CN103276736B - Trailer-type high polymer grouting system - Google Patents

Trailer-type high polymer grouting system Download PDF

Info

Publication number
CN103276736B
CN103276736B CN201310124800.XA CN201310124800A CN103276736B CN 103276736 B CN103276736 B CN 103276736B CN 201310124800 A CN201310124800 A CN 201310124800A CN 103276736 B CN103276736 B CN 103276736B
Authority
CN
China
Prior art keywords
trailer
high polymer
diaphragm pump
pneumatic diaphragm
slip casting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310124800.XA
Other languages
Chinese (zh)
Other versions
CN103276736A (en
Inventor
王复明
石明生
王小亮
何雷英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Anyuan Engineering Technology Co Ltd
Original Assignee
Safekey Engineering Technology Zhengzhou Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Safekey Engineering Technology Zhengzhou Ltd filed Critical Safekey Engineering Technology Zhengzhou Ltd
Priority to CN201310124800.XA priority Critical patent/CN103276736B/en
Publication of CN103276736A publication Critical patent/CN103276736A/en
Application granted granted Critical
Publication of CN103276736B publication Critical patent/CN103276736B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a kind of trailer-type high polymer grouting system, comprise trailer I, trailer I is equipped with air compressor, pneumatic diaphragm pump I is connected with air compressor respectively by gas rope with pneumatic diaphragm pump II, storage vat I and storage vat II trailer I be also equipped with, storage vat I is connected with pneumatic diaphragm pump I by conveying pipeline, storage vat II is connected with pneumatic diaphragm pump II by conveying pipeline, trailer I is also equipped with slip casting proportioning device, pneumatic diaphragm pump I is all connected with slip casting proportioning device by conveying pipeline with the discharging opening of pneumatic diaphragm pump II, the discharging opening of slip casting proportioning device is connected with grouting gun head by conveying pipeline.The present invention designs uniqueness, compact conformation, dependable performance, simple to operate, and job location can be hauled easily, there is the functions such as meticulous proportioning, high pressure mixing, temperature automatically controlled pressure control, for middle-size and small-size dykes and dams protection provides a whole set of high polymer grouting system with the high polymer grouting technology of traffic infrastructure, building reparation, demonstrate extremely strong practicality.

Description

Trailer-type high polymer grouting system
Technical field
The invention belongs to infrastructure reinforcing, antiseepage, the sprayings such as highway, water conservancy, building, particularly relate to a kind of trailer-type high polymer grouting system.
Background technology
Since founding of New, the infrastructure construction such as traffic, water conservancy, mine, environmental protection of China achieves remarkable achievement, has played important function to China's economic growth and social progress.Slurry injection technique is the Main Means of basement process, infrastructure project reinforcement and repair.Environment-friendly type macromolecule polymeric material and slurry injection technique thereof receive increasingly extensive concern at home and abroad, become study hotspot especially in the underground engineering constructions such as infrastructure protection and repair, tunnel and subway such as dyke, dam, speedway are speedily carried out rescue work etc.In recent years, the present inventor is under the multinomial plan of science and technology of country and Henan Province is supported, for growth requirement and the deficiency that exists of technology at present of the infrastructure anti-seepage reinforcings such as China's traffic, water conservancy and reparation, be devoted to the research and development of high polymer grouting technology, in anhydrous response high polymer grouting material behavior, slurry injection technique, construction equipment and engineering method, obtain system innovation achievement, define the engineering protection high polymer grouting complete set technology with China's independent intellectual property right.
In Transportation Infrastructure Construction, to the end of the year 2012, China's Mainland will build speedway 9.26 ten thousand kilometers, about have the speedway of 10% to enter the medium-capital overhauling phase every year.Road maintenance maintenance technique ensures usage capability of road and basic, the key technology in life-span.Traditional cement mud-jack, excavation change the method such as to fill out in maintenance effect, speed of application, cost and environmental protection etc., there is obviously deficiency, and particularly conventional method exists health requirement, causes long-time close traffic, does not meet the demand of speedway rapid-maintenance.Along with the fast development of high grade highway construction in China, day by day urgent to the demand of novel maintenance and repair technology.Under this engineering background, present inventors studied the repair mechanisms of the diseases such as anhydrous response dilatancy high polymer grouting material comes to nothing to road, ftractures, purt mud, based on anhydrous response high polymer material and Dynamic Non-Destruction Measurement, invent a whole set of technology of road rehabilitation high polymer grouting, start speedway no-dig technique maintenance new way.The mandate Chinese invention patent obtained has 5: " cement concrete road surface void identification and high polymer grouting rapid servicing technology (patent No.: ZL200710054045.7) ", " roadbed defect identification and high polymer grouting rapid reinforcement technology (patent No.: ZL200710054043.8) ", " Pavement on Semi-rigid Type Base Defect inspection and high polymer grouting rapid servicing technology (patent No.: ZL200710054044.2) ", " high polymer loading grouting method (patent No.: ZL200910172317.2) that roadbase is reinforced ", " Prevention of Bump at End of Bridge high polymer grouting technology and construction method (patent No.: ZL200910066336.7) thereof ".200910227697.5), " method for grouting polymers for tunnel protection (application number: 201010104839.1), " high polymer grouting technology for treating tunnel void and construction method (application number: 200910066333.3) thereof 3 patents of invention are separately had just on the docket: " Tunnel Water Leakage punishes method for grouting polymers (application number: fast.
In water resource infrastructure construction, because the most water conservancy projects of China was built 50 to the seventies of last century, be limited to economic technology condition at that time, many Design of Reservoirs and construction quality " inadequate natural endowment ".Through longtime running, long neglected and in disrepair, seriously aging, sick dangerous problem is very outstanding.At present, in China's 8.7 ten thousand dams, more than 90% is earth dam, wherein about 40% urgently reinforcement.There is potential safety hazard in more than 2000 tailing dam, a large amount of river levee.Seepage is the Focal point and difficult point of dykes and dams reinforcement.The existing impervious body built based on cement-based material is rigidity or plasticity, and antidetonation cracking resistance is not enough, and destroys comparatively large to dykes and dams disturbance, and the duration is longer, and cost is higher.Particularly for the middle-size and small-size dykes and dams of One's name is legion, limit by funds and construction plant, current art is difficult to practical requirement.The present inventor, from flexible barrier theory, proposes the new method building dyke seepage control body based on anhydrous response high polymer grouting material, has invented dykes and dams " Wicresoft " and has repaired complete set technology and equipment.Achievement in research obtains 3 U.S. patent Nos: " Directionalfracturegroutingmethodwithpolymerforseepageco ntrolofdikesanddams (the patent No.: US8, 182, 178B2) ", " Processforgroutingacurtainwithpolymer (the patent No.: US8, 272, 811B2) ", " Polymerinjectionmethodforblockingpipingindikesanddams (the patent No.: US8, 293, 325B2) " and 4 Chinese invention patents: " dam piping rescue high polymer closed grouting method (patent No.: ZL200910066332.9) ", " high polymer heavy curtain grouting technology (patent No.: ZL200910066335.2), " high polymer grouting directional splitting drilling tool and hole forming method (patent No.: ZL200910227699.4) ", " high polymer heavy curtain grouting drilling tool and casement construction method (patent No.: ZL200910227698.X) ".Separately there are 5 Chinese invention patents just on the docket: " dyke seepage control high polymer directional splitting grouting method (application number: 200910066334.8), " high polymer hoisting grouting method (application number: 201110288194.6), " grouting method for ultrathin high polymer cutoff wall (application number: 201110288192.7), " high polymer hoisting grouting control equipment (application number: 201110288196.5) ", " tri-cone-head pressing grooving plate and grouting slot construction method (application number: 201110288195.0) ".
The above-mentioned dykes and dams protection of the present inventor's invention repairs high polymer grouting technology with road, tunnel, bridge, there is advantages such as " fast, Wicresoft, durable, economy, environmental protection ", be successfully applied to the Important Project such as Yellow River dyke engineering, project of South-to-North water diversion, Beijing-Hongkong Australia speedway, Yichang-Wanzhou Railway, and economized in 300 multinomial dyke with defects or in danger reinforcements and speedway and tunnel protection reinstatement works in Henan, Hubei, Anhui, Hebei, Zhejiang, Jiangsu, Fujian, Yunnan etc. and be used widely.Compare with road rehabilitation reinforcing technique with existing dykes and dams, high polymer grouting technology not only saves the funds of more than 30%, and significantly saves the duration, and avoids the wasting of resources and environment pollution of excavating and keeping in repair and causing, and meets national energy-saving environmental protection development strategy demand.
Implement above-mentioned dykes and dams and protect the key of repairing high polymer grouting technology with road, tunnel, bridge how to carry out high polymer grouting.Existing cement mud-jack equipment pressure injection mostly be the typical cement-based material such as light silty sand, cement, water and water glass; What existing chemical grouting equipment was suitable for mostly is water response class polyurethane chemical grouting material, and wherein polyurethane chemical grouting material belongs to one-component water-swellable high molecular polymer.And high polymer grouting technical basis repaired by the dykes and dams protection of the present inventor's invention and road, tunnel, bridge is the theory of " anhydrous slip casting ", " flexible barrier ", employing be anhydrous response class pair component high-molecular polymer novel slurry filling material.Because its course of reaction does not need the participation of water, thus all can apply having in water and water-less environment, there is applicability widely.Anhydrous response class double component high polymer injecting paste material requires that grouting equipment has the functions such as meticulous proportioning, high pressure mixing, temperature automatically controlled pressure control, material is fully reacted, and carries out slip casting by the micropore of 15mm.Can find out, no matter be existing cement mud-jack equipment, or chemical grouting equipment all cannot meet the requirement of high polymer grouting technology for grouting equipment function of the present inventor's research and development.Therefore, in order to implement the high polymer grouting technology that above-mentioned a series of invention relates to, the double component high polymer precise micropore filling system with functions such as meticulous proportioning, high pressure mixing, temperature automatically controlled pressure controls need be researched and developed.
Summary of the invention
The dykes and dams protection that the object of the invention is for inventor's invention repairs high polymer grouting technology with road, tunnel, bridge, a kind of trailer-type high polymer grouting system being conveniently applicable to the protection of middle-size and small-size dykes and dams and repairing with road, tunnel, bridge, high ferro, building is provided, there is the functions such as meticulous proportioning, high pressure mixing, temperature automatically controlled pressure control.
For achieving the above object, the present invention adopts following technical scheme: a kind of trailer-type high polymer grouting system, comprise trailer I, trailer I is equipped with air compressor, pneumatic diaphragm pump I is connected with air compressor respectively by gas rope with pneumatic diaphragm pump II, storage vat I and storage vat II trailer I be also equipped with, storage vat I is connected with pneumatic diaphragm pump I by conveying pipeline, storage vat II is connected with pneumatic diaphragm pump II by conveying pipeline, trailer I is also equipped with slip casting proportioning device, pneumatic diaphragm pump I is all connected with slip casting proportioning device by conveying pipeline with the discharging opening of pneumatic diaphragm pump II, the discharging opening of slip casting proportioning device is connected with grouting gun head by conveying pipeline.
Also comprise air nozzle, air nozzle is connected with air compressor by gas rope.
Trailer I is also equipped with generator, and air compressor is connected by cable with generator, and slip casting proportioning device is also connected with generator by cable.
Trailer I is also equipped with power supply base, and power supply base is connected with generator by cable.
Also comprise trailer II, trailer II is connected with trailer I, and trailer II is equipped with generator, and air compressor is connected by cable with generator, and slip casting proportioning device is also connected with generator by cable.
Trailer I is also equipped with power supply base, and power supply base is connected with generator by cable.
Trailer II is also equipped with power supply base, and power supply base is connected with generator by cable.
The present invention designs uniqueness, compact conformation, dependable performance, simple to operate, and job location can be hauled easily, for high polymer grouting technology provides reliable a whole set of high polymer grouting system, and be successfully applied to the high polymer Grouting engineerings such as traffic, water conservancy, building, demonstrate its extremely strong practicality and irreplaceability.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention.
Detailed description of the invention
Trailer-type high polymer grouting system as shown in Figure 1, comprise trailer I 1A, trailer I 1A is equipped with air compressor 4, the air inlet port 10 of pneumatic diaphragm pump I 6 is connected with air compressor 4 by gas rope 11, the air inlet port 13 of pneumatic diaphragm pump II 7 is connected with air compressor 4 by gas rope 11, valve 5 gas rope 11 is equipped with, storage vat I 14A and storage vat II 14B trailer I 1A is also equipped with, storage vat I 14A is connected with pneumatic diaphragm pump I 6 by conveying pipeline I 16, storage vat II 14B is connected with pneumatic diaphragm pump II 5 by conveying pipeline II 15, trailer I 1A is also equipped with slip casting proportioning device 19, the discharging opening 9 of pneumatic diaphragm pump I 14A is connected with slip casting proportioning device 19 by conveying pipeline III 17, the discharging opening 12 of pneumatic diaphragm pump II 14B is connected with slip casting proportioning device 19 by conveying pipeline IV 18, the discharging opening 21 of slip casting proportioning device 19 is connected with grouting gun head 25 by conveying pipeline V 22.Also comprise air nozzle 24, air nozzle 24 is connected with air compressor 4 by gas rope.
Also comprise trailer II 1B, trailer II 1B is connected with trailer I 1A, and trailer II 1B is equipped with generator 2, and air compressor 4 is connected with the output 3 of generator 2 by cable 8, slip casting proportioning device 19 is also connected with generator 2 by cable, useful electric switch 20 on slip casting proportioning device.Trailer II is also equipped with power supply base 23, and power supply base 23 is connected with the output 3 of generator 2 by cable.Certainly, also power supply base 23 can be contained on trailer I, or respectively power supply base be installed on trailer I with trailer II.
In addition, if trailer I is enough large, also can not use trailer II, but generator is also contained on trailer I, air compressor is connected by cable with generator, and slip casting proportioning device is also connected with generator by cable.Trailer I also installs power supply base, and power supply base is connected with generator by cable.
The course of work of the present invention is:
(1) generator is opened, after working well, start power supply;
(2) open power switch, generator is powered respectively to air compressor and slip casting proportioning device and power supply base;
(3) air compressor electric switch is opened, air compressor work, and to pneumatic diaphragm pump and grouting gun head air feed;
(4) storage vat I and storage vat II feed valve is opened respectively;
(5) open slip casting proportioning device power switch, start slip casting proportioning device, and to slip casting proportioning device parameters, slip casting proportioning device normally works;
(6) slip casting position is determined, fixing connection between grouting gun head and Grouting Pipe;
(7) grouting gun head trigger is pulled, two pneumatic diaphragm pumps are started working, carry two kinds of different liquid high polymer grouting materials to slip casting proportioning device, by being transported in grouting gun head mixing chamber after the heating of slip casting proportioning device, proportioning, two kinds of liquid high polymer materials are through mixing jet gun head;
(8) the mixing material high polymer material sprayed, is transported to slip casting position by Grouting Pipe, freezing by expansion after high polymer material generation chemical reaction.

Claims (5)

1. a trailer-type high polymer grouting system, it is characterized in that: comprise trailer I, trailer I is equipped with air compressor, pneumatic diaphragm pump I is connected with air compressor respectively by gas rope with pneumatic diaphragm pump II, storage vat I and storage vat II trailer I be also equipped with, in storage vat I and storage vat II, different liquid high polymer grouting materials is housed, storage vat I is connected with pneumatic diaphragm pump I by conveying pipeline, storage vat II is connected with pneumatic diaphragm pump II by conveying pipeline, trailer I is also equipped with slip casting proportioning device, pneumatic diaphragm pump I is all connected with slip casting proportioning device by conveying pipeline with the discharging opening of pneumatic diaphragm pump II, the discharging opening of slip casting proportioning device is connected with grouting gun head by conveying pipeline, also comprise air nozzle, air nozzle is connected with air compressor by gas rope, trailer I is also equipped with generator, and air compressor is connected by cable with generator, and slip casting proportioning device is also connected with generator by cable.
2. trailer-type high polymer grouting system as claimed in claim 1, is characterized in that: trailer I is also equipped with power supply base, and power supply base is connected with generator by cable.
3. trailer-type high polymer grouting system as claimed in claim 1, it is characterized in that: also comprise trailer II, trailer II is connected with trailer I, and trailer II is equipped with generator, air compressor is connected by cable with generator, and slip casting proportioning device is also connected with generator by cable.
4. trailer-type high polymer grouting system as claimed in claim 3, is characterized in that: trailer I is also equipped with power supply base, and power supply base is connected with generator by cable.
5. trailer-type high polymer grouting system as claimed in claim 3, is characterized in that: trailer II is also equipped with power supply base, and power supply base is connected with generator by cable.
CN201310124800.XA 2013-04-11 2013-04-11 Trailer-type high polymer grouting system Active CN103276736B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310124800.XA CN103276736B (en) 2013-04-11 2013-04-11 Trailer-type high polymer grouting system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310124800.XA CN103276736B (en) 2013-04-11 2013-04-11 Trailer-type high polymer grouting system

Publications (2)

Publication Number Publication Date
CN103276736A CN103276736A (en) 2013-09-04
CN103276736B true CN103276736B (en) 2016-01-20

Family

ID=49059342

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310124800.XA Active CN103276736B (en) 2013-04-11 2013-04-11 Trailer-type high polymer grouting system

Country Status (1)

Country Link
CN (1) CN103276736B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104047430B (en) * 2013-10-10 2016-05-04 江苏鼎泰工程材料有限公司 A kind of vehicular slip casting complete set of equipments
CN104594294B (en) * 2014-12-01 2016-04-20 安徽瑞迪工程科技有限公司 The method that canal seepage is repaired and equipment-seepage repair machine thereof
CN106761834A (en) * 2017-01-10 2017-05-31 济南中铁重工轨道装备有限公司 A kind of split type secondary grouting system of shield machine
US20180266416A1 (en) 2017-03-20 2018-09-20 Recyca-Pipe Of America L.L.C. Grouting material delivery and application system
CN110424396A (en) * 2019-08-30 2019-11-08 郑州安源工程技术有限公司 A kind of crawler type whitewashing integrated system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2091325A (en) * 1980-06-17 1982-07-28 Mcalpine & Sons Ltd Sir Robert Underwater grouting apparatus
JPH04146325A (en) * 1990-10-09 1992-05-20 Masahiro Kitanaka Slime removing device in pile hole
CN201485853U (en) * 2009-09-04 2010-05-26 广东水电二局股份有限公司 High-pressure injecting and grouting system with construction quality monitoring equipment
CN201599041U (en) * 2010-02-25 2010-10-06 中铁十四局集团有限公司 Synchronous slip casting device for shielding machine
CN202031099U (en) * 2010-10-29 2011-11-09 浙江宝业建设集团有限公司 Oblique slip casting machine
CN203213115U (en) * 2013-04-11 2013-09-25 河南博特工程防护有限公司 Trailer type high polymer grouting system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2091325A (en) * 1980-06-17 1982-07-28 Mcalpine & Sons Ltd Sir Robert Underwater grouting apparatus
JPH04146325A (en) * 1990-10-09 1992-05-20 Masahiro Kitanaka Slime removing device in pile hole
CN201485853U (en) * 2009-09-04 2010-05-26 广东水电二局股份有限公司 High-pressure injecting and grouting system with construction quality monitoring equipment
CN201599041U (en) * 2010-02-25 2010-10-06 中铁十四局集团有限公司 Synchronous slip casting device for shielding machine
CN202031099U (en) * 2010-10-29 2011-11-09 浙江宝业建设集团有限公司 Oblique slip casting machine
CN203213115U (en) * 2013-04-11 2013-09-25 河南博特工程防护有限公司 Trailer type high polymer grouting system

Also Published As

Publication number Publication date
CN103276736A (en) 2013-09-04

Similar Documents

Publication Publication Date Title
CN111485922B (en) Method for treating water leakage, block falling and slurry turning of ELF railway tunnel
CN103276735B (en) Integrated form high polymer grouting system
Li et al. Protection against water or mud inrush in tunnels by grouting: a review
CN103276736B (en) Trailer-type high polymer grouting system
US20160169435A1 (en) Polymer composite grouting method for blocking leaking and sand inrush of underground pipelines
CN103556639B (en) Construction method for underwater non-dispersible cement-based self-compaction material
CN103161470A (en) Construction method for shield machine to penetrate through large caliber pipeline in long distance
CN104612134A (en) Cast-in place pile post-grouting construction method for pouring construction
CN110130936B (en) Construction method for sudden encountering untreated karst cave or crack in shield tunneling process
CN101788082A (en) Construction method for abutting jack pipe underground
CN112412496A (en) Full-section advanced curtain grouting construction method for water-rich broken geological zone tunnel
CN103215922A (en) High-pressure high-flow centralized leakage grouting leaking stoppage method
CN103696416A (en) Novel foundation treatment method
CN203213115U (en) Trailer type high polymer grouting system
CN203213116U (en) Integrated type high polymer grouting system
CN104032713B (en) A kind of pressure diversion tunnel composite lining concrete anti-seepage structure and construction technology thereof
CN103174135A (en) Repair method of unqualified post-grouting bored concrete pile
CN101768982B (en) Method and device for eliminating water burst,shifting sand danger of underground building curtain
CN204343286U (en) A kind of steel pipe pile support
CN105672203A (en) Blocking construction method for dyke-dam reinforced concrete culvert pipe
CN104612240A (en) Method for blocking large-pipe-diameter rainwater pipeline through short air bag
CN214614083U (en) Grouting assembly for repairing quality defects of karst geological cast-in-place pile
CN109503016A (en) Acrylates with magnetosensitive thickening power reinforces the application method of slurries
CN108755721A (en) A kind of novel cofferdam method for protecting support for crossing piping lane construction in water river
CN103114601A (en) Cut-off method of rapid-hardening high-spray grouting of strong leakage stratum and device thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20151119

Address after: The two North Road, South eight North four Avenue West port linkage 450000 Henan province Zhengzhou City Economic and Technological Development Zone

Applicant after: Zhengzhou Anyuan Engineering Technology Co., Ltd.

Address before: High tech Zone in Henan province Zhengzhou City, Tsui Chuk Street 450000 No. 100 and No. 10 Liyuan Sheng Yuan Building 1 unit 8

Applicant before: Henan Bote Engineering Protection Co., Ltd.

C14 Grant of patent or utility model