CN204456065U - A kind of X-type freezing pipe - Google Patents

A kind of X-type freezing pipe Download PDF

Info

Publication number
CN204456065U
CN204456065U CN201520064490.1U CN201520064490U CN204456065U CN 204456065 U CN204456065 U CN 204456065U CN 201520064490 U CN201520064490 U CN 201520064490U CN 204456065 U CN204456065 U CN 204456065U
Authority
CN
China
Prior art keywords
pipe
freezing
construction
freezing pipe
type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520064490.1U
Other languages
Chinese (zh)
Inventor
胡俊
李艳荣
佳琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hainan University
Original Assignee
Hainan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hainan University filed Critical Hainan University
Priority to CN201520064490.1U priority Critical patent/CN204456065U/en
Application granted granted Critical
Publication of CN204456065U publication Critical patent/CN204456065U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model discloses a kind of X-type freezing pipe, body section is X-type, is inserted with feed pipe in body, and the top of feed pipe is provided with liquid back pipe.Freezing pipe is low-carbon (LC) seamless steel pipe or pvc pipe or PPR pipe or ABS pipe or PE pipe.The beneficial effects of the utility model: compared with the circular freezing pipe technology of tradition, X-shaped freezing pipe has larger unit volume material specific surface area, thus can greatly improve single valve freezing ability under the prerequisite not increasing engineering quantity, thus improves cost performance.Grow up in its periphery, circulating refrigerant medium consumption is few, and this technology has that practical, the quality control on construction of construction is convenient, consolidation effect is good and the outstanding advantages such as economy is superior, has larger application value.

Description

A kind of X-type freezing pipe
Technical field
The utility model relates to a kind of freezing pipe, particularly a kind of X-type freezing pipe.
Background technology
Artificial stratum freezing process utilizes artificial cooling technology; make the water freezing in stratum; natural ground is become frozen soil; increase its strength and stability; contacting of isolated underground water and underground construction; to carry out the special constructional technique of underground engineering construction under the protection of frost wall, its essence is and utilize artificial cooling Iterim Change rock and soil properties with strengthening stratum.Artificial Soil freezing process, owing to not substantially being subject to the restriction of supporting scope and the supporting degree of depth, effectively can preventing the distortion of adjacent upper body during water burst and city are excavated, Drilling is constructed and be subject to increasing attention, one of technical way becoming underground construction.Traditional freezing pipe is the single round tube of shape, causes single valve freezing indifferent, substantially increases circulating refrigerant medium consumption and construction machinery energy consumption.
Summary of the invention
The purpose of this utility model is indifferent in order to solve existing freezing pipe single valve freezing, causes the problem substantially increasing circulating refrigerant medium consumption and construction machinery energy consumption and a kind of X-type freezing pipe provided.
The body section of the X-type freezing pipe that the utility model provides is X-type, is inserted with feed pipe in body, and the top of feed pipe is provided with liquid back pipe.
Freezing pipe is low-carbon (LC) seamless steel pipe or pvc pipe or PPR pipe or ABS pipe or PE pipe.
Construction method is as described below:
One, preparation of construction
(1) require to supply water in advance, supply power near construction plant, and clear up tunnel and construction plant, ensure that construction is current smooth and easy.
(2) " freezing hole construction scaffold built by steel pipe, installs boring construction lifting platform to creep into requirement by the freezing hole of diverse location, with 1.5.
(3) construction equipment is marched into the arena.Because scene is large to construction infection, reasonable arrangement construction equipment is answered to transport the time sequencing of infield to.
Two, freezing borehole construction
(1) according to construction reference point, freezing hole is arranged by freezing hole construction figure.The biased difference in hole should not be greater than 100mm.
(2) horizontal drilling uses MD-60A type rig, and vertical drilling selects GXY-1 type rig to creep into.Before horizontal drilling, orifice tube and port seal to be installed.After first hole is opened, do not have Sand can continue to creep into, but boring later still to fill opening arrangement, occur in case broke-out diseases gushes sand phenomenon; If Sand is more severe, also answer cement injection (or dual slurry) sealing.
(3) in order to ensure Drilling Precision, perforate section is crucial.When creeping into front 5m, to repeatedly check drilling rod verticality, adjustment rig position, and adopt decompression to creep into, can continue to creep into after detecting deflection no problem.
(4) under freezing pipe in hand-hole before want first pipe arrangement, ensure freezing pipe concentricity.During welding, weld seam is full, ensures that freezing pipe has sufficient intensity, in order to avoid fracture of freezing pipe during tube drawing.After lower good freezing pipe, adopt transit Inclination Measurement by Light method to detect, the then repetition measurement freezing hole degree of depth, and carry out suppressing leak test.
(5) the underproof freezing pipe of pressure testing must carry out can using after process reaches seal request.Can propose to manage in hole by root, and with slush pump, weld seam one by one be suppressed, find out and leak weld seam and reason, process in time, and perform record, still must self-inspection after entering under secondary.
(6) feed pipe is entered under in freezing pipe.Feed pipe bottom connects the long support of 150mm, Ф 12 reinforcement welding.Then install go, loop goat's horn and freezing pipe end cap.
(7) after freezing pipe installs, the mouth of pipe is blocked with stopper etc., in order to avoid foreign matter falls into freezing pipe.
(8) thermometer hole construction method is identical with freezing pipe.
The beneficial effects of the utility model:
Freezing pipe outer wall forms X-shaped cavity in the earth formation, and feed pipe is put at heart position wherein, and arrange liquid back pipe at freezing pipe head, coolant media flows into from feed pipe simultaneously, flows out through liquid back pipe, and so circulation forms X-shaped Frozen Soil Cylinder in the earth formation.Compared with the circular freezing pipe technology of tradition, X-shaped freezing pipe has larger unit volume material specific surface area, thus can greatly improve single valve freezing ability under the prerequisite not increasing engineering quantity, thus improves cost performance.Grow up in its periphery, circulating refrigerant medium consumption is few, and this technology has that practical, the quality control on construction of construction is convenient, consolidation effect is good and the outstanding advantages such as economy is superior, has larger application value.
Accompanying drawing explanation
Fig. 1 is the utility model front view.
Fig. 2 is the utility model sectional schematic diagram.
1, body 2, feed pipe 3, liquid back pipe.
Detailed description of the invention
Refer to shown in Fig. 1, Fig. 2:
Body 1 section of the X-type freezing pipe that the utility model provides is X-type, is inserted with feed pipe 2 in body 1, and the top of feed pipe 2 is provided with liquid back pipe 3.
The body 1 of freezing pipe is low-carbon (LC) seamless steel pipe or pvc pipe or PPR pipe or ABS pipe or PE pipe.
Construction method is as described below:
One, preparation of construction
(1) require to supply water in advance, supply power near construction plant, and clear up tunnel and construction plant, ensure that construction is current smooth and easy.
(2) " freezing hole construction scaffold built by steel pipe, installs boring construction lifting platform to creep into requirement by the freezing hole of diverse location, with 1.5.
(3) construction equipment is marched into the arena.Because scene is large to construction infection, reasonable arrangement construction equipment is answered to transport the time sequencing of infield to.
Two, freezing borehole construction
(1) according to construction reference point, freezing hole is arranged by freezing hole construction figure.The biased difference in hole should not be greater than 100mm.
(2) horizontal drilling uses MD-60A type rig, and vertical drilling selects GXY-1 type rig to creep into.Before horizontal drilling, orifice tube and port seal to be installed.After first hole is opened, do not have Sand can continue to creep into, but boring later still to fill opening arrangement, occur in case broke-out diseases gushes sand phenomenon; If Sand is more severe, also answer cement injection (or dual slurry) sealing.
(3) in order to ensure Drilling Precision, perforate section is crucial.When creeping into front 5m, to repeatedly check drilling rod verticality, adjustment rig position, and adopt decompression to creep into, can continue to creep into after detecting deflection no problem.
(4) under freezing pipe in hand-hole before want first pipe arrangement, ensure freezing pipe concentricity.During welding, weld seam is full, ensures that freezing pipe has sufficient intensity, in order to avoid fracture of freezing pipe during tube drawing.After lower good freezing pipe, adopt transit Inclination Measurement by Light method to detect, the then repetition measurement freezing hole degree of depth, and carry out suppressing leak test.
(5) the underproof freezing pipe of pressure testing must carry out can using after process reaches seal request.Can propose to manage in hole by root, and with slush pump, weld seam one by one be suppressed, find out and leak weld seam and reason, process in time, and perform record, still must self-inspection after entering under secondary.
(6) feed pipe 2 is entered under in freezing pipe.Feed pipe 2 bottom connects the long support of 150mm, Ф 12 reinforcement welding.Then install go, loop goat's horn and freezing pipe end cap.
(7) after freezing pipe installs, the mouth of pipe is blocked with stopper etc., in order to avoid foreign matter falls into freezing pipe.
(8) thermometer hole construction method is identical with freezing pipe.

Claims (2)

1. an X-type freezing pipe, is characterized in that: the body section of freezing pipe is X-type, is inserted with feed pipe in body, and the top of feed pipe is provided with liquid back pipe.
2. a kind of X-type freezing pipe according to claim 1, is characterized in that: described freezing pipe is low-carbon (LC) seamless steel pipe or pvc pipe or PPR pipe or ABS pipe or PE pipe.
CN201520064490.1U 2015-01-30 2015-01-30 A kind of X-type freezing pipe Expired - Fee Related CN204456065U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520064490.1U CN204456065U (en) 2015-01-30 2015-01-30 A kind of X-type freezing pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520064490.1U CN204456065U (en) 2015-01-30 2015-01-30 A kind of X-type freezing pipe

Publications (1)

Publication Number Publication Date
CN204456065U true CN204456065U (en) 2015-07-08

Family

ID=53662974

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520064490.1U Expired - Fee Related CN204456065U (en) 2015-01-30 2015-01-30 A kind of X-type freezing pipe

Country Status (1)

Country Link
CN (1) CN204456065U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104863596A (en) * 2015-03-31 2015-08-26 中铁时代建筑设计院有限公司 X-shaped freezing pipe and application method thereof in freezing construction
CN105908696A (en) * 2016-06-03 2016-08-31 长春工程学院 Foundation pit frozen soil retaining wall device and freezing method thereof
CN110984124A (en) * 2019-11-15 2020-04-10 中国矿业大学 Spiral liquid nitrogen freezer and method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104863596A (en) * 2015-03-31 2015-08-26 中铁时代建筑设计院有限公司 X-shaped freezing pipe and application method thereof in freezing construction
CN104863596B (en) * 2015-03-31 2017-11-07 中铁时代建筑设计院有限公司 X-shaped freezing pipe and its application process in frozen construction
CN105908696A (en) * 2016-06-03 2016-08-31 长春工程学院 Foundation pit frozen soil retaining wall device and freezing method thereof
CN110984124A (en) * 2019-11-15 2020-04-10 中国矿业大学 Spiral liquid nitrogen freezer and method

Similar Documents

Publication Publication Date Title
CN104963334B (en) Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement
CN109208637A (en) Increase the construction method of open-cut station newly on the basis of existing tunnel
CN103015402B (en) Construction method for inhibiting frost heaving and thaw collapse of horizontally frozen end through cement-soil reinforcement method
CN102691296A (en) Pipe pile foundation for static-pressure grouting on pile side and rotary jet grouting at pile bottom and construction method thereof
CN202745937U (en) Hidden trench for concentrated seepage water guidance and drainage of existing tunnel in cold area
CN204456065U (en) A kind of X-type freezing pipe
CN205260041U (en) Method of freezing supporting construction is spouted soon to level
CN206052685U (en) Screw thread freezing pipe
CN104790419A (en) Dewatering construction method applicable to tunnel in water-rich quicksand stratum
CN209277184U (en) Deep basal pit drilling water burst emits sand seal block apparatus
CN105909259B (en) Existing shield tunnel pipe curtain construction settlement control system and method are closely worn down
CN112963156A (en) Composite reinforcing method and composite reinforcing structure for shallow tunnel in soil-rock composite stratum
CN205046548U (en) Pipe is freezed to abnormal shape
CN106837340B (en) The construction method of wall clearance grouting waterproof and reinforcing shaft wall structure under frost wall protection
CN105839651A (en) Roadbed slope assembly type deformation self-adaptive protective framework and splicing method thereof
CN107575238B (en) Shield-tunneling construction super close distance grouting method and grouting device
CN104005768B (en) The construction reinforcing method of vertical shaft interlude Unfavorable geology layer
CN109024710A (en) A kind of method for blocking of deep-foundation pit engineering artesian water piping
CN203569561U (en) Novel pile forming device of steel pipe protection wall cast-in-place piles following up drill
CN215169870U (en) A water installation is prevented gushing in drill way for horizontal directional drilling engineering geological survey
CN204959787U (en) Novel tower crane combination formula basis
CN108005662B (en) A kind of processing method of underground water seal cave depot storage cavern area geology crushed zone
CN207143920U (en) Water-stopping system between novel pile under a kind of complicated circumstance of flowing water
CN206599781U (en) A kind of pile of deep water pile foundation ribs built-in steel casing
CN205653804U (en) Slope assembled warp self -adaptation protection skeleton

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150708

Termination date: 20160130

EXPY Termination of patent right or utility model