CN207143920U - Water-stopping system between novel pile under a kind of complicated circumstance of flowing water - Google Patents

Water-stopping system between novel pile under a kind of complicated circumstance of flowing water Download PDF

Info

Publication number
CN207143920U
CN207143920U CN201721014364.0U CN201721014364U CN207143920U CN 207143920 U CN207143920 U CN 207143920U CN 201721014364 U CN201721014364 U CN 201721014364U CN 207143920 U CN207143920 U CN 207143920U
Authority
CN
China
Prior art keywords
water
pile
steel plate
sealing
stopping system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721014364.0U
Other languages
Chinese (zh)
Inventor
秦凯
刘建雄
廖广超
谢志斌
郑伟文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Coal Jiangnan Construction Development Group Co., Ltd
Original Assignee
GUANGDONG CHINA COAL JIANGNAN FOUNDATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG CHINA COAL JIANGNAN FOUNDATION ENGINEERING Co Ltd filed Critical GUANGDONG CHINA COAL JIANGNAN FOUNDATION ENGINEERING Co Ltd
Priority to CN201721014364.0U priority Critical patent/CN207143920U/en
Application granted granted Critical
Publication of CN207143920U publication Critical patent/CN207143920U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses water-stopping system, its structure between novel pile under a kind of complicated circumstance of flowing water to include:Mixing pile, support pile, steel plate for sealing water, expansion bolt, outer drawing reinforced mesh, cement, grouting equipment, slip casting backstage, diaphragm wall, water-stopping system between novel pile under a kind of complicated circumstance of flowing water of the utility model, steel plate for sealing water rigidity can be reached greatly and be close to support pile, bulk strength is high, flowing pressure is effectively avoided to puncture weak surface layer between support pile, form water burst and gush sand, high-pressure injection device is avoided during construction, the pollution to environment is effectively prevented, according to foundation depth, stake seam size and shape, different-thickness is tailored respectively, the steel plate for sealing water of size, without waste of material, the system is mounted directly fixation, confirm that sealing label steel plate for sealing water can effectively solve joint leak at continuous wall connector, it is equally applicable to other kinds joint, strengthen sealing, earth-retaining effect.

Description

Water-stopping system between novel pile under a kind of complicated circumstance of flowing water
Technical field
The utility model is water-stopping system between novel pile under a kind of complicated circumstance of flowing water, belongs to new under complicated circumstance of flowing water Waterproof between piles system regions.
Background technology
Common shotcrete with wire mesh, have the characteristics that speed of application is fast, cost is low, take that working face is small is obtained in slope retaining Widely apply.
Prior art discloses Application No.:201420134851.0 a kind of waterproof concrete wall combination sealing system System, including middle buried water stop, water expandable waterstop, the middle buried water stop are fixed on the reinforcing bar of waterproof concrete wall On skeleton, and the middle buried water stop is located at the middle part of the framework of steel reinforcement through-thickness of waterproof concrete wall, in bury Formula waterstop extends to the other end from one end of the horizontal construction joint of waterproof concrete wall, and middle buried water stop is along width The center in direction and the horizontal construction joint of waterproof concrete wall it is highly consistent, the water expandable waterstop is fixed on waterproof On bottom concrete interface at the horizontal construction joint of concrete wall, and water expandable waterstop is from waterproof concrete wall One end of horizontal construction joint extend to the other end, utility model waterproof concrete wall combination water-stopping system, can solve The waterproof problem of large-scale waterproof concrete wall structure under the effect of super large head pressure, but prior art shotcrete with wire mesh is easy There is surface spray concrete uneven thickness, quality is unstable, the defects of plane of weakness of low intensity be present, in rich groundwater region, has Wet season and the big region of flowing pressure in water supply region are often due to spray concrete uneven thickness, flowing pressure is easily in weakness Breakdown net spray structure, forms water burst and gushes the hidden danger such as sand, bring threatening environment to pollute to deep pit monitor big, shotcrete with wire mesh typically uses Live mixing concrete, operation is carried out in the distance apart from slope side 1.0m or so using high-pressure injection device, larger raise can be produced Dirt, cause greatly to destroy to surrounding enviroment.
Waste of material is more, big through sandstone material rebound amount during testing shotcrete with wire mesh, and can not reuse, and causes material Expect that serious waste speed of application is relatively slow, shotcrete with wire mesh needs to hang bar-mat reinforcement processed after clearing up stake face surface dust, then could spray Concrete, and secondary need to survive, it is overall than relatively time-consuming, then conserved progressively upper intensity by 14 days, it is difficult to meet rainy season or ground The specific demand shotcrete with wire mesh surface perception that the abundant region of lower water must complete slope protection as early as possible is poor, due to course of injection Middle uneven distribution, height rise and fall, and local dent or projection cause that overall perception is poor, and water-stop curtain is in design of foundation pit in recent years It is more universal, but often because existing, old basis influences mixing pile construction quality, the perpendicularity of influence mixing pile causes overlap joint not It is good, form water stream channel;There are a large amount of water rechargings on project periphery, can not drain to form ponding for the moment;Foundation ditch region has greatly After a variety of causes such as the stratum of amount good water permeability cause excavation of foundation pit, water pressure is huge, finally racks mixing pile, so as to form base Leakage accident is cheated, but after such accident occurs, can be streamed because current run into barrier, can float that shove can not under water pressure Accurate judgement leakage point, cause to be difficult to fast and effectively to carry out slip casting closure, cause following inconvenience:Cost is high, it is difficult to which a labor is forever Ease, can stream because current run into barrier, can from different angles, highly gush out under water pressure, so that can not accurately sentence Disconnected leakage point, causes to be difficult to fast and effectively to carry out slip casting closure, and the supporting at leak is needed to thoroughly closure leakage point Stake periphery slip casting is constructed rotary churning pile on a large scale, and cost is huge, and has simply temporarily blocked leakage point after slip casting, but due to current Constantly impact, may gush from other weak spots, form new leakage point, bring grave danger to deep pit monitor, enter again Degree is slow, and time-consuming, needs first can just be continued to bore with the concrete diffusion region of the drill-through Guan Liang of coring bit and support pile during slip casting Enter slip casting, slip casting closure scope is wide, it is necessary to time-consuming longer in addition, it is more difficult to alleviates the pressure at heart of closure leakage point, calms down anxiety Mood.
Utility model content
In view of the deficienciess of the prior art, the utility model purpose is to provide under a kind of complicated circumstance of flowing water between novel pile Water-stopping system, easily there is surface spray concrete uneven thickness to solve shotcrete with wire mesh, quality is unstable, the plane of weakness etc. of low intensity be present Defect, in rich groundwater region, have water supply region wet season and the big region of flowing pressure often due to spray concrete is thick Degree is uneven, and flowing pressure easily punctures net spray structure in weakness, forms water burst and gushes the hidden danger such as sand, threat ring is brought to deep pit monitor Border pollution is big.Shotcrete with wire mesh typically uses live mixing concrete, using high-pressure injection device apart from slope side 1.0m's or so Distance carries out operation, can produce larger airborne dust, cause greatly to destroy to surrounding enviroment.
Waste of material is more, big through sandstone material rebound amount during testing shotcrete with wire mesh, and can not reuse, and causes material Expect that serious waste speed of application is relatively slow, shotcrete with wire mesh needs to hang bar-mat reinforcement processed after clearing up stake face surface dust, then could spray Concrete, and secondary need to survive, it is overall than relatively time-consuming, then conserved progressively upper intensity by 14 days, it is difficult to meet rainy season or ground The specific demand shotcrete with wire mesh surface perception that the abundant region of lower water must complete slope protection as early as possible is poor, due to course of injection Middle uneven distribution, height rise and fall, and local dent or projection cause that overall perception is poor, and water-stop curtain is in design of foundation pit in recent years It is more universal, but often because existing, old basis influences mixing pile construction quality, the perpendicularity of influence mixing pile causes overlap joint not It is good, form water stream channel;There are a large amount of water rechargings on project periphery, can not drain to form ponding for the moment;Foundation ditch region has greatly After a variety of causes such as the stratum of amount good water permeability cause excavation of foundation pit, water pressure is huge, finally racks mixing pile, so as to form base Leakage accident is cheated, but after such accident occurs, can be streamed because current run into barrier, can float that shove can not under water pressure Accurate judgement leakage point, cause to be difficult to fast and effectively to carry out slip casting closure, cause following inconvenience:Cost is high, it is difficult to which a labor is forever Ease, can stream because current run into barrier, can from different angles, highly gush out under water pressure, so that can not accurately sentence Disconnected leakage point, causes to be difficult to fast and effectively to carry out slip casting closure, and the supporting at leak is needed to thoroughly closure leakage point Stake periphery slip casting is constructed rotary churning pile on a large scale, and cost is huge, and has simply temporarily blocked leakage point after slip casting, but due to current Constantly impact, may gush from other weak spots, form new leakage point, bring grave danger to deep pit monitor, enter again Degree is slow, and time-consuming, needs first can just be continued to bore with the concrete diffusion region of the drill-through Guan Liang of coring bit and support pile during slip casting Enter slip casting, slip casting closure scope is wide, it is necessary to time-consuming longer in addition, it is more difficult to alleviates the pressure at heart of closure leakage point, calms down anxiety The problem of mood.
To achieve these goals, the utility model is to realize by the following technical solutions:A kind of complicated dynamic water ring Water-stopping system between novel pile under border, its structure include:Mixing pile, support pile, steel plate for sealing water, expansion bolt, it is outer drawing reinforced mesh, Cement, grouting equipment, slip casting backstage, diaphragm wall, the mixing pile are fixedly mounted on the front of cement, and the support pile is located at water The left and right sides of mud and it is secured to connect, the steel plate for sealing water is located at the rear surface of cement and fixed by expansion bolt Connection, the grouting equipment are located at the right flank of cement and are flexibly connected with it, and the slip casting backstage is positioned at the interior of grouting equipment Side and it is secured to connect.
Further, the diaphragm wall is located at the front and rear sides of mixing pile and coupled.
Further, the outer drawing reinforced mesh is located at the lateral surface of steel plate for sealing water and is flexibly connected with it.
Further, the support pile is parallel to each other.
Further, the cement is parallel to each other with outer drawing reinforced mesh.
Further, the grouting equipment is parallel to each other with slip casting backstage.
Further, the grouting equipment is made of metal material.
Beneficial effect
Water-stopping system between novel pile under a kind of complicated circumstance of flowing water of the utility model, can reach steel plate for sealing water rigidity it is big and It is close to support pile, no infiltration gap, support is fixed to drawing welding by setscrew with reinforcing bar outside steel plate for sealing water, it is overall strong Degree is high, effectively avoids weak surface layer between flowing pressure breakdown support pile, forms water burst and gush sand.High-pressure injection dress is avoided during construction Put, effectively prevented the pollution to environment, size and shape is stitched according to foundation depth, stake, tailors different-thickness, size respectively Steel plate for sealing water, no waste of material, the system are mounted directly fixation, can once survive, speed, can effectively reduce domatic Open-assembly time, while reduce manpower waste, the average whole light in surface after the completion of water-stopping system between novel pile under complicated circumstance of flowing water Clean, overall appearance, because speed of application is very fast, no waste of material, for overall cost than relatively low, the coplanar valency that manufactures is about shotcrete with wire mesh 3/4ths, when running into water burst and gushing the situation of sand, head into bat by the lumps of wood using digging machine and carry out the closure grains of sand, preliminary only sand Drainage tube is set if necessary afterwards, water is drawn and then quick fixation steel plate, then slip casting (can fill waterglass, biliquid note Slurry), the closure of periphery all piles seam is sequentially completed, forms entirety, forever trouble without offspring.Low cost is already described above, can be close to Continuous wall connector strengthens water-stagnating effect, and churning typically can be all set in joint area for enhancing water-stagnating effect in construction of diaphragm wall Stake, but by the way that it was verified that this behave is difficult still to avoid joint leak, continuous wall connector often occurs in excavation for many years Leak, after repeatedly attempting and improving, it was demonstrated that sealing label steel plate for sealing water can effectively solve joint leak at continuous wall connector, It is equally applicable to other kinds joint, enhancing sealing, the purpose of earth-retaining effect.
Brief description of the drawings
By reading the detailed description made with reference to the following drawings to non-limiting example, other spies of the present utility model Sign, objects and advantages will become more apparent upon:
Fig. 1 is the structural representation of water-stopping system between novel pile under a kind of complicated circumstance of flowing water of the utility model.
Fig. 2 is the external structure schematic diagram of water-stopping system between novel pile under the utility model kind complexity circumstance of flowing water.
Fig. 3 is the use schematic internal view of water-stopping system between novel pile under the utility model kind complexity circumstance of flowing water.
Fig. 4 is the use schematic diagram of water-stopping system between novel pile under the utility model kind complexity circumstance of flowing water
In figure:Mixing pile -1, support pile -2, steel plate for sealing water -3, expansion bolt -4, outer drawing reinforced mesh -5, cement -6, note Starch equipment -7, slip casting backstage -8, diaphragm wall -9.
Embodiment
Technological means, creation characteristic, reached purpose and effect to realize the utility model are easy to understand, below With reference to embodiment, the utility model is expanded on further.
Refer to Fig. 1-Fig. 4, the utility model provides under a kind of complicated circumstance of flowing water water-stopping system, its structure between novel pile Including:After mixing pile 1, support pile 2, steel plate for sealing water 3, expansion bolt 4, outer drawing reinforced mesh 5, cement 6, grouting equipment 7, slip casting Platform 8, diaphragm wall 9, the mixing pile 1 are fixedly mounted on the front of cement 6, and the support pile 2 is located at the left and right sides of cement 6 simultaneously And be secured to connect, the steel plate for sealing water 3 is located at the rear surface of cement 6 and is fixedly connected by expansion bolt 4, the note Slurry equipment 7 be located at the right flank of cement 6 and is flexibly connected with it, slip casting backstage 8 be located at the inner side of grouting equipment 7 and and its It is fixedly connected, the diaphragm wall 9 is located at front and rear sides of mixing pile 1 and coupled, and the outer drawing reinforced mesh 5 is positioned at only The lateral surface of water steel plate 3 and it is flexibly connected with it, the support pile 2 is parallel to each other, the cement 6 and the outer drawing phase of reinforced mesh 5 Mutually parallel, the grouting equipment 7 is parallel to each other with slip casting backstage 8, and the grouting equipment 7 is made of metal material.
Expansion bolt 4 described in the utility model be by pipeline branch/hang/bracket or equipment fix on the wall, on floor, post A kind of upper special thread connector used.
When using water-stopping system between novel pile under complicated circumstance of flowing water, if can directly be blocked only without leak scene after excavating Water steel plate, accelerating construction progress;If leak occurs after excavating, depending on whether gushing husky and leak size, using backfill back-pressure, bat plug After the measure processing such as stifled, drainage repairing, you can directly block steel plate for sealing water 3, accelerating construction progress, top necessarily be greater than underground water Position;Bottom has to enter into foundation ditch bottom and is no less than 0.5m, and overlap joint be no less than 10cm between steel plate, when running into water burst and gushing husky situation, The bat closure grains of sand are headed into by the lumps of wood using digging machine, drainage tube is set if necessary after preliminary only sand, pressure release power, maintains primary Mother-in-law is stable, and water is drawn into then quick fixation steel plate, steel plate thickness about 3mm, has certain plasticity, can firmly extrude, ensure steel Plate is in close contact with support pile, and tight, steel plate must be embedded in foundation ditch bottom and be no less than 50cm, overlap and be no less than between steel plate 10cm, after fixing steel plate, it to be close to steel plate and squeezes into setscrew, it is necessary to assure setscrew enters the certain depth of support pile, Meet force request, it is possible to provide reliable withdrawal resistance, use the round steel of Ф 10 after squeezing into setscrew, spacing 150mm welds to drawing, shape Into bar-mat reinforcement, stable support is provided steel plate for sealing water jointly, after completing the support to steel plate, in the space of support pile and steel plate In pour into cement mortar, enrich all spaces, inaccessible water stream channel, play the effect of sealing earth-retaining.
Mixing pile 1 of the present utility model, support pile 2, steel plate for sealing water 3, expansion bolt 4, outer drawing reinforced mesh 5, cement 6, Grouting equipment 7, slip casting backstage 8, the part that the part of diaphragm wall 9 is universal standard part or those skilled in the art know, it is tied Structure and principle are all that this technology personnel can be learnt by technical manual or be known by normal experiment method, the utility model solution Certainly the problem of is that shotcrete with wire mesh surface spray concrete uneven thickness easily occurs, and quality is unstable, the defects of plane of weakness of low intensity be present, In rich groundwater region, have water supply region wet season and the big region of flowing pressure often due to spray concrete thickness not , flowing pressure easily punctures net spray structure in weakness, forms water burst and gushes the hidden danger such as sand, brings threatening environment dirty to deep pit monitor Dye is big.Shotcrete with wire mesh typically uses live mixing concrete, using high-pressure injection device in the distance apart from slope side 1.0m or so Operation is carried out, larger airborne dust can be produced, cause greatly to destroy to surrounding enviroment.
Waste of material is more.It is big through sandstone material rebound amount during testing shotcrete with wire mesh, and can not reuse, cause material Expect that serious waste speed of application is relatively slow.Shotcrete with wire mesh needs to hang bar-mat reinforcement processed after clearing up stake face surface dust, then could spray Concrete, and secondary need to survive, it is overall than relatively time-consuming, then conserved progressively upper intensity by 14 days, it is difficult to meet rainy season or ground The specific demand shotcrete with wire mesh surface perception that the abundant region of lower water must complete slope protection as early as possible is poor.Due to course of injection Middle uneven distribution, height rise and fall, and local dent or projection cause that overall perception is poor, and water-stop curtain is in design of foundation pit in recent years It is more universal, but often because existing, old basis influences mixing pile construction quality, the perpendicularity of influence mixing pile causes overlap joint not It is good, form water stream channel;There are a large amount of water rechargings on project periphery, can not drain to form ponding for the moment;Foundation ditch region has greatly After a variety of causes such as the stratum of amount good water permeability cause excavation of foundation pit, water pressure is huge, finally racks mixing pile, so as to form base Cheat leakage accident.But it after such accident occurs, can be streamed because current run into barrier, can float that shove can not under water pressure Accurate judgement leakage point, cause to be difficult to fast and effectively to carry out slip casting closure, cause following inconvenience:Cost is high, it is difficult to which a labor is forever Ease.It can stream because current run into barrier, can from different angles, highly gush out under water pressure, so that can not accurately sentence Disconnected leakage point, causes to be difficult to fast and effectively to carry out slip casting closure, and the supporting at leak is needed to thoroughly closure leakage point Stake periphery slip casting is constructed rotary churning pile on a large scale, and cost is huge, and has simply temporarily blocked leakage point after slip casting, but due to current Constantly impact, may gush from other weak spots, form new leakage point, bring grave danger to deep pit monitor, enter again Degree is slow, and time-consuming.Need first can just be continued to bore with the concrete diffusion region of the drill-through Guan Liang of coring bit and support pile during slip casting Enter slip casting, slip casting closure scope is wide, it is necessary to time-consuming longer in addition, it is more difficult to alleviates the pressure at heart of closure leakage point, calms down anxiety The problem of mood, the utility model are combined with each other by above-mentioned part, can be reached steel plate for sealing water rigidity greatly and are close to supporting Stake, no infiltration gap, support is fixed to drawing welding by setscrew with reinforcing bar outside steel plate for sealing water, bulk strength is high, has Effect avoids weak surface layer between flowing pressure breakdown support pile, forms water burst and gushes sand.High-pressure injection device is avoided during construction, effectively The pollution to environment is prevented, size and shape is stitched according to foundation depth, stake, tailors different-thickness, the water-stopping steel of size respectively Plate, no waste of material, the system are mounted directly fixation, can once survive, speed, can effectively reduce domatic exposure Time, while manpower waste is reduced, surface is average whole bright and clean after the completion of water-stopping system between novel pile under complicated circumstance of flowing water, overall Attractive in appearance, because speed of application is very fast, no waste of material, overall cost is than relatively low, coplanar four points for manufacturing valency and being about shotcrete with wire mesh Three, when running into water burst and gushing the situation of sand, head into bat by the lumps of wood using digging machine and carry out the closure grains of sand, it is preliminary it is only husky after it is necessary When drainage tube is set, water is drawn and then quick fixation steel plate, then slip casting (waterglass, two fluid grouting can be filled), successively The closure of periphery all piles seam is completed, forms entirety, forever trouble without offspring.Low cost is already described above, can be close to diaphragm wall and be connect Head enhancing water-stagnating effect, rotary churning pile typically can be all set in construction of diaphragm wall in joint area for enhancing water-stagnating effect, but logical It was verified that this behave is difficult still to avoid joint leak, continuous wall connector leak often occurs in excavation after for many years, passes through Cross after repeatedly attempting and improving, it was demonstrated that sealing label steel plate for sealing water can effectively solve joint leak at continuous wall connector, same suitable For other kinds joint, enhancing sealing, the purpose of earth-retaining effect are described in detail below:
The mixing pile 1 is fixedly mounted on the front of cement 6, the support pile 2 be located at the left and right sides of cement 6 and with It is fixedly connected, and the steel plate for sealing water 3 is located at the rear surface of cement 6 and is fixedly connected by expansion bolt 4, and the slip casting is set Standby 7 are located at the right flank of cement 6 and are flexibly connected with it, and the slip casting backstage 8 is positioned at the inner side of grouting equipment 7 and is secured to Connection, the diaphragm wall 9 are located at front and rear sides of mixing pile 1 and coupled.The outer drawing reinforced mesh 5 is located at water-stopping steel The lateral surface of plate 3 and it is flexibly connected with it.
The advantages of general principle and principal character of the present utility model and the utility model has been shown and described above, for For those skilled in the art, it is clear that the utility model is not limited to the details of above-mentioned one exemplary embodiment, and without departing substantially from this In the case of the spirit or essential attributes of utility model, the utility model can be realized in other specific forms.Therefore, no matter From the point of view of which point, embodiment all should be regarded as exemplary, and be nonrestrictive, the scope of the utility model is by institute Attached claim rather than described above limit, it is intended that will fall in the implication and scope of the equivalency of claim All changes are included in the utility model.Any reference in claim should not be considered as to the involved right of limitation It is required that.
Moreover, it will be appreciated that although the present specification is described in terms of embodiments, not each embodiment is only wrapped Containing an independent technical scheme, this narrating mode of specification is only that those skilled in the art should for clarity Using specification as an entirety, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art It is appreciated that other embodiment.

Claims (6)

  1. A kind of 1. water-stopping system between novel pile under complicated circumstance of flowing water, it is characterised in that:Its structure includes:Mixing pile (1), supporting Stake (2), steel plate for sealing water (3), expansion bolt (4), outer drawing reinforced mesh (5), cement (6), grouting equipment (7), slip casting backstage (8), diaphragm wall (9), the mixing pile (1) are fixedly mounted on the front of cement (6), and the support pile (2) is located at cement (6) The left and right sides and it is secured to connect, the steel plate for sealing water (3) is located at the rear surface of cement (6) and passes through expansion bolt (4) it is fixedly connected, the grouting equipment (7) is located at the right flank of cement (6) and is flexibly connected with it, the slip casting backstage (8) Positioned at the inner side of grouting equipment (7) and it is secured to connect.
  2. 2. water-stopping system between novel pile under a kind of complicated circumstance of flowing water according to claim 1, it is characterised in that:The company Continuous wall (9) is located at front and rear sides of mixing pile (1) and coupled.
  3. 3. water-stopping system between novel pile under a kind of complicated circumstance of flowing water according to claim 1, it is characterised in that:It is described outer Reinforced mesh (5) is drawn to be located at the lateral surface of steel plate for sealing water (3) and be flexibly connected with it.
  4. 4. water-stopping system between novel pile under a kind of complicated circumstance of flowing water according to claim 1, it is characterised in that:The branch Fender pile (2) is parallel to each other.
  5. 5. water-stopping system between novel pile under a kind of complicated circumstance of flowing water according to claim 1, it is characterised in that:The water Mud (6) is parallel to each other with outer drawing reinforced mesh (5).
  6. 6. water-stopping system between novel pile under a kind of complicated circumstance of flowing water according to claim 1, it is characterised in that:The note Slurry equipment (7) is parallel to each other with slip casting backstage (8).
CN201721014364.0U 2017-08-15 2017-08-15 Water-stopping system between novel pile under a kind of complicated circumstance of flowing water Active CN207143920U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721014364.0U CN207143920U (en) 2017-08-15 2017-08-15 Water-stopping system between novel pile under a kind of complicated circumstance of flowing water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721014364.0U CN207143920U (en) 2017-08-15 2017-08-15 Water-stopping system between novel pile under a kind of complicated circumstance of flowing water

Publications (1)

Publication Number Publication Date
CN207143920U true CN207143920U (en) 2018-03-27

Family

ID=61666434

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721014364.0U Active CN207143920U (en) 2017-08-15 2017-08-15 Water-stopping system between novel pile under a kind of complicated circumstance of flowing water

Country Status (1)

Country Link
CN (1) CN207143920U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110670598A (en) * 2019-07-24 2020-01-10 青岛理工大学 Cold joint treatment structure and method for secant pile construction
CN111764397A (en) * 2020-05-28 2020-10-13 浙江土工岩土科技有限公司 Underground diaphragm wall plugging device and method
CN112726626A (en) * 2020-12-25 2021-04-30 中国建筑第八工程局有限公司 Method for stopping leakage between foundation pit retaining piles

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110670598A (en) * 2019-07-24 2020-01-10 青岛理工大学 Cold joint treatment structure and method for secant pile construction
CN111764397A (en) * 2020-05-28 2020-10-13 浙江土工岩土科技有限公司 Underground diaphragm wall plugging device and method
CN112726626A (en) * 2020-12-25 2021-04-30 中国建筑第八工程局有限公司 Method for stopping leakage between foundation pit retaining piles

Similar Documents

Publication Publication Date Title
CN104594348B (en) Enlarged footing bellows anchor pole and construction method thereof
CN204343312U (en) A kind of plugging device of precipitation well in foundation pit
CN104806272B (en) Tunnel shunting combined type guarded drainage integrated system and construction method and using method
CN106437726B (en) Shallow-depth-excavation tunnel crosses ground fissure crushed zone construction method
CN105298518B (en) A kind of profound cavern bridging of hidden-type blocks the administering method of water burst
CN104453946B (en) Advanced reinforcing construction method for building tunnel in soft surrounding rock
CN109208637A (en) Increase the construction method of open-cut station newly on the basis of existing tunnel
CN203034467U (en) Combined steel pile cofferdam with water-proof fore shafts
CN207143920U (en) Water-stopping system between novel pile under a kind of complicated circumstance of flowing water
CN204572015U (en) A kind of tunnel shunting combined type waterproof and water drainage system
CN103225318B (en) Anti-seepage and leaking-stoppage device for underground consecutive wall groove section joint point and construction method thereof
CN103924987B (en) A kind of SMW engineering method stake tunnel shielding portal seepage-proof structure and construction method thereof
CN106193032B (en) A kind of anti-float anchor rod construction method
CN102011397A (en) Construction process of concrete form water-stopping occlusion pile
JP7257086B2 (en) Comprehensive Construction Method for Low Overburden Sections of Tunnels
CN103981782A (en) Method and structure for reinforcing flat hole grouting roadbed without damaging road surface
CN109629845A (en) Concrete structure seam areas leakage treatment device and its construction method
CN107217676A (en) A kind of steel cylinder with seal groove and occlusion structure or steel sheet pile and steel construction diaphragm wall
CN104314106A (en) Underground diaphragm wall with joint water stop and filling vacancy structure and construction method thereof
CN113153379B (en) Tunnel waterproof and drainage system and construction process
CN107653889A (en) A kind of shaped steel pressure is poured water the construction method of soil curtain support pile
CN105220700B (en) Foundation pit waterproof curtain reinforcement
CN108005662B (en) A kind of processing method of underground water seal cave depot storage cavern area geology crushed zone
CN203855868U (en) Flat-hole grouted roadbed reinforcing structure without damages to road surface
CN104632228B (en) Main track entering construction method for cross aisle and cross aisle

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 510000 Unit 1002-1007, 140 Dongfeng West Road, Yuexiu District, Guangzhou City, Guangdong Province

Patentee after: China Coal Jiangnan Construction Development Co., Ltd.

Address before: 510000 Unit 1002-1007, 140 Dongfeng West Road, Yuexiu District, Guangzhou City, Guangdong Province

Patentee before: Guangdong China Coal Jiangnan Foundation Engineering Co., Ltd.

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: Unit 1002-1007, 140 Dongfeng West Road, Yuexiu District, Guangzhou, Guangdong 510000

Patentee after: China Coal Jiangnan Construction Development Group Co., Ltd

Address before: Unit 1002-1007, 140 Dongfeng West Road, Yuexiu District, Guangzhou, Guangdong 510000

Patentee before: CHINA COAL JIANGNAN CONSTRUCTION DEVELOPMENT Co.,Ltd.

CP01 Change in the name or title of a patent holder