CN204781961U - Accurate positioner of high -rise floor buried sleeve - Google Patents

Accurate positioner of high -rise floor buried sleeve Download PDF

Info

Publication number
CN204781961U
CN204781961U CN201520462189.6U CN201520462189U CN204781961U CN 204781961 U CN204781961 U CN 204781961U CN 201520462189 U CN201520462189 U CN 201520462189U CN 204781961 U CN204781961 U CN 204781961U
Authority
CN
China
Prior art keywords
infrared ray
floor
lower floor
buried sleeve
upper strata
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520462189.6U
Other languages
Chinese (zh)
Inventor
郭玉峰
贾高莲
王江平
刘继军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi First Construction Group Co Ltd
Original Assignee
Shanxi First Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi First Construction Group Co Ltd filed Critical Shanxi First Construction Group Co Ltd
Priority to CN201520462189.6U priority Critical patent/CN204781961U/en
Application granted granted Critical
Publication of CN204781961U publication Critical patent/CN204781961U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility mode relates to an accurate positioner of high -rise floor buried sleeve, the phenomenon leads to the fact the problem that intensity of labour is big, with high costs and the efficiency of construction is lower because the inaccurate existence in location easily takes place to do over again to have solved the installation of present buried sleeve. Including lower floor's floor and upper slab form, be provided with the buried sleeve of lower floor on lower floor's floor, be provided with on the buried sleeve of lower floor rather than endocentric laser mark target, it has the infrared ray hole to open on the slab form of upper strata, and the infrared ray hole coats is stamped the guiding orientation board, the cover has upper buried sleeve on the guiding orientation board, be provided with the marking appearance on the laser mark target, the downward infrared ray point of intersect of marking appearance is located the centre of a circle of laser mark target, the upwards infrared ray of marking appearance passes the infrared ray hole, and the upwards infrared ray point of intersect of marking appearance is located the guiding orientation board centre of a circle. The utility model discloses saved the process that the grout of the sleeve pipe outside was handled, do benefit to moreover waterproof, simultaneously can disposable accurate buried sleeve.

Description

High-rise floor service sleeve accurate positioning device
Technical field
The utility model relates to building operations positioner, is specially a kind of high-rise floor service sleeve accurate positioning device.
Background technology
When highrise building main body construction in the past, have the sleeve pipe of many pipelines to be all first reserving hole, during later installation pipeline, more again unwrapping wire, pick the mouth that holes, mounting sleeve and pipeline, outside of sleeve needs grouting treatment, is also unfavorable for waterproof.
If direct service sleeve during construction, locate inaccurate meeting and cause pipeline cannot wear bottom from top cross, also need to pick cutter concrete, reinstall sleeve pipe, existence is done over again, is picked the large phenomenon of cutter amount, and artificial input is also more.
Summary of the invention
The utility model is installed and is caused that labour intensity is large, cost is high and the problem that efficiency of construction is lower in order to solve pre existing bushing burying owing to locating inaccurate existence phenomenon of easily doing over again, and provides a kind of high-rise floor service sleeve accurate positioning device.
The utility model adopts following technical scheme to realize: high-rise floor service sleeve accurate positioning device, comprise lower floor's floor and upper strata slab form, lower floor's floor is provided with lower floor's service sleeve, lower floor's service sleeve is provided with concentric laser target, upper strata slab form has infrared ray hole, and infrared ray hole is coated with the guide positioning plate be supported on the slab form of upper strata, guide positioning plate overlaps to have and is mated and the upper strata service sleeve be placed on the slab form of upper strata, laser target is provided with frame for line marking instrument, the downward infrared rays intersection point of frame for line marking instrument is positioned at the center of circle of laser target, the upwards infrared rays of frame for line marking instrument is through infrared ray hole, and the upwards infrared rays intersection point of frame for line marking instrument is positioned at the guide positioning plate center of circle.
When positioning operation, first surveying setting-out, lower floor's service sleeve, laser target and frame for line marking instrument are laid in correct location, guide positioning plate is placed subsequently at infrared ray hole place, frame for line marking instrument infrared rays is upwards incident upon in guide positioning plate through infrared ray hole, after mobile guide location-plate overlaps to its center of circle with infrared rays intersection point, fix upper strata service sleeve by the position of guide positioning plate, overcome pre existing bushing burying and install and cause that labour intensity is large, cost is high and the problem that efficiency of construction is lower owing to locating inaccurate existence phenomenon of easily doing over again.
The diameter 2mm less of the internal diameter of upper strata service sleeve of guide positioning plate, this fit clearance is through that test of many times draws, while ensureing the vertical precision of service sleeve, is convenient to guide positioning plate and takes out smoothly in service sleeve.
The utility model reasonable in design is reliable, eliminates the operation of outside of sleeve grouting treatment, and is beneficial to waterproof, the disposable correct embedment sleeve pipe of energy, does not need to do over again, and then alleviates labour intensity simultaneously, improve efficiency of construction, there is simple, the easy to operate and advantage that cost is low of structure.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
In figure: 1-lower floor floor, 2-upper strata slab form, 3-lower floor service sleeve, 4-laser target, 5-infrared ray hole, 6-guide positioning plate, 7-upper strata service sleeve, 8-frame for line marking instrument.
Detailed description of the invention
High-rise floor service sleeve accurate positioning device, comprise lower floor's floor 1 and upper strata slab form 2, lower floor's floor 1 is provided with lower floor's service sleeve 3, lower floor's service sleeve 3 is provided with concentric laser target 4, upper strata slab form 2 has infrared ray hole 5, and infrared ray hole 5 is coated with the guide positioning plate 6 be supported on upper strata slab form 2, guide positioning plate 6 overlaps to have and is mated and the upper strata service sleeve 7 be placed on upper strata slab form 2, laser target 4 is provided with frame for line marking instrument 8, the downward infrared rays intersection point of frame for line marking instrument 8 is positioned at the center of circle of laser target 4, the upwards infrared rays of frame for line marking instrument 8 is through infrared ray hole 5, and the upwards infrared rays intersection point of frame for line marking instrument 8 is positioned at guide positioning plate 6 center of circle.
The diameter 2mm less of the internal diameter of upper strata service sleeve 7 of guide positioning plate 6.
In specific implementation process, the diameter of infrared ray hole 5 is 50mm.

Claims (2)

1. a high-rise floor service sleeve accurate positioning device, comprise lower floor's floor (1) and upper strata slab form (2), it is characterized in that: lower floor's floor (1) is provided with lower floor's service sleeve (3), lower floor's service sleeve (3) is provided with concentric laser target (4), upper strata slab form (2) has infrared ray hole (5), and infrared ray hole (5) is coated with the guide positioning plate (6) be supported on upper strata slab form (2), the upper cover of guide positioning plate (6) has and is mated and the upper strata service sleeve (7) be placed on upper strata slab form (2), laser target (4) is provided with frame for line marking instrument (8), the downward infrared rays intersection point of frame for line marking instrument (8) is positioned at the center of circle of laser target (4), the upwards infrared rays of frame for line marking instrument (8) is through infrared ray hole (5), and the upwards infrared rays intersection point of frame for line marking instrument (8) is positioned at guide positioning plate (6) center of circle.
2. high-rise floor service sleeve accurate positioning device according to claim 1, is characterized in that: the diameter 2mm less of the internal diameter of upper strata service sleeve (7) of guide positioning plate (6).
CN201520462189.6U 2015-07-01 2015-07-01 Accurate positioner of high -rise floor buried sleeve Active CN204781961U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520462189.6U CN204781961U (en) 2015-07-01 2015-07-01 Accurate positioner of high -rise floor buried sleeve

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520462189.6U CN204781961U (en) 2015-07-01 2015-07-01 Accurate positioner of high -rise floor buried sleeve

Publications (1)

Publication Number Publication Date
CN204781961U true CN204781961U (en) 2015-11-18

Family

ID=54522032

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520462189.6U Active CN204781961U (en) 2015-07-01 2015-07-01 Accurate positioner of high -rise floor buried sleeve

Country Status (1)

Country Link
CN (1) CN204781961U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113309369A (en) * 2021-06-29 2021-08-27 方泽华 Accurate positioning and mounting method for building structure embedded sleeve and sleeve assembly component
CN113531219A (en) * 2021-07-09 2021-10-22 安徽三建工程有限公司 Installation device and method for improving laying precision of embedded sleeve
CN116397904A (en) * 2023-06-08 2023-07-07 山西三建集团有限公司 Positioning method of positioning mechanism for reserved steel sleeve on cast-in-situ floor plate of high-rise building

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113309369A (en) * 2021-06-29 2021-08-27 方泽华 Accurate positioning and mounting method for building structure embedded sleeve and sleeve assembly component
CN113531219A (en) * 2021-07-09 2021-10-22 安徽三建工程有限公司 Installation device and method for improving laying precision of embedded sleeve
CN116397904A (en) * 2023-06-08 2023-07-07 山西三建集团有限公司 Positioning method of positioning mechanism for reserved steel sleeve on cast-in-situ floor plate of high-rise building
CN116397904B (en) * 2023-06-08 2023-08-08 山西三建集团有限公司 Positioning method of positioning mechanism for reserved steel sleeve on cast-in-situ floor plate of high-rise building

Similar Documents

Publication Publication Date Title
CN204781961U (en) Accurate positioner of high -rise floor buried sleeve
CN209066908U (en) A kind of positioning device for pre-buried floor sleeve
CN205917944U (en) Floor buried sleeve positioner
CN103913146B (en) The continuous operational monitoring station of GNSS
CN106638318B (en) The localization method and cable guide pipe installation method of cable-stayed bridge beam-ends anchor point
CN201902020U (en) Ultrared positioning embedded sleeve pipe die
CN204983657U (en) Floor buried sleeve positioner
CN202119352U (en) Multifunctional adjusting rack
CN201650319U (en) Angle installer for anchor bolt
CN216042637U (en) Embedded part for electric embedded pipe
CN205808417U (en) A kind of vertical detection device of building template
CN103196423B (en) The sedimentation ring accurately self-align for deep soil settlement survey system and using method thereof
CN103061454A (en) Locating method of installing concrete filled steel tubular column in underground deep hole
CN203594055U (en) Structure of basement guide wall waterproof concrete horizontal construction joint
CN206428768U (en) A kind of plumbing steel-pipe assembly sleeve pipe
CN101900553B (en) Laser level positioning control frame for digitized architectural mapping
CN210421921U (en) Auxiliary tool for installing and positioning riser sleeve
CN210636402U (en) Fixing structure for water supply pipeline of outlet shaft well wall of deep-buried underground powerhouse of hydropower station
CN104153372B (en) A kind of vertical support unit of foundation ditch doubles as bearing pile method
CN203684226U (en) Improved vertical control device for top-down steel pipe column
CN203160245U (en) Positioning device for temporary steel-pipe column pile
CN206346081U (en) 1 point of CP installation aiding device in a kind of tunnel of utilization injected hole
CN205300589U (en) Hydroelectric power plant's dam observation device
CN205745678U (en) The construction positioner of embedding pipe fittings
CN207047706U (en) A kind of pre-embedded device for improving anchor slab positioning precision

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant