CN204850048U - Overlap joint structure of quick hoist and mount of supplementary high -rise girder steel - Google Patents
Overlap joint structure of quick hoist and mount of supplementary high -rise girder steel Download PDFInfo
- Publication number
- CN204850048U CN204850048U CN201520555679.0U CN201520555679U CN204850048U CN 204850048 U CN204850048 U CN 204850048U CN 201520555679 U CN201520555679 U CN 201520555679U CN 204850048 U CN204850048 U CN 204850048U
- Authority
- CN
- China
- Prior art keywords
- steel
- cantilever beam
- cantilever
- upper flange
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本实用新型公开了一种辅助高层钢梁快速吊装的搭接结构,对于在第一钢柱和第二钢柱之间架设钢梁的结构形式,其特征是:在第一钢柱和第二钢柱的侧壁上分别焊接第一挑梁和第二挑梁,钢梁是以钢梁第一端与第一挑梁对接并在腹板上利用连接板实施螺栓固定,以钢梁第二端与第二挑梁对接并在腹板上利用连接板实施螺栓固定;在钢梁与第一挑梁的对接位置处,在钢梁上翼缘板上焊接第一过渡板,以第一过渡板搭在第一挑梁上翼缘板上,以第一挑梁上翼缘板通过第一过渡板对钢梁形成临时支撑,相同的结构形式在钢梁与第二挑梁的对接位置处同样设置。本实用新型可有效提高吊装设备的利用率,加快施工进度,保证工程质量。
The utility model discloses a lap joint structure for assisting high-rise steel beams to be quickly hoisted. For the structural form of erecting steel beams between the first steel column and the second steel column, the feature is that: the first steel column and the second steel column The first cantilever beam and the second cantilever beam are respectively welded on the side wall of the steel column. The first end of the steel beam is connected to the first cantilever beam, and the connecting plate is used to implement bolts on the web. The end is butted with the second cantilever beam, and the connecting plate is used to implement bolts on the web; at the butt joint position between the steel beam and the first cantilever beam, the first transition plate is welded on the upper flange of the steel beam, and the first transition plate On the upper flange plate of the first cantilever beam, the steel beam is temporarily supported by the upper flange plate of the first cantilever beam through the first transition plate, and the same structural form is also set at the joint position of the steel beam and the second cantilever beam. The utility model can effectively improve the utilization rate of the hoisting equipment, speed up the construction progress and ensure the project quality.
Description
技术领域technical field
本实用新型涉及辅助高层钢梁快速吊装的搭接结构。The utility model relates to a lap joint structure for assisting the rapid hoisting of high-rise steel girders.
背景技术Background technique
高层钢结构以其连接方式简单快捷被大量采用和复制;但是往往在施工中又不得不面对楼层横七竖八的钢结构梁,如果不采取有效的施工方法,将会给施工造成大量的人工和机械的损耗,增加施工成本,还具有安装过程中的安全隐患。High-rise steel structures are widely adopted and replicated because of their simple and fast connection methods; however, they often have to face the steel structure beams on the floors during construction. If effective construction methods are not adopted, it will cause a lot of labor and machinery for the construction. The loss of the installation increases the construction cost and also has potential safety hazards during the installation process.
现有技术中,当吊装一榀钢梁时,机械在没有安装完成钢梁与钢牛腿对接时,是不能脱钩另行作业的,只能等待操作人员安装所有螺栓才能吊装下一榀钢梁,因此,对于高层钢结构梁的吊装以及其安装过程费工费时,给机械作业带来很大负担,在很大程度上浪费机械台班资源。In the prior art, when hoisting a steel girder, the machine cannot be unhooked before the butt joint between the steel girder and the steel corbel is installed, and the next steel girder can be hoisted only after the operator installs all the bolts. Therefore, the hoisting of high-rise steel structure beams and its installation process are labor-intensive and time-consuming, which brings a great burden to mechanical operations and wastes mechanical shift resources to a large extent.
实用新型内容Utility model content
本实用新型是为避免上述现有技术存在的不足之处,提供一种辅助高层钢梁快速吊装的搭接结构,以使高层钢梁的吊装过程快捷、高效,保证施工质量,并提高吊装设备的流转过程,提高设备利用率The utility model is to avoid the shortcomings of the above-mentioned prior art, and provides a lap joint structure for assisting the rapid hoisting of high-rise steel girders, so that the hoisting process of high-rise steel girders is fast and efficient, the construction quality is guaranteed, and the hoisting equipment is improved. The circulation process, improve equipment utilization
本实用新型为解决技术问题采用如下技术方案:The utility model adopts following technical scheme for solving technical problems:
本实用新型辅助高层钢梁快速吊装的搭接结构,对于在第一钢柱和第二钢柱之间架设钢梁的结构形式,本实用新型的结构特点是:在第二钢柱的侧壁上焊接第一挑梁,在第二钢柱的侧壁上焊接第二挑梁,所述钢梁是以钢梁第一端与第一挑梁对接,以钢梁第二端与第二挑梁对接;在所述钢梁与第一挑梁的对接位置处、在钢梁上翼缘板上焊接第一过渡板,并以所述第一过渡板搭在第一挑梁上翼缘板上,以所述第一挑梁上翼缘板通过第一过渡板对钢梁形成临时支撑;在所述钢梁与第二挑梁的对接位置处、在钢梁上翼缘板上焊接有第二过渡板,并以第二过渡板搭在第二挑梁上翼缘板上,以所述第二挑梁上翼缘板通过第二过渡板对钢梁形成临时支撑。The utility model assists the fast hoisting of high-rise steel beams. For the structural form of erecting steel beams between the first steel column and the second steel column, the structural characteristics of the utility model are: the side wall of the second steel column The first cantilever is welded on the top, and the second cantilever is welded on the side wall of the second steel column. The steel beam is connected with the first cantilever by the first end of the steel beam, and the second cantilever is connected by the second end of the steel beam. Beam docking; at the butt joint position between the steel beam and the first cantilever beam, the first transition plate is welded on the upper flange plate of the steel beam, and the first transition plate is placed on the upper flange plate of the first cantilever beam, so that The upper flange plate of the first cantilever beam forms a temporary support for the steel beam through the first transition plate; at the butt joint position of the steel beam and the second cantilever beam, a second transition plate is welded on the upper flange plate of the steel beam, and the second transition plate is welded with the first transition plate The second transition plate is placed on the upper flange plate of the second cantilever beam, and the upper flange plate of the second cantilever beam forms a temporary support for the steel beam through the second transition plate.
本实用新型辅助高层钢梁快速吊装的搭接结构的特点也在于:所述钢梁第一端与第一挑梁之间的对接,以及钢梁第二端与第二挑梁之间的对接都是在腹板上利用连接板实施螺栓固定连接。The feature of the lap joint structure of the utility model for assisting the fast hoisting of high-rise steel girders also lies in: the butt joint between the first end of the steel girder and the first cantilever, and the butt joint between the second end of the steel girder and the second cantilever All are bolted connections on the web using connecting plates.
与已有技术相比,本实用新型有益效果体现在:Compared with the prior art, the beneficial effects of the utility model are reflected in:
本实用新型通过设置第一过渡板和第二过渡板,实现了由第一挑梁和第二挑梁对钢梁的临时支撑,因而使得吊装设备可以提前退出,可极大地提高吊装设备的利用率,加快施工进度,保证工程质量。The utility model realizes the temporary support of the steel beam by the first and second cantilever beams by setting the first transition plate and the second transition plate, so that the hoisting equipment can be withdrawn in advance, and the utilization of the hoisting equipment can be greatly improved rate, speed up the construction progress, and ensure the quality of the project.
附图说明Description of drawings
图1为本实用新型结构示意图;Fig. 1 is the structural representation of the utility model;
图2为本实用新型钢梁及过渡板示意图;Fig. 2 is the utility model steel girder and transition plate schematic diagram;
图3为本实用新型中钢梁及第一过渡板结构示意图;Fig. 3 is the structure schematic diagram of steel beam and the first transition plate in the utility model;
图中标号:1第一钢柱;2第二钢柱;3第一挑梁;4第二挑梁;5钢梁;6第一挑梁上翼缘板;7第二挑梁上翼缘板;8第一过渡板;9钢梁上翼缘板;10第二过渡板;11连接板。具体实施方式Symbols in the figure: 1 first steel column; 2 second steel column; 3 first cantilever beam; 4 second cantilever beam; 5 steel beam; 6 first cantilever beam upper flange plate; 1 transition plate; 9 steel beam upper flange plate; 10 second transition plate; 11 connecting plate. Detailed ways
参见图1、图2和图3,本实施例中辅助高层钢梁快速吊装的搭接结构是对于在第一钢柱1和第二钢柱2之间架设钢梁5的结构形式,在第二钢柱2的侧壁上焊接第一挑梁3,在第二钢柱2的侧壁上焊接第二挑梁4,所述钢梁5是以钢梁第一端与第一挑梁3对接,以钢梁第二端与第二挑梁4对接;在所述钢梁5与第一挑梁3的对接位置处、在钢梁上翼缘板9上焊接第一过渡板8,并以所述第一过渡板8搭在第一挑梁上翼缘板6上,以所述第一挑梁上翼缘板6通过第一过渡板8对钢梁5形成临时支撑;在所述钢梁5与第二挑梁4的对接位置处、在钢梁上翼缘板9上焊接有第二过渡板10,并以第二过渡板10搭在第二挑梁上翼缘板7上,以所述第二挑梁上翼缘板7通过第二过渡板10对钢梁5形成临时支撑。Referring to Fig. 1, Fig. 2 and Fig. 3, the overlapping structure of auxiliary high-rise steel girder fast hoisting in the present embodiment is for the structural form of erecting steel girder 5 between the first steel column 1 and the second steel column 2, in the The first cantilever 3 is welded on the side wall of the second steel column 2, and the second cantilever 4 is welded on the side wall of the second steel column 2. The steel beam 5 is based on the first end of the steel beam and the first cantilever 3 Docking, with the second end of the steel beam docked with the second cantilever beam 4; at the butt joint position of the steel beam 5 and the first cantilever beam 3, weld the first transition plate 8 on the steel beam upper flange plate 9, and use the Said first transition plate 8 rides on the first cantilever beam upper flange plate 6, forms temporary support to steel beam 5 with said first cantilever beam upper flange plate 6 through first transition plate 8; Between said steel beam 5 and the second At the butt joint position of the cantilever beam 4, a second transition plate 10 is welded on the steel beam upper flange plate 9, and the second transition plate 10 is placed on the second cantilever beam upper flange plate 7, and the second cantilever beam upper flange plate 7 Form a temporary support for the steel beam 5 through the second transition plate 10.
具体实施中,钢梁第一端与第一挑梁3之间的对接,以及钢梁第二端与第二挑梁4之间的对接都是在腹板上利用连接板11实施螺栓固定连接。In specific implementation, the butt joint between the first end of the steel beam and the first cantilever beam 3, and the butt joint between the second end of the steel beam and the second cantilever beam 4 are all implemented on the web by using the connecting plate 11 to implement bolted connection .
以本实施例中的搭接结构实施高层钢梁快速安装的方法是按如下过程进行:The method for fast installation of high-rise steel girders with the lap joint structure in this embodiment is carried out as follows:
首先,利用吊装设备将钢梁5就位在第一挑梁3和第二挑梁4之间,并且使第一过渡板8处在第一挑梁上翼缘板6的上方,使第二过渡板10处在第二挑梁上翼缘板7的上方。First, the steel girder 5 is positioned between the first joist beam 3 and the second joist beam 4 by means of hoisting equipment, and the first transition plate 8 is placed above the upper flange plate 6 of the first joist beam, so that the second transition plate 10 is above the upper flange plate 7 of the second cantilever.
然后,将第一过渡板8搭在第一挑梁上翼缘板6上,并将第二过渡板10搭在第二挑梁上翼缘板7上,由第一挑梁3和第二挑梁4通过第一过渡板8和第二过渡板10对钢梁5进行临时支撑;在钢梁5获得临时支撑后,吊装设备即退出。Then, put the first transition plate 8 on the upper flange plate 6 of the first cantilever beam, and put the second transition plate 10 on the upper flange plate 7 of the second cantilever beam, and pass through the first cantilever beam 3 and the second cantilever beam 4 The first transition plate 8 and the second transition plate 10 temporarily support the steel beam 5; after the steel beam 5 obtains the temporary support, the hoisting equipment exits.
最后,将钢梁5在两端分别与第一挑梁3和第二挑梁4通过腹板上的螺栓孔实施螺栓固定,完成施工。Finally, the two ends of the steel beam 5 are respectively bolted to the first cantilever beam 3 and the second cantilever beam 4 through the bolt holes on the web plate to complete the construction.
具体实施中,为了在钢梁5与第一挑梁3以及第二挑梁4之间实施螺栓固定,需要在钢梁5、第一挑梁3以及第二挑梁4的端部腹板上预制螺栓孔,为光孔。In the specific implementation, in order to implement bolt fixing between the steel beam 5 and the first cantilever beam 3 and the second cantilever beam 4, it is necessary to install Prefabricated bolt holes are light holes.
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520555679.0U CN204850048U (en) | 2015-07-24 | 2015-07-24 | Overlap joint structure of quick hoist and mount of supplementary high -rise girder steel |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520555679.0U CN204850048U (en) | 2015-07-24 | 2015-07-24 | Overlap joint structure of quick hoist and mount of supplementary high -rise girder steel |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204850048U true CN204850048U (en) | 2015-12-09 |
Family
ID=54740614
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201520555679.0U Expired - Lifetime CN204850048U (en) | 2015-07-24 | 2015-07-24 | Overlap joint structure of quick hoist and mount of supplementary high -rise girder steel |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204850048U (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105019556A (en) * | 2015-07-24 | 2015-11-04 | 安徽富煌钢构股份有限公司 | Lap-joint structure assisting quick hoisting of high-rise steel beam, and application of lap-joint structure |
| CN106013418A (en) * | 2016-06-09 | 2016-10-12 | 毛强平 | A construction method and building structure for connecting platforms between adjacent high-rise buildings |
| CN114439115A (en) * | 2020-11-06 | 2022-05-06 | 宁波建工工程集团有限公司 | Steel frame beam column connecting structure and connecting method thereof |
-
2015
- 2015-07-24 CN CN201520555679.0U patent/CN204850048U/en not_active Expired - Lifetime
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105019556A (en) * | 2015-07-24 | 2015-11-04 | 安徽富煌钢构股份有限公司 | Lap-joint structure assisting quick hoisting of high-rise steel beam, and application of lap-joint structure |
| CN106013418A (en) * | 2016-06-09 | 2016-10-12 | 毛强平 | A construction method and building structure for connecting platforms between adjacent high-rise buildings |
| CN106013418B (en) * | 2016-06-09 | 2018-06-26 | 江苏美城建筑规划设计院有限公司 | A construction method and building structure for connecting platforms between adjacent high-rise buildings |
| CN114439115A (en) * | 2020-11-06 | 2022-05-06 | 宁波建工工程集团有限公司 | Steel frame beam column connecting structure and connecting method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| WO2022062294A1 (en) | Suspension connection node for large-span cantilever steel truss and construction method therefor | |
| CN101100902A (en) | Diagonal steel truss high-formwork structural system and construction method thereof | |
| CN104358207A (en) | Rapid steel trestle construction structure and construction method | |
| CN204899180U (en) | Steel construction jar body aerial working platform simply sets up device | |
| CN104060542B (en) | Compound beam cable stayed bridge direction across bridge prestress application device and applying method thereof | |
| CN102518300A (en) | Embedded conical bearing joint type steel structure support and construction method thereof | |
| CN204850048U (en) | Overlap joint structure of quick hoist and mount of supplementary high -rise girder steel | |
| CN100504031C (en) | Steel cage hoisting structure in tank wall construction | |
| CN211733582U (en) | Wet seam template dismouting system of shifting | |
| CN202416191U (en) | Lifting device of main girder for offshore demolition of downward mobile formwork | |
| CN205636498U (en) | Wet seam construction equipment | |
| CN201991226U (en) | Flange template support structure | |
| CN104924419B (en) | Automatic template opening/closing system for construction of large-volume precast concrete component | |
| CN103993739A (en) | Method for constructing stiff beam of spraying layer of prilling tower | |
| CN210025768U (en) | A operation platform system for caisson template installation | |
| CN106320681A (en) | Elevator shaft standard operation platform and implementation platform | |
| CN205224045U (en) | Examine and repair gate slot second phase concrete construction device | |
| CN104131635A (en) | Method and platform for constructing peripheral shear wall of prefabricated staircase | |
| CN204959933U (en) | Upper and lower diplopore concrete circulating pipe ditch template | |
| CN203361642U (en) | Cast-in-place stair steel formwork of assembled structure | |
| CN102605945B (en) | Manufacturing method of big wood formwork | |
| CN107060173B (en) | Construction Method of Early Formwork Removal in the Structural Hole of Fair-faced Concrete Waffle Slab | |
| CN215289748U (en) | T roof beam transverse connection board seam construction equipment | |
| CN204225503U (en) | Large span steel truss high altitude bulk conversion beam moulding bed | |
| CN205132926U (en) | Special well word hoist of hydroelectric set tail water ell |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CX01 | Expiry of patent term | ||
| CX01 | Expiry of patent term |
Granted publication date: 20151209 |