CN204343326U CN201420786415.1U CN201420786415U CN204343326U CN 204343326 U CN204343326 U CN 204343326U CN 201420786415 U CN201420786415 U CN 201420786415U CN 204343326 U CN204343326 U CN 204343326U
Authority
CN
China
Prior art keywords
pipe
pvc
buried
buried pvc
spreading
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420786415.1U
Other languages
Chinese (zh)
Inventor
武伟华
袁明泉
温凯
张奎
宋述强
王贤春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of CTCE Group
Original Assignee
Third Construction Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of CTCE Group filed Critical Third Construction Co Ltd of CTCE Group
Priority to CN201420786415.1U priority Critical patent/CN204343326U/en
Application granted granted Critical
Publication of CN204343326U publication Critical patent/CN204343326U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model relates to pipe spreading shutoff leakage preventing structure in the pre-buried pvc pipe cover of a kind of concrete wall, it is characterized in that: be coaxially installed with in the asbestos cement sealant in PVC between pipe and pre-buried pvc pipe and combine waterproof packed layer, the structure of this combination waterproof packed layer is: coaxial installation one hydro-expansive rubber sealing collar on pipe in the PVC in asbestos cement sealant, is symmetrically installed with spunyarn and soaks polyurethane water-swellable water stop gel ring between this water-swellable sealing collar both sides and asbestos cement sealant.The utility model carries out after reinforced concrete wall construction, eliminate built-in pipe in concrete construction and pass template spillage problem, avoid the generation of hidden danger of quality, within can being widely used in DN500, impervious concrete pipe built-in pvc pipe overlaps interior pipe spreading shutoff antiseepage, workable, anti-seepage effect is very good.

Description

Pipe spreading shutoff leakage preventing structure in the pre-buried pvc pipe cover of a kind of concrete wall
Technical field
The utility model belongs to building, water conservancy construction field, relates to the antiseep process between PVC pipeline, pipe spreading shutoff leakage preventing structure in the pre-buried pvc pipe cover of especially a kind of concrete wall.
Background technology
Pipe grafting technique in the pre-buried pvc pipe cover of Reinforced Concrete Retaining Walls, is widely used in building, hydraulic engineering.Reinforced concrete wall behind ponding is discharged often through wall pre-embedded water pipe, and water pipe need extend to the outer 2-5 rice of body of wall, by Waterflow-guiding to assigned address.But when practice of construction, affecting by template restriction or extension tube front-end architecture can not one-shot forming, need first pre-buried pvc pipe between reinforced concrete wall, by pipeline spreading after wall construction is complete, because reinforced concrete wall requires restriction by antiseepage requirement and pipeline gradient, adopt the direct spreading of inner connecting tube cannot reach antiseepage requirement, therefore to need to adopt in cover close measure after pipe spreading, workable, anti-seepage effect is very good.
Retrieved by patent document, not yet find the patent document identical with the utility model.
Summary of the invention
The purpose of this utility model overcomes the deficiencies in the prior art part, pipe spreading shutoff leakage preventing structure in the pre-buried pvc pipe cover of a kind of concrete wall is provided, this structure seeps water can obtain effective block wall after pvc pipe spreading after, ensures that occluding member is the same with concrete guard wall anti-seepage effect.
The utility model is that technical solution problem adopts following technical scheme:
Pipe spreading shutoff leakage preventing structure in the pre-buried pvc pipe cover of a kind of concrete wall, pre-buried pvc pipe is inclined and mounted in impervious concrete barricade, in pre-buried pvc pipe, coaxial installation in PVC is managed, asbestos cement sealant is adopted to seal between pipe and pre-buried pvc pipe in this PVC, it is characterized in that: be coaxially installed with in the asbestos cement sealant in PVC between pipe and pre-buried pvc pipe and combine waterproof packed layer, the structure of this combination waterproof packed layer is: coaxial installation one hydro-expansive rubber sealing collar on pipe in the PVC in asbestos cement sealant, be symmetrically installed with spunyarn in asbestos cement sealant in the PVC of these hydro-expansive rubber sealing collar both sides between pipe and pre-buried pvc pipe and soak polyurethane water-swellable water stop gel ring.
And, clog by polyurethane water-swellable water-stop glue between the hydro-expansive rubber sealing collar between spunyarn leaching polyurethane water-swellable water stop gel ring and pre-buried pvc pipe inwall.
And the difference of the external diameter of pipe is not less than 5cm in the external diameter of described pre-buried pvc pipe and PVC.
Advantage of the present utility model and good effect are:
1, the utility model adopts the method for pipe spreading in cover, and decrease the fixation problem that front pvc pipe sponson built by steel concrete, technological operation is easy, and constructor is easy to grasp, safe and reliable, and pvc pipe spreading synchronously can carry out with rolling earth behind retaining wall.
2, the utility model carries out after reinforced concrete wall construction, eliminate built-in pipe in concrete construction and pass template spillage problem, avoid the generation of hidden danger of quality, within can being widely used in DN500, impervious concrete pipe built-in pvc pipe overlaps interior pipe spreading, workable, anti-seepage effect is very good.
Accompanying drawing explanation
Fig. 1 is cross section schematic diagram of the present utility model;
Fig. 2 is that the A-A of Fig. 1 is to cross-sectional view.
Detailed description of the invention
Describe embodiment of the present utility model in detail below in conjunction with accompanying drawing, it should be noted that, the present embodiment is narrative, is not determinate, can not limit protection domain of the present utility model with this.
Pipe spreading shutoff leakage preventing structure in the pre-buried pvc pipe cover of a kind of concrete wall, pre-buried pvc pipe 4 is downward-sloping to be arranged in impervious concrete barricade 1, in pre-buried pvc pipe, pipe 7 in coaxial installation PVC, adopts asbestos cement sealant 6 to seal between pipe and pre-buried pvc pipe in this PVC.
Innovative point of the present utility model is:
Be coaxially installed with in asbestos cement sealant in PVC between pipe and pre-buried pvc pipe and combine waterproof packed layer, its structure is: coaxial installation one hydro-expansive rubber sealing collar 3 on pipe in the PVC in asbestos cement sealant, is symmetrically installed with spunyarn and soaks polyurethane water-swellable water stop gel ring 5 between this hydro-expansive rubber sealing collar both sides and asbestos cement sealant.
In order to improve barrier performance further, polyurethane water-swellable water-stop glue 2 is clogged between pipe in hydro-expansive rubber sealing collar between spunyarn leaching polyurethane water-swellable water stop gel ring and PVC, this structure can ensure the bonding of pvc pipe and water expandable waterstop, can prevent the capillary water seepage flow between packed layer and pvc pipe wall.
In the present embodiment, in the external diameter of described pre-buried pvc pipe and PVC, the difference of the external diameter of pipe is not less than 5cm.
In the present embodiment, the thickness of described water-swelling rubber water bar is not less than 2.0cm.
In the present embodiment, described spunyarn leaching polyurethane water-swellable water stop gel ring take PN-220 as material.
In the present embodiment, be water in mass ratio in described asbestos cement sealant: asbestos: cement=1: 3: 7, asbestos cement sealant is used for outer sealing, also claim asbestos expansive cement, these asbestos are 4 grades or 5 grades of asbestos wools, and cement adopts the portland cement being not less than No. 425, asbestos cement packing seal layer should be finished in 1 hour, otherwise exceeding jelling time can affect sealing effect, the maintenance of asbestos cement sealant need more than 24 hours; Asbestos cement has higher-strength and good shock resistance, watertightness and bonding force good;
In the present embodiment, described water-swellable sealing collar rubber strip used is by the quality of rubber materials with water-swellable characteristic, meets water and start expansion and make waterproof, stagnant water effect better under expanded rubber effect.
When in PVC, pre-buried pvc pipe put into by pipe, the center of interior pipe and concrete embedded pipe to be ensured on the same axis as far as possible, before the filling carrying out asbestos cement sealant, need to carry out the process of brush polyurethane water-swellable water-stop glue to tube wall, asbestos cement sealant needs filling closely knit in interlayer, after completing filling, use water-repellent paint brushing, complete the work of pipeline spreading.

Claims (3)

1. pipe spreading shutoff leakage preventing structure in the pre-buried pvc pipe cover of concrete wall, pre-buried pvc pipe is inclined and mounted in impervious concrete barricade, in pre-buried pvc pipe, coaxial installation in PVC is managed, asbestos cement sealant is adopted to seal between pipe and pre-buried pvc pipe in this PVC, it is characterized in that: be coaxially installed with in the asbestos cement sealant in PVC between pipe and pre-buried pvc pipe and combine waterproof packed layer, the structure of this combination waterproof packed layer is: coaxial installation one hydro-expansive rubber sealing collar on pipe in the PVC in asbestos cement sealant, be symmetrically installed with spunyarn in asbestos cement sealant in the PVC of these hydro-expansive rubber sealing collar both sides between pipe and pre-buried pvc pipe and soak polyurethane water-swellable water stop gel ring.
2. pipe spreading shutoff leakage preventing structure in the pre-buried pvc pipe cover of concrete wall according to claim 1, is characterized in that: the hydro-expansive rubber sealing collar between spunyarn leaching polyurethane water-swellable water stop gel ring is clogged with a coaxial polyurethane water-swellable water-stop glue of installing between pre-buried PVC inwall.
3. in concrete wall according to claim 1 pre-buried pvc pipe cover, pipe spreading blocks up leakage preventing structure, it is characterized in that: in the external diameter of described pre-buried pvc pipe and PVC, the difference of the external diameter of pipe is not less than 5cm.
CN201420786415.1U 2014-12-11 2014-12-11 Pipe spreading shutoff leakage preventing structure in the pre-buried pvc pipe cover of a kind of concrete wall Expired - Fee Related CN204343326U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420786415.1U CN204343326U (en) 2014-12-11 2014-12-11 Pipe spreading shutoff leakage preventing structure in the pre-buried pvc pipe cover of a kind of concrete wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420786415.1U CN204343326U (en) 2014-12-11 2014-12-11 Pipe spreading shutoff leakage preventing structure in the pre-buried pvc pipe cover of a kind of concrete wall

Publications (1)

Publication Number Publication Date
CN204343326U true CN204343326U (en) 2015-05-20

Family

ID=53226604

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420786415.1U Expired - Fee Related CN204343326U (en) 2014-12-11 2014-12-11 Pipe spreading shutoff leakage preventing structure in the pre-buried pvc pipe cover of a kind of concrete wall

Country Status (1)

Country Link
CN (1) CN204343326U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105112652A (en) * 2015-08-10 2015-12-02 江西理工大学 Structure of channel for recovering in-situ leaching mother solution of rare earth ore
CN105673933A (en) * 2015-12-31 2016-06-15 中交第二航务工程局有限公司 Waterproof sealing device for post-through-wall pipeline and construction method
CN107143701A (en) * 2017-07-07 2017-09-08 上海民防建筑研究设计院有限公司 A kind of waterproof wall bushing
CN107191685A (en) * 2017-07-07 2017-09-22 上海民防建筑研究设计院有限公司 A kind of Novel civil air defense engineering tubular construction through walls
CN107313559A (en) * 2017-07-12 2017-11-03 南通市市政工程设计院有限责任公司 A kind of waterproof roof
CN110067384A (en) * 2018-01-22 2019-07-30 五冶集团上海有限公司 A kind of pvc pipe wears template provided pipe hole cavity construction method
CN115573373A (en) * 2022-10-21 2023-01-06 中国电建集团成都勘测设计研究院有限公司 Plugging device and method for underground concrete permeable wall

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105112652A (en) * 2015-08-10 2015-12-02 江西理工大学 Structure of channel for recovering in-situ leaching mother solution of rare earth ore
CN105673933A (en) * 2015-12-31 2016-06-15 中交第二航务工程局有限公司 Waterproof sealing device for post-through-wall pipeline and construction method
CN107143701A (en) * 2017-07-07 2017-09-08 上海民防建筑研究设计院有限公司 A kind of waterproof wall bushing
CN107191685A (en) * 2017-07-07 2017-09-22 上海民防建筑研究设计院有限公司 A kind of Novel civil air defense engineering tubular construction through walls
CN107313559A (en) * 2017-07-12 2017-11-03 南通市市政工程设计院有限责任公司 A kind of waterproof roof
CN107313559B (en) * 2017-07-12 2019-08-16 南通市市政工程设计院有限责任公司 A kind of waterproof roof
CN110067384A (en) * 2018-01-22 2019-07-30 五冶集团上海有限公司 A kind of pvc pipe wears template provided pipe hole cavity construction method
CN115573373A (en) * 2022-10-21 2023-01-06 中国电建集团成都勘测设计研究院有限公司 Plugging device and method for underground concrete permeable wall

Similar Documents

Publication Publication Date Title
CN204343326U (en) Pipe spreading shutoff leakage preventing structure in the pre-buried pvc pipe cover of a kind of concrete wall
CN202730973U (en) Concrete outer wall bolt hole leakproof structure
CN204343312U (en) Plugging device of precipitation well in foundation pit
CN105350953A (en) Measuring method for coal seam gas pressure in complicated geological condition
CN204703312U (en) A kind of outer shear wall bolt hole plugging structure
CN101666234A (en) Fracture rock no-slurry-blocking wall compound grouting construction method
CN101418641A (en) Obligate pore construction method for construction floor
CN107117910A (en) Waterproof material for building and preparation method thereof
CN104003673B (en) A kind of underground installation rigid-flexible composite waterproofing and leakage-stopping emulsion
CN113107018B (en) Method for treating leakage water of underground structure crack
CN103821114B (en) A kind of reservoir culvert method for blocking discarded under seepage pressure effect
CN107816361A (en) Tunnel rich water section partitioning waterproofing system
CN104058711B (en) A kind of water-proof building material
CN102002950B (en) Liquid division slip casting reinforcing method for subsurface structure construction joints
CN103276736B (en) Trailer-type high polymer grouting system
CN103452081B (en) A kind of construction method of flexible composite impermeable layer of upstream face of high arch dam
CN104278717A (en) Waterproof and drainage structure of sunken toilet
CN207513619U (en) Tunnel rich water section partitioning waterproofing system
CN103133785A (en) Water-proof processing structure of tube-penetrating position on wall
CN204420369U (en) A kind of linkage structure of large-caliber drainage pipeline
CN214429183U (en) Cable sleeve plugging structure with multi-layer combination of rigidity and flexibility
CN214117025U (en) Wear floor riser waterproof construction
CN204703169U (en) A kind of grouting machine for building
CN212318013U (en) Combined grouting structure suitable for rapidly plugging tunnel leakage
CN211776003U (en) Quick leaking stoppage system of concrete

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150520

Termination date: 20171211

CF01 Termination of patent right due to non-payment of annual fee