下方并与立柱正对着的行走车轮,所述横向钢梁设置在两侧相应立柱的顶端并通过设于横向钢梁、立柱之间的斜支撑加以固定;所述脚手架包括沿纵向设置的立杆和沿横向设置的横管,立杆与横管形成的十字连接处设有支撑钢管;所述脚手架通过焊接与所述门型车架相连,并通过钢铰链与所述门型车架的横、纵断面拉结。通过如上设置使得门型车架与脚手架形成整体模板支架,在外加牵引动力的基础上沿隧道内轨道得以整体移动,满足大断面的施工要求。 Technical solution: The large-section integral mobile formwork support described in the utility model includes at least one set of door-shaped frames and scaffolds arranged along the outside of the door-shaped frames; the door-shaped frames include supporting components arranged on both sides and horizontal steel beams, each side support assembly includes a bottom beam, a number of uprights on the bottom beam, channel steel connecting adjacent uprights, and walking wheels set under both ends of the bottom beam and facing the uprights. The horizontal steel beams are arranged on the tops of the corresponding uprights on both sides and are fixed by oblique supports arranged between the horizontal steel beams and the uprights; The cross connection formed by the horizontal pipes is provided with supporting steel pipes; the scaffold is connected with the door-shaped frame by welding, and tied with the horizontal and vertical sections of the door-shaped frame through steel hinges. Through the above settings, the portal frame and scaffolding form an integral formwork support, which can be moved as a whole along the inner track of the tunnel on the basis of external traction power, meeting the construction requirements of large sections.
进一步完善上述方案,所述门型车架和脚手架整体通过行走组件带动沿隧道内的钢轨移动,所述行走组件包括手拉葫芦和地锚;所述地锚在所述门型车架行进前方以逆向45°、深度为3米的方式设置,所述手拉葫芦的固定吊钩与所述地锚相连,所述手拉葫芦的悬重吊钩与所述门型车架相连。采用手拉葫芦和地锚作为行走组件提供牵引动力,施工方便,操作简单。 To further improve the above scheme, the portal frame and the scaffold are driven to move along the steel rails in the tunnel through the walking assembly, and the walking assembly includes a hand chain hoist and a ground anchor; the ground anchor is in front of the portal frame. It is arranged in a reverse direction of 45° and a depth of 3 meters. The fixed hook of the chain block is connected with the ground anchor, and the suspension hook of the chain block is connected with the portal frame. Chain blocks and ground anchors are used as walking components to provide traction power, which is convenient for construction and operation.
进一步地,所述立柱上设有用于固定所述槽钢的固定双扣,固定双扣分布在所述立柱的顶部、底部和/或中部,相邻立柱之间的槽钢的一端通过立柱顶部或底部的固定双扣固定、另一端通过立柱中部的固定双扣固定形成倾斜支撑。门型车架的固定方式保证整体移动和施工过程中的稳固,提高施工的安全系数。 Further, the column is provided with fixed double buckles for fixing the channel steel, and the fixed double buckles are distributed on the top, bottom and/or middle of the column, and one end of the channel steel between adjacent columns passes through the top of the column Or the fixed double buckle at the bottom is fixed, and the other end is fixed by the fixed double buckle in the middle of the column to form an inclined support. The fixing method of the portal frame ensures the stability of the overall movement and the construction process, and improves the safety factor of the construction.
进一步地,所述钢铰链一端与所述横向钢梁的端部相连、另一端向斜上方或斜下方延伸与所述脚手架相连,与所述横向钢梁的端部连接点同时保持横向、纵向间隔。通过钢铰链拉结门型车架和脚手架,使得整体模板支架结构稳固,保证施工质量和移动过程的稳固。 Further, one end of the steel hinge is connected to the end of the transverse steel beam, and the other end extends obliquely upward or downward to connect with the scaffold, and the connection point of the end of the transverse steel beam maintains a horizontal and vertical direction at the same time. interval. The door-type frame and scaffolding are connected by steel hinges, which makes the overall formwork support structure stable, ensuring the construction quality and the stability of the moving process.
为满足大断面隧道施工,优选的,采用两组所述门型车架、两组门型车架沿隧道方向依次紧密设置;所述门型车架的横向钢梁每侧通过三组所述钢铰链与所述脚手架拉结,每组钢铰链为两根,从所述横向钢梁的同一连接点分别向斜上方、斜下方延伸。 In order to meet the requirements of large-section tunnel construction, preferably, two sets of portal frames are used, and the two sets of portal frames are closely arranged along the direction of the tunnel; each side of the horizontal steel beam of the portal frame passes through three sets of The steel hinges are tied to the scaffolding, and each set of steel hinges is two, extending obliquely upward and downward from the same connection point of the transverse steel beam respectively.
进一步地,所述行走车轮为旋转式单轮体。采用旋转式单轮体方便整体模板支架的移动。 Further, the traveling wheel is a rotary single wheel body. The rotating single wheel body is used to facilitate the movement of the overall formwork support.
所述门型车架的宽度为4500mm、高度为4700mm,位于同侧的立柱相邻间距为1200mm。 The door frame has a width of 4500mm and a height of 4700mm, and the distance between adjacent columns on the same side is 1200mm.
所述立杆下方均垫设有木方块。 Wooden squares are all padded below the vertical poles.
有益效果:与现有技术相比,本实用新型的优点:本实用新型在现有基础上进一步对其进行改进、优化,使得门型支架和脚手架组合形成的整体模板支架在完成一模混凝土浇筑后能实现整体推移,相当于一人工改造而成的衬砌台车;该模板支架体系省去脱模之后的满堂架拆除和下一工作面的再次搭设满堂架,节约人工、节省工期、避免不必要的材料损耗,同时保证了施工质量。 Beneficial effects: Compared with the prior art, the utility model has the advantages: the utility model further improves and optimizes it on the existing basis, so that the integral formwork bracket formed by the combination of the portal bracket and the scaffold can complete the concrete pouring in one mold Afterwards, the overall movement can be realized, which is equivalent to a manually transformed lining trolley; the formwork support system saves the removal of the full-frame frame after demoulding and the re-installation of the full-frame frame on the next working face, saving labor, saving construction time, and avoiding unnecessary Necessary material loss while ensuring construction quality.
附图说明 Description of drawings
图1为门型车架的主视图。 Figure 1 is a front view of the portal frame.
图2为门型车架的侧视图。 Figure 2 is a side view of the portal frame.
图3为本实用新型的主视图。 Fig. 3 is the front view of the utility model.
图4为本实用新型的侧视图。 Fig. 4 is a side view of the utility model.
图中:1、横向钢梁,2、立柱,3、斜支撑,4、行走车轮,5、槽钢,6、支撑槽钢,7、固定双扣,8、底部横梁,21、横管,22、立杆,23、支撑钢管,24、钢铰链,25、木方块,26、手拉葫芦,27、地锚,31、钢模板,32、钢拱架,33、既有人防结构。 In the figure: 1. Transverse steel beam, 2. Upright column, 3. Diagonal support, 4. Traveling wheel, 5. Channel steel, 6. Supporting channel steel, 7. Fixed double buckle, 8. Bottom beam, 21. Horizontal tube, 22. Pole, 23. Supporting steel pipe, 24. Steel hinge, 25. Wooden block, 26. Chain block, 27. Ground anchor, 31. Steel formwork, 32. Steel arch frame, 33. Existing civil air defense structure.
具体实施方式 Detailed ways
下面通过附图对本实用新型技术方案进行详细说明。 The technical scheme of the utility model is described in detail below by means of the accompanying drawings.
实施例1:本实用新型提供的大断面整体移动式模板支架,用于主通道隧道人防改造段70米衬砌断面、该衬砌断面相对标准断面加宽约4米,包括沿隧道方向依次设置的两组门型车架和脚手架,门型车架的宽度为4500mm、高度为4700mm。如图1、图2所示的一组门型车架,包括在每侧边设置的底部横梁8、设于底部横梁上的四根立柱2、在底部横梁8两端下方与立柱2正对的位置设有行走车轮4,横向钢梁1设置在两侧相应立柱2的顶端并通过斜支撑3加以固定,斜支撑3一端与横向钢梁1的底端相连、另一端与立柱2内侧壁的底部相连,两斜支撑3的间距为2795mm,每侧相邻立柱2之间的间距1200mm;横向钢梁1顶端设有支撑槽钢6,两侧立柱2上设有固定双扣7,固定双扣7分布在立柱2的顶部、底部或中部,用于固定连接同侧相邻立柱2之间的槽钢5,槽钢5一端通过立柱2顶部或底部的固定双扣7固定、另一端通过相邻立柱2中部的固定双扣7固定形成倾斜支撑。如图3、图4所示,在门型车架外侧设置脚手架,脚手架包括沿纵向设置的立杆22和沿横向设置的横管21,相邻立杆22和横管21之间的间距为750mm;立杆22下方垫有木方块25,脚手架从隧道中心线向两侧在立杆22与横管21形成的十字连接处设有支撑钢管23,其中门型车架上部的脚手架全部落至横向钢梁1上,脚手架与门型车架的连接节点全部焊接,且整个脚手架与门型车架的横、纵断面均通过钢铰链24拉结,在门型车架的横向钢梁1每侧选取3个点设置钢铰链24,钢铰链24一端与横向钢梁1的端部相连,另一端向斜上方和斜下方延伸与脚手架相连、与横向钢梁1的连接点同时保持横向、纵向间隔,使得脚手架与门型车架形成一个整体。在既有人防结构33和脚手架外侧的钢拱架32之间设置5cm厚的钢模板31,并通过工字钢背楞对钢模板31进行加固。在门型车架行进方向20米左右距离逆向45°方向打设深度大于3米的地锚27,通过手拉葫芦26作为门型车架和脚手架牵引动力,手拉葫芦26的固定吊钩与地锚27相连,手拉葫芦26的悬重吊钩与门型车架相连。 Embodiment 1: The large-section integral mobile formwork support provided by the utility model is used for the 70-meter lining section of the civil air defense reconstruction section of the main channel tunnel. The lining section is about 4 meters wider than the standard section, including two sequentially arranged along the tunnel direction A combination of door frame and scaffolding, the width of the door frame is 4500mm, and the height is 4700mm. A group of door-shaped vehicle frames as shown in Figure 1 and Figure 2, including a bottom crossbeam 8 arranged on each side, four columns 2 arranged on the bottom crossbeam, facing the uprights 2 under the two ends of the bottom crossbeam 8 There are walking wheels 4 at the position, and the transverse steel beam 1 is set on the top of the corresponding column 2 on both sides and fixed by the diagonal support 3. The bottom of the horizontal steel beam 1 is connected, the distance between the two inclined supports 3 is 2795mm, and the distance between the adjacent columns 2 on each side is 1200mm; the top of the transverse steel beam 1 is provided with a supporting channel steel 6, and the columns 2 on both sides are provided with fixed double buckles 7, which are fixed The double buckle 7 is distributed on the top, bottom or middle of the column 2, and is used for fixedly connecting the channel steel 5 between the adjacent column 2 on the same side. One end of the channel steel 5 is fixed by the fixed double buckle 7 on the top or bottom of the column 2, and the other end is The fixed double buckle 7 in the middle of the adjacent column 2 is fixed to form an inclined support. As shown in Fig. 3 and Fig. 4, a scaffolding is set outside the portal frame, and the scaffolding includes vertically arranged vertical rods 22 and horizontally arranged horizontal tubes 21, and the distance between adjacent vertical rods 22 and horizontal tubes 21 is 750mm; wooden squares 25 are placed under the vertical pole 22, and the scaffolding is provided with a supporting steel pipe 23 at the cross connection formed by the vertical pole 22 and the horizontal pipe 21 from the centerline of the tunnel to both sides. On the transverse steel beam 1, the connection nodes between the scaffold and the portal frame are all welded, and the horizontal and vertical sections of the entire scaffold and the portal frame are tied by steel hinges 24, and each horizontal steel beam 1 of the portal frame Select three points on the side to install steel hinges 24. One end of the steel hinge 24 is connected to the end of the horizontal steel beam 1, and the other end extends obliquely upward and downward to connect with the scaffolding, and the connection point with the horizontal steel beam 1 maintains both horizontal and vertical The spacing makes the scaffolding and the portal frame form a whole. A 5cm-thick steel formwork 31 is set between the existing civil air defense structure 33 and the steel arch 32 on the outside of the scaffold, and the steel formwork 31 is reinforced by an I-shaped steel back corrugation. Set the ground anchor 27 with a depth greater than 3 meters at a distance of about 20 meters in the direction of travel of the portal frame at a distance of about 45°, and use the chain block 26 as the traction power for the portal frame and scaffolding. The fixed hook of the chain block 26 is connected to the The ground anchor 27 links to each other, and the suspension hook of the chain block 26 links to each other with the door type vehicle frame.
具体施工过程如下: The specific construction process is as follows:
在门型支架的行走车轮下铺设钢轨,钢轨需支撑在枕木上、且必须固定,将门型车架牵引至衬砌部位,门架车架中心线与隧道中心线重合,到位后用木楔子锁定行走车轮,用液压千斤顶支撑门型车架,抽出钢轨使门型车架直接落到已硬化的混凝土底板面上,并再次用木楔子锁定行走车轮;然后搭设脚手架,脚手架通过焊接与门型车架形成整体模板支架,并通过钢铰链拉结,设置钢模板并采用工字钢背楞对钢模板进行加固施工,加固完成后进行第一模混凝土浇筑施工。 Lay steel rails under the walking wheels of the portal bracket. The rails need to be supported on the sleepers and must be fixed. Pull the portal frame to the lining part. The centerline of the portal frame coincides with the centerline of the tunnel. After it is in place, lock it with a wooden wedge for walking. Wheels, use a hydraulic jack to support the portal frame, pull out the rails so that the portal frame directly falls on the hardened concrete floor, and lock the walking wheels with wooden wedges again; then set up scaffolding, which is welded to the portal frame The overall formwork support is formed and tied by steel hinges, the steel formwork is set up and the steel formwork is reinforced with I-shaped steel back corrugated, and the first concrete pouring construction is carried out after the reinforcement is completed.
第一模混凝土浇筑施工过程如下:混凝土浇注通过钢模板两侧天窗自下而上对称地分层进行,为保证门型车架受力均衡,不偏压、不移位,两边混凝土浇筑高差不超过1m;捣固利用钢模板天窗人工用捣固棒捣固,确保混凝土密实;封顶时注意浇注情况,防止注满后强行灌注混凝土而导致爆模或支撑体系破坏,又需防止泵送不到位、不饱满、出现空层;混凝土浇筑时需时刻检查支撑钢管、顶托、钢模板的支撑情况,一旦有松动、位移、弯扭及时减缓浇筑或停止浇筑,更换或加固支撑钢管,确保混凝土质量、门型车架基本结构和施工人员的人身安全。 The construction process of the first mold concrete pouring is as follows: Concrete pouring is carried out in layers symmetrically from bottom to top through the skylights on both sides of the steel formwork. More than 1m; use steel formwork skylights to tamp manually with tamping rods to ensure that the concrete is compact; pay attention to the pouring situation when capping the roof, to prevent the mold from being forced to pour concrete after filling, which will cause the mold to explode or the support system to be damaged, and to prevent pumping from being in place , is not full, and there is an empty layer; when pouring concrete, it is necessary to check the support of the supporting steel pipes, jacking brackets, and steel formwork at all times. Once there is looseness, displacement, and bending, slow down or stop pouring in time, and replace or strengthen the supporting steel pipes to ensure the quality of the concrete. , The basic structure of the portal frame and the personal safety of the construction personnel.
第一模混凝土养护强度满足施工要求后,对顶托卸载,进行脱模及表面清理工作,并对脚手架进行检查维修。然后通过电葫芦进一步拉紧钢铰链,稳定整个模板支架,后用4个30t的液压千斤顶撑起整个模板支架,调整钢轨使其到位后逐步降落千斤顶,待行走车轮全都在钢轨上后,以手拉葫芦作为门型车架牵引动力,利用行走轨道移动门型车架,同时在门型车架移动时运载整个钢管架,这样门型车架就和钢管架作为一个整体支撑体系,工作面得以转移,即可转入相邻施工面开始施工。 After the curing strength of the first mold concrete meets the construction requirements, the jacking is unloaded, demoulding and surface cleaning are carried out, and the scaffolding is inspected and maintained. Then use the electric hoist to further tighten the steel hinge to stabilize the entire formwork support, and then use four 30t hydraulic jacks to prop up the entire formwork support, adjust the rails to make them in place, and then gradually lower the jacks. As the traction power of the portal frame, the chain hoist uses the walking track to move the portal frame, and at the same time carries the entire steel pipe frame when the portal frame moves, so that the portal frame and the steel pipe frame serve as an integral support system, and the working surface can be Transfer, you can transfer to the adjacent construction surface to start construction.
在以往进行大断面衬砌时多采用满堂钢管架,这样的满堂架施工有较多缺点:首先需要大量的钢管材料(扣件、顶托);其次搭设和拆除时需要人工多、时间长,且通行不方便;工序转换复杂,劳动强度大;一次混凝土浇筑周期长,工期压力大;密集的钢管架造成施工段道路阻隔,影响现场材料机械、车辆通行。 In the past, full-wall steel pipe frames were often used for large-section linings. Such full-wall frame construction has many disadvantages: first, a large amount of steel pipe materials (fasteners, jacking) are required; The traffic is inconvenient; the process conversion is complicated and labor-intensive; the one-time concrete pouring cycle is long and the construction period is under pressure; the dense steel pipe frame blocks the road in the construction section, affecting the passage of materials, machinery and vehicles on site.
而采用本实用新型提供的整体移动式模板支架取得了良好的效果:不需要施工完后拆除满堂架、再搭设满堂架的复杂过程,大大减少人工并节约了工期,只需第一模混凝土浇筑时完成整个支架体系及行走装置的实施,后续施工便可大大缩短单模混凝土浇筑时间,且门型车架提供的作业面安全性提高,操作人员和通行人员的安全得到保障。具有施工进度快、混凝土整体性能好的优点。 However, the use of the integral mobile formwork support provided by the utility model has achieved good results: it is not necessary to dismantle the full frame after the construction and then erect the complex process of the full frame, which greatly reduces labor and saves the construction period, and only needs to pour the first mold concrete The implementation of the entire support system and walking device can be completed in time, and the subsequent construction can greatly shorten the single-form concrete pouring time, and the safety of the working surface provided by the portal frame is improved, and the safety of operators and passers-by is guaranteed. It has the advantages of fast construction progress and good overall performance of concrete.
采用整体移动式模板支架用于生产后使施工效率快速提升,缩减施工工期,降低施工成本,减少了人工投入,减弱了复杂工序,有效提高施工效益。该段模板支架体系搭设长度为8米,70米衬砌施工共需完成9模混凝土浇筑。如此,经第一模混凝土浇筑实际测算,采用常规门型架配合脚手架支撑体系,单循环拆除并重新搭设钢管架需100个工日,该模板支架体系的优化,使每个施工循环过程省去拆除、搭设钢管架的工序,如此整个人防改造段衬砌可节约800个工日,同时工期提前80d,极大地节省机械设备、材料的投入,节约人工费和钢管扣件的租赁费。总的来说,省工省时、节约工期,节省成本,质量还得到保证,取得了良好的经济效益。 The overall mobile formwork support is used for production to rapidly improve the construction efficiency, shorten the construction period, reduce the construction cost, reduce the labor input, weaken the complex process, and effectively improve the construction efficiency. The length of the formwork support system in this section is 8 meters, and a total of 9 molds of concrete need to be poured for the 70-meter lining construction. In this way, based on the actual measurement and calculation of the first mold concrete pouring, it takes 100 working days to dismantle and re-erect the steel pipe frame in a single cycle by using the conventional portal frame with the scaffold support system. The optimization of the formwork support system saves each construction cycle process The process of dismantling and erecting the steel pipe frame can save 800 man-days for the lining of the entire civil air defense reconstruction section, and at the same time, the construction period is advanced by 80 days, which greatly saves the investment in mechanical equipment and materials, and saves labor costs and rental fees for steel pipe fasteners. In general, it saves labor and time, saves construction period, saves cost, and the quality is guaranteed, and good economic benefits have been achieved.
如上所述,尽管参照特定的优选实施例已经表示和表述了本实用新型,但其不得解释为对本实用新型自身的限制。在不脱离所附权利要求定义的本实用新型的精神和范围前提下,可对其在形式上和细节上作出各种变化。 As stated above, although the invention has been shown and described with reference to certain preferred embodiments, this should not be construed as limiting the invention itself. Various changes in form and details may be made therein without departing from the spirit and scope of the invention as defined by the appended claims.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520553496.5U CN204851287U (en) | 2015-07-28 | 2015-07-28 | Big section moving as a whole formula formwork support |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520553496.5U CN204851287U (en) | 2015-07-28 | 2015-07-28 | Big section moving as a whole formula formwork support |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204851287U true CN204851287U (en) | 2015-12-09 |
Family
ID=54741845
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201520553496.5U Expired - Fee Related CN204851287U (en) | 2015-07-28 | 2015-07-28 | Big section moving as a whole formula formwork support |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204851287U (en) |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107725074A (en) * | 2017-11-08 | 2018-02-23 | 中国水利水电第四工程局有限公司 | A kind of constructing tunnel Moveable support structure |
| CN109538242A (en) * | 2018-10-23 | 2019-03-29 | 中建局集团第建筑有限公司 | Building method of tunnel construction formwork support |
| CN111927496A (en) * | 2020-07-15 | 2020-11-13 | 中交第一航务工程局有限公司 | Integral rapid transfer system of support and template system and construction method |
| CN112458936A (en) * | 2020-11-30 | 2021-03-09 | 中铁十六局集团地铁工程有限公司 | Construction method for integrally translating box culvert full-hall support |
| CN114396295A (en) * | 2021-11-01 | 2022-04-26 | 中铁二局集团有限公司 | Secondary lining construction method for lower anchor section of railway tunnel |
| CN115653285A (en) * | 2022-10-31 | 2023-01-31 | 中建海峡建设发展有限公司 | Template support pre-assembly translation structure and working method thereof |
-
2015
- 2015-07-28 CN CN201520553496.5U patent/CN204851287U/en not_active Expired - Fee Related
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107725074A (en) * | 2017-11-08 | 2018-02-23 | 中国水利水电第四工程局有限公司 | A kind of constructing tunnel Moveable support structure |
| CN109538242A (en) * | 2018-10-23 | 2019-03-29 | 中建局集团第建筑有限公司 | Building method of tunnel construction formwork support |
| CN109538242B (en) * | 2018-10-23 | 2020-09-29 | 中建一局集团第一建筑有限公司 | A kind of construction method of tunnel construction formwork support |
| CN111927496A (en) * | 2020-07-15 | 2020-11-13 | 中交第一航务工程局有限公司 | Integral rapid transfer system of support and template system and construction method |
| CN112458936A (en) * | 2020-11-30 | 2021-03-09 | 中铁十六局集团地铁工程有限公司 | Construction method for integrally translating box culvert full-hall support |
| CN114396295A (en) * | 2021-11-01 | 2022-04-26 | 中铁二局集团有限公司 | Secondary lining construction method for lower anchor section of railway tunnel |
| CN114396295B (en) * | 2021-11-01 | 2023-12-12 | 中铁二局集团有限公司 | A kind of secondary lining construction method for the lower anchor section of railway tunnel |
| CN115653285A (en) * | 2022-10-31 | 2023-01-31 | 中建海峡建设发展有限公司 | Template support pre-assembly translation structure and working method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN111271092B (en) | A rapid construction structure and method for secondary lining of a dark-excavated tunnel with multiple variable cross-sections | |
| CN204851287U (en) | Big section moving as a whole formula formwork support | |
| CN113235472B (en) | Concrete placement platform truck is contained to apron | |
| CN100587165C (en) | Construction method of in-situ cast-in-place beams for fabricated supports | |
| CN106089253B (en) | A kind of all-hydraulic template system poured for culvert | |
| CN105803947B (en) | A kind of cast-in-situ box girder gate-type full framing whole lateral moving system and method for traversing | |
| CN111424570A (en) | Assembly type trolley for box culvert construction and construction method thereof | |
| CN204151823U (en) | Along building the one-sided cantilever hydraulic template trolley of side wall under covered back-digging structural slab | |
| CN205805577U (en) | A kind of arch wall type open cut tunnel chassis | |
| CN205935643U (en) | Outer wall is from climbing die carrier | |
| CN208203298U (en) | A kind of big punching block of rail type side wall | |
| CN105568854A (en) | Construction method of overwater curved fish-bellied cast-in-place reinforced concrete box girder | |
| CN111809660A (en) | Rectangular trolley for integrated pipe gallery and construction method | |
| CN107460889A (en) | Integral mobile support formwork and its construction method in the construction of underground comprehensive pipe gallery | |
| CN108252504A (en) | Tube shear wall concrete structure large form hoisting type construction method and constructing device | |
| CN214993219U (en) | Concrete placement platform truck is contained to apron | |
| CN106013783A (en) | Formwork support and erecting method thereof | |
| CN213510645U (en) | PBA secretly digs platform truck support template system that station side span was just propped up and is encircleed | |
| CN204386615U (en) | A self-propelled tunnel inverted arch construction trolley | |
| CN115418983B (en) | Construction method of prefabricated box culverts in large-section shield tunnels jointly built by highway and railway | |
| CN112458936A (en) | Construction method for integrally translating box culvert full-hall support | |
| CN114737599B (en) | Construction method of fine stone concrete filled block stone retaining wall | |
| CN107386119A (en) | A kind of variable cross-section beam sections type variable framework of steel reinforcement construction moulding bed device | |
| CN222990595U (en) | Multifunctional portal for suspension bridge construction | |
| CN110184915A (en) | The cast-in-place king-post of cable-stayed bridge and its construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20151209 |