CN204252020U - Bridge engineering coping construction bracket - Google Patents

Bridge engineering coping construction bracket Download PDF

Info

Publication number
CN204252020U
CN204252020U CN201420616223.6U CN201420616223U CN204252020U CN 204252020 U CN204252020 U CN 204252020U CN 201420616223 U CN201420616223 U CN 201420616223U CN 204252020 U CN204252020 U CN 204252020U
Authority
CN
China
Prior art keywords
bracket
main
truss
pin
main chords
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420616223.6U
Other languages
Chinese (zh)
Inventor
陈先均
伍永泽
唐和容
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN201420616223.6U priority Critical patent/CN204252020U/en
Application granted granted Critical
Publication of CN204252020U publication Critical patent/CN204252020U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of bridge engineering Coping Construction bracket, comprise several truss, described truss comprises upper and lower two main chords be parallel to each other and is arranged on the web member coupled together between upper and lower two main chords and by upper and lower two main chords, main chord and web member are all the square steel being connect welding by two channel-section steels and formed, and couple together between the main chord of left and right two adjacent truss with splicing construction.Bracket of the present utility model compared with hood type bracket, be less likely to occur glide, worker stands on bracket during operation security performance greatly improve; Bracket of the present utility model is compared with full hall formula bracket, and splicing is more simple, and splicing number of times is few, substantially reduces the engineering time, reduces construction cost; Simultaneously because bracket of the present utility model utilizes channel-section steel to process, add and only need man-hour to carry out blanking by size, and then carry out welding, should draw materials and process, with low cost, practicality is high, is easy to promote.

Description

Bridge engineering Coping Construction bracket
Technical field
The utility model relates to a kind of bridge engineering Coping Construction bracket.
Background technology
In bridge engineering, Coping Construction bracket majority adopts hood type bracket or full hall formula bracket, hood type bracket utilizes to install anchor ear at the suitable position of bridge pier, and make it to be clamped on bridge pier, produce maximum stiction, overcome the weight of temporory structure and bent cap, the safety of this hood type bracket is bad, easily glides; Full hall formula bracket is spliced with a large amount of steel pipe, and the engineering time is long, and cost is high, is only suitable for the Coping Construction of particular/special requirement, as tunnel etc.
Utility model content
For the deficiencies in the prior art, the purpose of this utility model is to provide a kind of bridge engineering Coping Construction bracket, to make up poor stability, engineering time length, high in cost of production defect that existing bracket exists.
In order to solve the problems of the technologies described above, the utility model have employed following technical scheme:
A kind of bridge engineering Coping Construction bracketcomprise several truss, described truss comprises upper and lower two main chords be parallel to each other and is arranged on the web member coupled together between upper and lower two main chords and by upper and lower two main chords, main chord and web member are all the square steel being connect welding by two channel-section steels and formed, and couple together between the main chord of left and right two adjacent truss with splicing construction.
Preferably, described splicing construction comprises subrack and latch, and described subrack is arranged between two main chords of left and right two adjacent truss, and the two ends of subrack are inserted in left and right two main chords respectively; The splicing position of left and right two main chords all has the pin-and-hole perpendicular to its length direction, in the pin-and-hole of left and right two main chords, insert latch respectively, and latch is locked with pin after running through main chord; The two ends of subrack have the perforation corresponding with pin-and-hole, and the latch on left and right two main chords runs through the two ends of subrack respectively.
Preferably, arrange stiffener in the both sides at main chord splicing position, described stiffener has the perforation corresponding with pin-and-hole, and latch runs through the stiffener of both sides and is locked with the stiffener of pin by both sides.
The beneficial effects of the utility model are:
When constructing, first in the perforation of bridge column, reinforcing bar is inserted, and then bracket is set up on reinforcing bar, workman can stand directly on operation on platform bracket, compared with hood type bracket, bracket of the present utility model is set up on the reinforcing bar of bridge pier, be less likely to occur glide, worker stands on bracket during operation security performance greatly improve; Compared with full hall formula bracket, bracket of the present utility model is spliced by several truss, couples together during splicing with the main chord of splicing construction by adjacent truss, splice simpler, splicing number of times is few, substantially reduces the engineering time, reduces construction cost; Simultaneously because bracket of the present utility model utilizes channel-section steel to process, add and only need man-hour to carry out blanking by size, and then carry out welding, should draw materials and process, with low cost, practicality is high, is easy to promote.
Accompanying drawing explanation
Fig. 1 is the constitutional diagram of the present embodiment truss;
Fig. 2 is the A-A sectional drawing of Fig. 1;
Fig. 3 is the front view of truss the first from left section in Fig. 1;
Fig. 4 is the lateral view of truss the first from left section in Fig. 1;
Fig. 5 is the sectional drawing of corresponding position in Fig. 3;
Fig. 5 a is along the sectional drawing that A-A line is cut open in Fig. 3;
Fig. 5 b is along the sectional drawing that B-B line is cut open in Fig. 3;
Fig. 5 c is along the sectional drawing that C-C line is cut open in Fig. 3;
Fig. 6 is the front view of truss the second from left section in Fig. 1;
Fig. 7 is the front view of truss the second from left section in Fig. 1;
Fig. 8 is the sectional drawing of corresponding position in Fig. 6.
Fig. 8 a is along the sectional drawing that A-A line is cut open in Fig. 6;
Fig. 8 b is along the sectional drawing that B-B line is cut open in Fig. 6;
Fig. 8 c is along the sectional drawing that C-C line is cut open in Fig. 6.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model is described in further detail.
See Fig. 1-8c, bridge engineering Coping Construction bracket of the present utility model is spliced by some sections of truss, the quantity of truss depends on the length of bridge, truss comprises upper and lower two main chords be parallel to each other 11 and is arranged on the web member coupled together between upper and lower two main chords 11 and by upper and lower two main chords, web member comprises vertical web member 12 and inclination web member 13, and main chord 11, vertical web member 12 and inclination web member 13 are all the square steel being connect welding by two channel-section steels and formed.
The bridge engineering Coping Construction bracket of the present embodiment is spliced mutually by truss the first from left section 1, truss the second from left section 2, two section 3, the truss right side and right one section 4 of truss, wherein, couple together with splicing construction between the main chord 11 of left and right two adjacent truss, splicing construction comprises subrack 5 and latch 6, subrack 5 is arranged between two main chords 11 of left and right two adjacent truss, and the two ends of subrack 5 are inserted in left and right two main chords 11 respectively; The splicing position of left and right two main chords 11 all has the pin-and-hole perpendicular to its length direction, inserts latch 6 respectively, insert pin lock dead after latch 6 runs through main chord 11 in the pin-and-hole of latch 6 front end in the pin-and-hole of left and right two main chords 11; The two ends of subrack 5 have the perforation corresponding with pin-and-hole, latch 6 on left and right two main chords runs through the two ends of subrack 5 respectively, because the two ends of subrack 5 are locked on left and right two main chords 11 by latch 6, therefore left and right two main chords 11 are coupled together by subrack 5.
In order to increase bonding strength, the both sides can also splicing position at main chord 11 arrange stiffener 14, stiffener 14 have the perforation corresponding with pin-and-hole, latch 6 inserts pin after running through the stiffener 14 of both sides in the pin-and-hole of latch 6 front end, is locked at by stiffener 14 on the two sides of main chord 11.
Finally it should be noted that, above embodiment is only in order to illustrate the technical solution of the utility model but not restriction technologies scheme, although applicant has been described in detail the utility model with reference to preferred embodiment, those of ordinary skill in the art is to be understood that, those are modified to the technical solution of the utility model or equivalent replacement, and do not depart from aim and the scope of the technical program, all should be encompassed in the middle of right of the present utility model.

Claims (3)

1. one kind bridge engineering Coping Construction bracketit is characterized in that, comprise several truss, described truss comprises upper and lower two main chords be parallel to each other and is arranged on the web member coupled together between upper and lower two main chords and by upper and lower two main chords, main chord and web member are all the square steel being connect welding by two channel-section steels and formed, and couple together between the main chord of left and right two adjacent truss with splicing construction.
2. according to claim 1 bridge engineering Coping Construction bracket, it is characterized in that, described splicing construction comprises subrack and latch, and described subrack is arranged between two main chords of left and right two adjacent truss, and the two ends of subrack are inserted in left and right two main chords respectively; The splicing position of left and right two main chords all has the pin-and-hole perpendicular to its length direction, in the pin-and-hole of left and right two main chords, insert latch respectively, and latch is locked with pin after running through main chord; The two ends of subrack have the perforation corresponding with pin-and-hole, and the latch on left and right two main chords runs through the two ends of subrack respectively.
3. according to claim 1 bridge engineering Coping Construction bracket, it is characterized in that, arrange stiffener in the both sides at main chord splicing position, described stiffener has the perforation corresponding with pin-and-hole, and latch runs through the stiffener of both sides and is locked with the stiffener of pin by both sides.
CN201420616223.6U 2014-10-23 2014-10-23 Bridge engineering coping construction bracket Active CN204252020U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420616223.6U CN204252020U (en) 2014-10-23 2014-10-23 Bridge engineering coping construction bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420616223.6U CN204252020U (en) 2014-10-23 2014-10-23 Bridge engineering coping construction bracket

Publications (1)

Publication Number Publication Date
CN204252020U true CN204252020U (en) 2015-04-08

Family

ID=52956345

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420616223.6U Active CN204252020U (en) 2014-10-23 2014-10-23 Bridge engineering coping construction bracket

Country Status (1)

Country Link
CN (1) CN204252020U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105484157A (en) * 2015-11-19 2016-04-13 宁波交通工程建设集团有限公司 Positioning device and construction method of capping beam of prefabricated bridge

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105484157A (en) * 2015-11-19 2016-04-13 宁波交通工程建设集团有限公司 Positioning device and construction method of capping beam of prefabricated bridge
CN105484157B (en) * 2015-11-19 2017-04-26 宁波交通工程建设集团有限公司 Positioning device and construction method of capping beam of prefabricated bridge

Similar Documents

Publication Publication Date Title
CN203080736U (en) Combined profile steel box-shaped steel plate shear wall
CN103572708B (en) Large-span concrete continuous girder bridge side span folding device and method
WO2017020685A1 (en) Prefabricated t beam steel die
CN106192717A (en) Bridge steel and concrete mixing section and installation method thereof
CN204252020U (en) Bridge engineering coping construction bracket
CN206034265U (en) Steel reinforced concrete of bridge combines section
CN102966032B (en) A kind of structural member of aluminum alloy passenger foot-bridge
CN201991229U (en) Combined fixture of beam
CN204754945U (en) Mine method tunnel preliminary bracing lining cutting grid steel support make
CN104594533A (en) Adjustable flexible connecting structure for masonry filler wall and frame column
CN203530864U (en) Large-span concrete continuous beam bridge side span folding device
CN204418433U (en) A kind of adjustable masonry filler wall and frame column flexible connecting structure
CN202031309U (en) Suspending operation platform for structural concrete constructions
CN206015686U (en) A kind of internal support of foundation pit device
CN105464584A (en) Manufacturing method of water conservancy project detachable ladder stand
CN210947661U (en) Installation device of socket type overhanging scaffold
CN208792806U (en) A kind of floor of steel structure transformation node
CN203559432U (en) Underground powerhouse vault
CN202945540U (en) Aluminum alloy structural member for pedestrian overcrossing
CN205296525U (en) Lower hanging steel bar truss structure
CN205617580U (en) Assembled primary and secondary roof beam connection structure
CN206468021U (en) A kind of new type foldable plate bracing frame
CN201525697U (en) Crane bridge
CN104047379A (en) Steel tube bundle composite structure shear wall field splice node
CN203603260U (en) Light stable connecting structure of prefabricated building wall beam

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant