CN212612627U - Utility tunnel rectangle platform truck - Google Patents

Utility tunnel rectangle platform truck Download PDF

Info

Publication number
CN212612627U
CN212612627U CN202021284250.XU CN202021284250U CN212612627U CN 212612627 U CN212612627 U CN 212612627U CN 202021284250 U CN202021284250 U CN 202021284250U CN 212612627 U CN212612627 U CN 212612627U
Authority
CN
China
Prior art keywords
utility tunnel
utility
template
supporting structure
crossbeam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021284250.XU
Other languages
Chinese (zh)
Inventor
戴兴民
张庆华
王丙仲
喻洋
崔鸿鹏
邱立光
贠宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 16th Bureau Group Co Ltd
Metro Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Original Assignee
China Railway 16th Bureau Group Co Ltd
Metro Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 16th Bureau Group Co Ltd, Metro Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd filed Critical China Railway 16th Bureau Group Co Ltd
Priority to CN202021284250.XU priority Critical patent/CN212612627U/en
Application granted granted Critical
Publication of CN212612627U publication Critical patent/CN212612627U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a utility tunnel rectangle trolley, this utility tunnel rectangle trolley includes internal supporting structure, the top of internal supporting structure is connected with the crossbeam through the bolt, the both sides of internal supporting structure are connected with the stand through hydraulic telescoping system respectively, the both ends of crossbeam are articulated with the top of stand respectively, the bottom of internal supporting structure is connected with hydraulic lifting system, traveling system, hydraulic lifting system is located the both sides of traveling system; the top of crossbeam is equipped with the top template, the outside of stand is equipped with the side wall template. The utility model discloses a utility tunnel rectangle platform truck relies on the template through inside bearing structure, adopts hydraulic pressure operating system, and the traveling system that unites has realized the two lining of undercut utility tunnel and has under construction fast, have efficient, assemble fast, the safe risk is low, easy operation, easy control, construction quality, precision are high, dismouting, transport manual consumption are low, advantage such as with low costs.

Description

Utility tunnel rectangle platform truck
Technical Field
The utility model relates to an underground excavation utility tunnel two-lining construction technical field particularly, relates to a utility tunnel rectangle platform truck.
Background
With the development of underground space in China and the continuous deep research on urban underground comprehensive pipe galleries at home and abroad, the construction of the comprehensive pipe gallery is comprehensively planned and implemented in urban construction, and the comprehensive pipe gallery is an important infrastructure for guaranteeing urban operation. Because the utility tunnel is not suitable for being built by stages, the engineering quantity is large, the one-time investment cost is too high, particularly, when the urban area is built, the open cut construction can interfere the ground traffic and the removal of the buildings, the engineering difficulty is large, and the cost is high.
The traditional pipe gallery two-lining construction method mainly adopts open cut cast-in-place, the cross section is mostly square, a bottom plate is poured firstly, then an inner mold support is erected, at present, a full-hall support is mainly adopted, after steel bars are bound, an outer mold is reinforced, and side walls and a top plate are poured at one time.
The traditional pipe gallery second lining construction method has the following defects: 1) the loss of the template and the batten is large, and the turnover frequency is low; 2) the field operation amount is large, the turnover workload of materials in a flowing water section is large, and the labor force demand is high; 3) the mechanization degree is low, and the construction period is long; 4) the difficulty of quality control is high; 5) a large amount of square timbers and templates are stacked on site, and the safety risk is high.
SUMMERY OF THE UTILITY MODEL
To the above-mentioned technical problem among the correlation technique, the utility model provides a utility tunnel rectangle platform truck can overcome prior art's the aforesaid not enough.
In order to achieve the technical purpose, the technical scheme of the utility model is realized as follows:
a comprehensive pipe gallery rectangular trolley comprises an internal supporting structure, wherein the top of the internal supporting structure is connected with a cross beam through a bolt, two sides of the internal supporting structure are respectively connected with an upright post through a hydraulic telescopic system, two ends of the cross beam are respectively hinged with the top end of the upright post, the bottom of the internal supporting structure is connected with a hydraulic lifting system and a traveling system, and the hydraulic lifting system is positioned on two sides of the traveling system; the top of crossbeam is equipped with the top template, the outside of stand is equipped with the side wall template.
Furthermore, two ends of the hydraulic telescopic system are respectively movably connected with two sides of the internal supporting structure and the inner side of the upright post.
Further, the internal support structure is square.
Further, a corner support is arranged in the inner supporting structure.
Furthermore, the walking system is the walking wheels which are symmetrically distributed at the bottom of the internal supporting structure.
The utility model has the advantages that: the utility model discloses a utility tunnel rectangle platform truck supports the template through inside bearing structure, adopts hydraulic pressure operating system, and the combined traveling system has realized that the two linings of undercut utility tunnel are under construction fast, has efficient, assemble fast, safe risk low, easy operation, easy control, construction quality, precision are high, dismouting, transport the artifical consumption low, advantage such as with low costs; the utility model discloses a utility tunnel rectangle platform truck flexible operation is convenient, the walking freely, the bulk rigidity is good, and the traveling system who sets up through the bottom makes the platform truck walking more convenient, when same section construction, can wholly remove, template and platform truck when can practicing thrift adjacent section tunnel construction in a large number are repeatedly assembled.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required to be used in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic plan view of a running rail and a rectangular trolley for a comprehensive pipe rack according to an embodiment of the present invention;
fig. 2 is a schematic plan view of a utility tunnel rectangular trolley according to an embodiment of the present invention along the track direction;
fig. 3 is a schematic plan view of an enlarged section of a rectangular trolley for a comprehensive pipe rack according to an embodiment of the present invention;
in the figure: 1. internal support structure, 2, crossbeam, 3, hydraulic telescoping system, 4, stand, 5, hydraulic lifting system, 6, traveling system, 7, top template, 8, side wall template, 9, angle brace.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art all belong to the protection scope of the present invention.
As shown in fig. 1-3, according to the embodiment of the present invention, the utility model provides a utility tunnel rectangular trolley, including an internal supporting structure 1, the top of the internal supporting structure 1 is connected with a cross beam 2 through a bolt, both sides of the internal supporting structure 1 are respectively connected with a column 4 through a hydraulic telescopic system 3, both ends of the cross beam 2 are respectively hinged with the top end of the column 4, the bottom of the internal supporting structure 1 is connected with a hydraulic lifting system 5 and a traveling system 6, the hydraulic lifting system 5 is located both sides of the traveling system 6; the top of crossbeam 2 is equipped with top template 7, the outside of stand 4 is equipped with side wall template 8. The two ends of the hydraulic telescopic system 3 are respectively movably connected with the two sides of the internal supporting structure 1 and the inner sides of the stand columns 4, the internal supporting structure 1 is square, and corner supports 9 are arranged in the internal supporting structure 1. The walking system 6 is walking wheels symmetrically distributed at the bottom of the internal supporting structure 1.
The construction method of the rectangular trolley for the comprehensive pipe rack comprises the following steps:
s1, paving the walking tracks, after the concrete of the bottom plate of the comprehensive pipe gallery is poured in advance and reaches the design strength, measuring, paying off and positioning the concrete surface, paving the walking tracks on the concrete of the bottom plate, wherein the walking tracks are smooth and straight and are firmly installed, and the distance is just matched with the trolley walking system, as shown in figure 1. The bottom of the two sides of the trolley is provided with 4 walking wheels which are symmetrically arranged below the bottom longitudinal beam of the single-section trolley. The diameter of the walking wheel is 300, and the walking track is a light rail of 38 kg/m.
S2, assembling a rectangular trolley of the comprehensive pipe gallery in the hole, wherein the internal supporting structure of the trolley adopts a 22a I-shaped steel square structure, two corner supports and one butt support are used in the middle of the trolley, and channel steel is longitudinally adopted for reinforcing connection. The template frame body is supported by 22a I-steel, consists of a cross beam and two upright posts and is connected by an oval hinge. The crossbeam directly adopts bolted connection with inside to support, uses hydraulic telescoping system to contact between stand and the inside bearing structure, and swing joint is adopted at hydraulic telescoping system both ends. After the trolley main truss is installed, debugging before use is carried out, wherein the debugging comprises walking, hydraulic pressure, a screw rod piece, inner side template folding and unfolding and top die lifting system overall debugging.
S3, positioning the rectangular trolley of the comprehensive pipe gallery, and moving the trolley to the designed position along the rail after the side wall and the top plate steel bars are bound. Adjusting a screw rod and a braking device at the bottom of the trolley, locking a walking wheel, painting template paint, starting a hydraulic lifting system (a hydraulic pump supporting system), lifting the whole trolley, and determining the elevation and the central position of the template by matching with measuring personnel. If the elevation and the center line position have deviation, the hydraulic system is used for local adjustment. The plug template adopts a 50mm thick wood pattern, and is matched with the distribution ribs to be fixed firmly. The control is mainly as follows: the trolley is lifted synchronously and symmetrically, and the positions of the top template and the side die are matched with the measurement and accurate positioning. Note that: the plug die is firmly reinforced to prevent the die from expanding due to overlarge pressure during concrete pouring.
S4, demolding the rectangular trolley of the comprehensive pipe gallery and advancing the trolley, finishing concrete pouring, and dismantling and advancing the template after curing for a certain time to reach a demolding condition. And (3) removing the internal screw rod mould jacking system, unlocking the protective device of the side wall combined steel template positioned at the hinge part, starting the hydraulic telescopic system (lateral hydraulic system), slowly withdrawing the oil cylinder, and slowly putting down the side wall steel template under the driving of the hinge. And (5) similarly, the top screw rod die ejecting system is disassembled, a hydraulic lifting system (a die ejecting hydraulic system) is started, and the top die is lowered. And after all the trolley is recovered, checking whether the inner side mould and the outer side mould are separated from the concrete wall, dismantling all the opposite tension rod rods and separating the top mould from the top plate, checking whether barriers such as materials for blocking the trolley to advance exist around the trolley, starting a traveling system after cleaning is finished, and slowly moving the trolley to the next construction working face.
In conclusion, by means of the technical scheme of the utility model, the quick construction of the second lining of the underground excavation comprehensive pipe gallery is realized by the internal supporting structure depending on the template, the hydraulic lifting system and the combined walking system; the utility model has the advantages of flexible and convenient operation, free walking, good integral rigidity, integral movement during the construction of the same section, and repeated assembly of templates and trolleys during the construction of adjacent sections of tunnels; when carrying out the template and setting up and demolising, adopt hydraulic cylinder's flexible control template position, it is comparatively easy in the adjustment process, during concrete placement, adopt screw rod as the template support, also can assemble fast in heterotypic section, increase the connecting rod utensil and reduce heterotypic section material cost under the cooperation of telescopic joint.
The above description is only a preferred embodiment of the present invention, and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (5)

1. The utility model provides a utility tunnel rectangle platform truck, characterized in that, includes internal support structure (1), the top of internal support structure (1) is passed through the bolt and is connected with crossbeam (2), the both sides of internal support structure (1) are connected with stand (4) through hydraulic telescoping system (3) respectively, the both ends of crossbeam (2) are articulated with the top of stand (4) respectively, the bottom of internal support structure (1) is connected with hydraulic lifting system (5), traveling system (6), hydraulic lifting system (5) are located the both sides of traveling system (6); the top of crossbeam (2) is equipped with top template (7), the outside of stand (4) is equipped with side wall template (8).
2. The utility tunnel rectangular trolley according to claim 1, characterized in that the two ends of the hydraulic telescoping system (3) are movably connected with the two sides of the internal support structure (1) and the inner sides of the columns (4), respectively.
3. The utility tunnel rectangular trolley according to claim 1, characterized in that the internal support structure (1) is square.
4. Utility tunnel rectangular trolley according to claim 3, characterized in that inside the internal supporting structure (1) there are corner supports (9).
5. The utility tunnel rectangular trolley according to claim 1, characterized in that the walking system (6) is walking wheels symmetrically distributed at the bottom of the internal support structure (1).
CN202021284250.XU 2020-07-03 2020-07-03 Utility tunnel rectangle platform truck Active CN212612627U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021284250.XU CN212612627U (en) 2020-07-03 2020-07-03 Utility tunnel rectangle platform truck

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021284250.XU CN212612627U (en) 2020-07-03 2020-07-03 Utility tunnel rectangle platform truck

Publications (1)

Publication Number Publication Date
CN212612627U true CN212612627U (en) 2021-02-26

Family

ID=74757285

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021284250.XU Active CN212612627U (en) 2020-07-03 2020-07-03 Utility tunnel rectangle platform truck

Country Status (1)

Country Link
CN (1) CN212612627U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111809660A (en) * 2020-07-03 2020-10-23 中铁十六局集团地铁工程有限公司 Comprehensive pipe gallery rectangular trolley and construction method
CN114575586A (en) * 2022-03-10 2022-06-03 上海欧跃建筑安装工程有限公司 Quick support and quick release system and method for outer frame steel structure floor slab concrete casting template

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111809660A (en) * 2020-07-03 2020-10-23 中铁十六局集团地铁工程有限公司 Comprehensive pipe gallery rectangular trolley and construction method
CN114575586A (en) * 2022-03-10 2022-06-03 上海欧跃建筑安装工程有限公司 Quick support and quick release system and method for outer frame steel structure floor slab concrete casting template

Similar Documents

Publication Publication Date Title
CN109968499B (en) Special die for pouring T-shaped beam and application method thereof
CN109403374A (en) Factorial construction method for open trench tunnel integral tunnel lining
CN113235472B (en) Concrete placement platform truck is contained to apron
CN206092022U (en) Be used for lining cutting rectangular -section or radiation gradual change rectangular -section formula operation car of crawling
CN111809660A (en) Comprehensive pipe gallery rectangular trolley and construction method
CN110513125B (en) Inner and outer mould trolley lining system for open cut underdrain
CN111424570A (en) Assembly type trolley for box culvert construction and construction method thereof
CN107387122A (en) A kind of formwork jumbo and its construction method for the construction of piping lane tunneling boring
CN212612627U (en) Utility tunnel rectangle platform truck
CN102146796A (en) Construction technology for inverted arch of two-track tunnel of high-speed railway
CN111911194A (en) Multifunctional two-lining trolley construction equipment and method for long and wide tunnel
CN204851287U (en) Big section moving as a whole formula formwork support
CN112458936A (en) Construction method for integrally translating box culvert full-hall support
CN110468748B (en) Culvert trolley
CN114657884B (en) Construction method of descending movable formwork for bridge abutment assembly and sectional propulsion
CN110424722B (en) Integrally assembled large-formwork narrow space wall and construction method
CN210256640U (en) Dry dock sequence method full-section integral prefabricated immersed tube template system
CN216305944U (en) Template trolley system suitable for construction of small-section double-bin underground excavation tunnel lining
CN205936645U (en) A full liquid die plate system for culvert is pour
CN113356268A (en) Integrated movable type formwork system for comprehensive pipe rack
CN210564557U (en) Tunnel secondary lining form trolley
CN210370698U (en) Mould shifting trolley for shed tunnel lining arch construction
CN211547804U (en) Cantilever type retaining wall rapid construction device
CN219260758U (en) Trolley for cast-in-situ cover plate culvert wall construction
CN112160773A (en) Tunnel lining reinforcing steel bar trolley and lining reinforcing steel bar binding construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant