CN107191685A - A kind of Novel civil air defense engineering tubular construction through walls - Google Patents

A kind of Novel civil air defense engineering tubular construction through walls Download PDF

Info

Publication number
CN107191685A
CN107191685A CN201710552580.9A CN201710552580A CN107191685A CN 107191685 A CN107191685 A CN 107191685A CN 201710552580 A CN201710552580 A CN 201710552580A CN 107191685 A CN107191685 A CN 107191685A
Authority
CN
China
Prior art keywords
wall pipe
walls
air defense
civil air
tubular construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710552580.9A
Other languages
Chinese (zh)
Inventor
刘慧玲
储汇东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Civil Defence Building Research & Design Institute Co Ltd
Original Assignee
Shanghai Civil Defence Building Research & Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Civil Defence Building Research & Design Institute Co Ltd filed Critical Shanghai Civil Defence Building Research & Design Institute Co Ltd
Priority to CN201710552580.9A priority Critical patent/CN107191685A/en
Publication of CN107191685A publication Critical patent/CN107191685A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L5/00Devices for use where pipes, cables or protective tubing pass through walls or partitions
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L5/00Devices for use where pipes, cables or protective tubing pass through walls or partitions
    • F16L5/02Sealing
    • F16L5/04Sealing to form a firebreak device

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Building Environments (AREA)

Abstract

The present invention relates to a kind of Novel civil air defense engineering tubular construction through walls, including reinforced concrete wall, wall pipe, cable through walls and drag piece component, wherein, wall pipe is embedded in reinforced concrete wall, passed through for cable through walls, drag piece component is fixed on one end of wall pipe, the outer surface of wall pipe is fixed with anchor pole, drag piece component includes drag piece, screw rod and nut, wherein, drag piece abuts on the end face of wall pipe and is provided with through hole, one end of screw rod is connected on anchor pole, the other end of screw rod stretches out from through hole and coordinated with nut thread.The Novel civil air defense engineering tubular construction through walls of the present invention, omits welding operation, so as to avoid the cooperation of electric welding field work and other work posts operating personnel when can install at the scene, it is to avoid the narrow and small caused quality problems of site space.Moreover, the operational sequence is simple, project progress is drastically increased.

Description

A kind of Novel civil air defense engineering tubular construction through walls
Technical field
The present invention relates to civil air defense constructions and installations wall pipe, relate more specifically to a kind of Novel civil air defense engineering tubular construction through walls.
Background technology
There are various pipelines and wall passed through on the outside of the building into inside people's air defense protective zone in civil air defense constructions and installations, or from people One protective zone of preventing engineering enters another protective zone.According to civil air defense constructions and installations specification, civil air defense constructions and installations tubular construction through walls is needed It can prevent shock wave from being damaged to protective zone inside.
In the prior art, when civil air defense constructions and installations tubular construction through walls is included in in-site installation, by bolt electric welding on wall pipe. There are many problems in this method:Such as the more influence progress of process;Site operation narrow space is difficult to ensure that quality;Need electric welding Operation work and other work posts operating personnel cooperation etc..
The content of the invention
It is more and the problem of be difficult to ensure that quality in order to solve process that above-mentioned prior art is present, the present invention is intended to provide A kind of Novel civil air defense engineering tubular construction through walls.
Novel civil air defense engineering tubular construction through walls of the present invention, including reinforced concrete wall, wall pipe, cable through walls With drag piece component, wherein, wall pipe is embedded in reinforced concrete wall, is passed through for cable through walls, drag piece component quilt One end of wall pipe is fixed on, the outer surface of wall pipe is fixed with anchor pole, and drag piece component includes drag piece, screw rod and spiral shell Mother, wherein, drag piece is abutted on the end face of wall pipe and is provided with through hole, and one end of screw rod is connected on anchor pole, screw rod The other end stretched out from through hole and with nut thread coordinate.
The fire prevention for also including being packed in wall pipe fills out embedding.
It is additionally included in and closes on the fire prevention that the side of exterior wall is packed in wall pipe and fill out embedding and in the side for closing on protective zone The waterproof being packed in wall pipe fills out embedding.
Wall pipe is steel wall pipe.
Steel plate for sealing water is provided with the middle part of the outer surface of wall pipe.
Steel plate for sealing water is the circular ring structure for the outer surface for being welded in wall pipe.
Anchor pole is the reinforced anchor bolt of the one end for closing on protective zone for being welded on wall pipe.
Drag piece component also includes the pad being located between drag piece and nut.
Screw rod includes clamping ring and straight-bar, wherein, clamping ring is the circular ring structure being set on anchor pole, and straight-bar is from connection Enclose on the body of rod extended, the outer surface of the one end of the body of rod away from clamping ring and be provided with external screw thread.
Drag piece is stacked two panels drag piece.
The Novel civil air defense engineering tubular construction through walls of the present invention, omits welding operation, so as to avoid when can install at the scene The cooperation of electric welding field work and other work posts operating personnel, it is to avoid quality problems caused by site space is narrow and small.Moreover, the behaviour Make process simple, drastically increase project progress.
Brief description of the drawings
Fig. 1 is the overall schematic of Novel civil air defense engineering tubular construction through walls according to a preferred embodiment of the present invention;
Fig. 2 is the schematic diagram of Fig. 1 wall pipe;
Fig. 3 is Fig. 2 profile;
Fig. 4 is Fig. 1 region A enlarged drawing;
Fig. 5 is the schematic diagram of Fig. 1 screw rod;
Fig. 6 is the overall signal of Novel civil air defense engineering tubular construction through walls according to a further advantageous embodiment of the invention Figure.
Embodiment
Below in conjunction with the accompanying drawings, presently preferred embodiments of the present invention is provided, and is described in detail.
Fig. 1 is the overall schematic of Novel civil air defense engineering tubular construction through walls according to a preferred embodiment of the present invention, Including reinforced concrete wall 1, wall pipe 2, cable through walls 3, drag piece component 4, fire prevention fill out embedding 5 and waterproof fill out embedding 6.Wherein, Wall pipe 2 is embedded in reinforced concrete wall 1, is passed through for cable 3 through walls.In protective zone, drag piece component 4 is pacified Dress is fixed on one end of wall pipe 2.In wall pipe 2, the side for closing on exterior wall is packed with fire prevention and fills out embedding 5, empty closing on protection Between side be packed with waterproof and fill out embedding 6.The fire prevention fill out embedding 5 and waterproof fill out embedding 6 direct neighbor.
Fig. 2 is the schematic diagram of Fig. 1 wall pipe, and the wall pipe 2 is to be welded with only in the middle part of steel wall pipe, its outer surface Water steel plate 21.Fig. 3 is Fig. 2 profile, and the steel plate for sealing water 21 is the circular ring structure for the outer surface for being welded in steel wall pipe.Return To Fig. 2, one end for closing on protective zone of the outer surface of the wall pipe 2 is welded with anchor pole 22.In the present embodiment, the anchor pole 22 For a diameter of 6mm reinforced anchor bolt.Referring to Fig. 3, the anchor pole 22 is the cylindrical structure for being welded in steel tube outer surface through walls.
Fig. 4 is Fig. 1 region A enlarged drawing, and drag piece component 4 includes drag piece 41, screw rod 42, nut 43 and pad 44.Wherein, drag piece 41 is abutted on the protective zone inner face of wall pipe 2, and it is provided with through hole 411, the one of screw rod 42 End is connected on anchor pole 22, and the other end stretches out from through hole 411.Nut 43 is threaded in the remote anchor pole 22 of screw rod 42 On end.Pad 44 is arranged between drag piece 41 and nut 43.In this way, drag piece 41 is fastened to the end of wall pipe 2.
Fig. 5 is the schematic diagram of Fig. 1 screw rod, and the screw rod 42 includes clamping ring 421 and straight-bar 422, wherein, clamping ring 421 For circular ring structure, it can be set on anchor pole 22 so that the screw rod 42 is fixedly attached to anchor pole 22.Straight-bar 422 is from clamping ring Be provided with external screw thread on 421 bodies of rod extended, the outer surface of its one end away from clamping ring 421, thus with nut 43 Screw thread coordinates so that drag piece 41 can be fastened on to the end of wall pipe 2 by nut 43.
With reference to Fig. 1 and Fig. 4, the drag piece 41 is stacked two panels drag piece, in order to be better protected from shock wave to anti- Shield interior volume is damaged.In the relative both sides up and down of wall pipe 2, screw rod 42, nut 43 and pad 44 are symmetrically arranged with, So that drag piece 41 is fastened on the end of wall pipe 2 by uniform force.
At the scene in installation process, it is only necessary to screw rod 42 is passed through to the through hole 411 of drag piece 41, pad 44 is enclosed on into spiral shell On bar 42, nut 43 coordinates with the screw thread of screw rod 42, then the clamping ring 421 of screw rod 42 is enclosed on the anchor pole 22 of wall pipe 2, so After tighten nut 43.In this way, welding operation is omitted when can install at the scene, so as to avoid electric welding field work and other The cooperation of work post operating personnel, it is to avoid quality problems caused by site space is narrow and small.Moreover, the operational sequence is simple, greatly Ground improves project progress.
Fig. 6 is the overall signal of Novel civil air defense engineering tubular construction through walls according to a further advantageous embodiment of the invention Figure.It will not be repeated here with upper embodiment identical part, its difference is:The Novel civil air defense engineering tubular construction through walls Two protective zones are arranged on, therefore, it includes symmetrically arranged two sets of drag pieces component 4 ', and corresponding anchor pole 22 ' has four Root, and be only packed with fire prevention in wall pipe 2 ' and fill out embedding 5 '.
Above-described, only presently preferred embodiments of the present invention is not limited to the scope of the present invention, of the invention is upper Stating embodiment can also make a variety of changes.What i.e. every claims and description according to the present patent application were made Simply, equivalent changes and modifications, falls within the claims of patent of the present invention.The present invention not detailed description is Routine techniques content.

Claims (10)

1. a kind of Novel civil air defense engineering tubular construction through walls, including reinforced concrete wall, wall pipe, cable through walls and drag piece group Part, wherein, wall pipe is embedded in reinforced concrete wall, is passed through for cable through walls, and drag piece component is fixed on One end of wall pipe, it is characterised in that the outer surface of wall pipe is fixed with anchor pole, drag piece component include drag piece, screw rod and Nut, wherein, drag piece is abutted on the end face of wall pipe and is provided with through hole, and one end of screw rod is connected on anchor pole, spiral shell The other end of bar stretches out from through hole and coordinated with nut thread.
2. Novel civil air defense engineering tubular construction through walls according to claim 1, it is characterised in that also including being packed in wall pipe Interior fire prevention fills out embedding.
3. Novel civil air defense engineering tubular construction through walls according to claim 1, it is characterised in that be additionally included in and close on exterior wall The fire prevention that side is packed in wall pipe is filled out embedding and fills out embedding in the waterproof that the side for closing on protective zone is packed in wall pipe.
4. Novel civil air defense engineering tubular construction through walls according to claim 1, it is characterised in that wall pipe is that steel is through walls Pipe.
5. Novel civil air defense engineering tubular construction through walls according to claim 1, it is characterised in that in the outer surface of wall pipe Portion is provided with steel plate for sealing water.
6. Novel civil air defense engineering tubular construction through walls according to claim 5, it is characterised in that steel plate for sealing water is worn to be welded in The circular ring structure of the outer surface of wall coil.
7. Novel civil air defense engineering tubular construction through walls according to claim 1, it is characterised in that anchor pole is to be welded on wall pipe The one end for closing on protective zone reinforced anchor bolt.
8. Novel civil air defense engineering tubular construction through walls according to claim 1, it is characterised in that drag piece component also includes position Pad between drag piece and nut.
9. Novel civil air defense engineering tubular construction through walls according to claim 1, it is characterised in that screw rod includes clamping ring and straight Bar, wherein, clamping ring is the circular ring structure being set on anchor pole, and straight-bar is the body of rod extended from clamping ring, and the body of rod is away from even External screw thread is provided with the outer surface of one end of adapter ring.
10. Novel civil air defense engineering tubular construction through walls according to claim 1, it is characterised in that drag piece is stacked two Piece drag piece.
CN201710552580.9A 2017-07-07 2017-07-07 A kind of Novel civil air defense engineering tubular construction through walls Pending CN107191685A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710552580.9A CN107191685A (en) 2017-07-07 2017-07-07 A kind of Novel civil air defense engineering tubular construction through walls

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710552580.9A CN107191685A (en) 2017-07-07 2017-07-07 A kind of Novel civil air defense engineering tubular construction through walls

Publications (1)

Publication Number Publication Date
CN107191685A true CN107191685A (en) 2017-09-22

Family

ID=59883542

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710552580.9A Pending CN107191685A (en) 2017-07-07 2017-07-07 A kind of Novel civil air defense engineering tubular construction through walls

Country Status (1)

Country Link
CN (1) CN107191685A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108086542A (en) * 2017-11-10 2018-05-29 中建三局第二建设工程有限责任公司 A kind of concrete structure pipe construction through walls reserves structure and construction method
CN109577369A (en) * 2018-12-24 2019-04-05 惠州市人防工程设计院有限公司 Cannula structure and its construction method are gone along with sb. to guard him in a kind of people's air defense

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200961755Y (en) * 2006-09-29 2007-10-17 王金全 Pipeline protection closed device
CN201109995Y (en) * 2007-08-15 2008-09-03 北京住总集团有限责任公司 Assembled template being convenient for stacking
CN202560751U (en) * 2012-05-20 2012-11-28 朱一军 Novel bolt with two fixing holes
CN202706518U (en) * 2012-08-20 2013-01-30 汪玉平 Bracket type anti-skid cross-shaped fastener
CN203412883U (en) * 2013-06-04 2014-01-29 常州市金美机械制造有限公司 Stainless steel stud bolt
CN204343326U (en) * 2014-12-11 2015-05-20 中铁四局集团第三建设有限公司 Pipe spreading shutoff leakage preventing structure in the pre-buried pvc pipe cover of a kind of concrete wall
CN105351326A (en) * 2015-10-23 2016-02-24 舒城县博力非标异型紧固件厂 Military radar swing bolt and production process thereof
CN205400024U (en) * 2016-02-23 2016-07-27 广西大业建设集团有限公司 Instrument formula external scaffolding bolt that can dismantle used repeatedly links wall spare
CN206918422U (en) * 2017-07-07 2018-01-23 上海民防建筑研究设计院有限公司 A kind of Novel civil air defense engineering tubular construction through walls

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200961755Y (en) * 2006-09-29 2007-10-17 王金全 Pipeline protection closed device
CN201109995Y (en) * 2007-08-15 2008-09-03 北京住总集团有限责任公司 Assembled template being convenient for stacking
CN202560751U (en) * 2012-05-20 2012-11-28 朱一军 Novel bolt with two fixing holes
CN202706518U (en) * 2012-08-20 2013-01-30 汪玉平 Bracket type anti-skid cross-shaped fastener
CN203412883U (en) * 2013-06-04 2014-01-29 常州市金美机械制造有限公司 Stainless steel stud bolt
CN204343326U (en) * 2014-12-11 2015-05-20 中铁四局集团第三建设有限公司 Pipe spreading shutoff leakage preventing structure in the pre-buried pvc pipe cover of a kind of concrete wall
CN105351326A (en) * 2015-10-23 2016-02-24 舒城县博力非标异型紧固件厂 Military radar swing bolt and production process thereof
CN205400024U (en) * 2016-02-23 2016-07-27 广西大业建设集团有限公司 Instrument formula external scaffolding bolt that can dismantle used repeatedly links wall spare
CN206918422U (en) * 2017-07-07 2018-01-23 上海民防建筑研究设计院有限公司 A kind of Novel civil air defense engineering tubular construction through walls

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108086542A (en) * 2017-11-10 2018-05-29 中建三局第二建设工程有限责任公司 A kind of concrete structure pipe construction through walls reserves structure and construction method
CN109577369A (en) * 2018-12-24 2019-04-05 惠州市人防工程设计院有限公司 Cannula structure and its construction method are gone along with sb. to guard him in a kind of people's air defense

Similar Documents

Publication Publication Date Title
CN202936485U (en) Feeding device for underground pipeline system
CN103114722A (en) Three-sectional water stopping screw for basement exterior wall
CN107191685A (en) A kind of Novel civil air defense engineering tubular construction through walls
CN104088375B (en) Buckling restriction steel bar structure
CN206918422U (en) A kind of Novel civil air defense engineering tubular construction through walls
CN204185856U (en) Novel anti-floating anchor cable device
CN205577187U (en) Prefabricated steel pipe concrete constructional column rammed earth wall
CN204356774U (en) Bendable recoverable anchor rod
CN204112379U (en) Inclinometer pipe casing in supporting pile body
CN104278690A (en) Novel high-voltage power transmission line tower pile foundation
CN101892851B (en) Metal mine anchor rod support method
CN204385762U (en) A kind of Rock Bolt Foundation structure
CN210238643U (en) Rapid-forming type pipe well
CN209011146U (en) A kind of sky iron open caisson system
CN101532322A (en) Rectangular concrete filled beam with hollow steel tube
CN106168026A (en) Churning reaming type sub warhead recoverable anchor rod stake and manufacture method thereof
CN208717980U (en) The nozzle protective device of pre-buried inclinometer pipe in retaining wall
CN203907087U (en) Medium-and-low-pressure grouting quick joint device
CN110145129A (en) A kind of foundation bolt screw thread protective case in concrete
CN110568171A (en) method for detecting grouting fullness of pier connecting sleeve by applying water injection
CN104532873A (en) Rock anchor rod foundation structure
CN205421249U (en) Electric power construction is with multiway stock of scalable regulation
CN205188946U (en) Prevention of seepage water precast concrete tubular pile
CN204254026U (en) A kind of direct-buried pipeline shock insulation vibration damping equipment
CN203977968U (en) The vertical device turning to of a kind of fixedly iron tower of power transmission line group

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 201700 room 209, 2 story D, 2 building, 349 West Cen street, Qingpu District, Shanghai.

Applicant after: SHANGHAI CIVIL DEFENSE ARCHITECTURAL DESIGN & RESEARCH INSTITUTE CO.,LTD.

Address before: 200032 room 1302, 1223 Tu Tu Road, Xuhui District, Shanghai.

Applicant before: SHANGHAI CIVIL DEFENSE ARCHITECTURAL DESIGN & RESEARCH INSTITUTE CO.,LTD.

WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170922