CN201991229U - Combined fixture of beam - Google Patents

Combined fixture of beam Download PDF

Info

Publication number
CN201991229U
CN201991229U CN2011200009239U CN201120000923U CN201991229U CN 201991229 U CN201991229 U CN 201991229U CN 2011200009239 U CN2011200009239 U CN 2011200009239U CN 201120000923 U CN201120000923 U CN 201120000923U CN 201991229 U CN201991229 U CN 201991229U
Authority
CN
China
Prior art keywords
square tube
jig
bolt
hole
stupefied
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011200009239U
Other languages
Chinese (zh)
Inventor
曲荆海
谢远人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ANGANG CONSTRUCTION CONSORTIUM Co Ltd
Original Assignee
ANGANG CONSTRUCTION CONSORTIUM Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANGANG CONSTRUCTION CONSORTIUM Co Ltd filed Critical ANGANG CONSTRUCTION CONSORTIUM Co Ltd
Priority to CN2011200009239U priority Critical patent/CN201991229U/en
Application granted granted Critical
Publication of CN201991229U publication Critical patent/CN201991229U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to a combined fixture of a beam, which comprises a beam bottom fixture, a beam side fixture, a right-angled standby ridge support, a movable standby ridge fixture and self-locking bolts, wherein the beam bottom fixture and the beam side fixture are vertical to each other and are fixed together by the self-locking bolts; two ends of the right-angled standby ridge support are respectively connected with the beam bottom fixture and the beam side fixture by the self-locking bolts; and the movable standby ridge fixture is arranged on the beam side fixture. The combined fixture of the beam has reasonable structural deign and low cost, is convenient and flexible in use, and can be widely applied to the field of construction technology.

Description

The beam combined clamp appts
Technical field
The utility model relates to a kind of building operations instrument, particularly relates to a kind of beam combined clamp appts.
Background technology
At present, the template of using in the building operations often can only be used once, causes construction cost than higher, and gang form generally adopts wooden structures, if in-situ processing is improper, causes fire easily, thereby has brought great potential safety hazard to construction.In the prior art, template and accessory thereof that some are made through special process also appear, but this template processing and manufacturing difficulty, cost is higher, and weight is big, is not suitable for a large amount of uses.
Summary of the invention
The utility model has overcome deficiency of the prior art, provides a kind of simple in structure, and cost is low, lightweight beam combined clamp appts.
In order to address the above problem, the utility model by the following technical solutions:
The beam combined clamp appts comprises that jig at the bottom of the beam, beam group jig, right angle are equipped with stupefied support, activity is equipped with stupefied jig and Bolt with latching action, and jig is mutual vertical with beam group jig and be fixed together by Bolt with latching action at the bottom of the beam; The right angle is equipped with stupefied support two ends and helps jig to be connected by Bolt with latching action with jig at the bottom of the beam and beam respectively; Activity is equipped with stupefied jig and is installed on the beam group jig.
Jig comprises square tube and tube connector at the bottom of two beams at the bottom of the described beam, and square tube is parallel to each other at the bottom of two beams, is connected and fixed by tube connector between the square tube at the bottom of two beams, and square tube is provided with installing hole at the bottom of the beam, and installing hole is a through hole.
Described beam is helped jig to comprise beam group's square tube and is equipped with stupefied groove, and the cross section of beam group square tube is a rectangle; Wide of beam group square tube is provided with high surely hole, and leptoprosopy is provided with tie rod hole; Fixed high hole and tie rod hole are respectively through hole, and being equipped with stupefied groove is the L shaped steel plate, are equipped with the end that stupefied groove one end is fixed on beam group square tube; Bolt with latching action passes respectively that square tube is fixed together at the bottom of square tube and beam are helped with beam in the Fixed width hole of square tube at the bottom of the fixed high hole of beam group square tube and the beam.
Described right angle is equipped with stupefied support and comprises the short tube support and be connected clamp, the short tube support is the square tube of rectangle for the cross section, short tube supports the fixedly connection clamp of pair of L type of termination portion both sides, the other end is provided with connecting hole at the bottom of the beam, the Connection Card front edge of board is provided with beam group connecting hole, the short tube support is connected with jig at the bottom of the beam by Bolt with latching action, connects clamp and helps jig to be connected by Bolt with latching action and beam.
Described activity is equipped with stupefied jig and comprises square tube skeleton and two-sided inserted link, the square tube skeleton is by rectangular pipe, short square tube and be connected square tube and form, connecting the square tube two ends is connected with short square tube vertical fixing with rectangular pipe respectively, the length of rectangular pipe is greater than the length of short square tube, two-sided inserted link vertically inserts short square tube, and stretch out outside the short square tube at two-sided inserted link two ends.
Described Bolt with latching action comprises bolt rod and locking bar, bolt rod adopts the round steel of L type structure to make, the bolt rod head is provided with gap, the bolt rod of gap upper and lower is provided with pin-and-hole, locking bar adopts round steel to make, the locking bar head is platy structure and is provided with the bar shaped groove, is connected and fixed in the gap of locking bar head insertion bolt rod head and by steady pin and bolt rod.
Compared with prior art, the beneficial effects of the utility model are:
1, the utility model is made simply, and cost is low, and easy installation and removal is reusable, has saved construction cost greatly, has improved operating efficiency.
2, the utility model instrument adopts steel material to make, and is not yielding, not only improved work quality, also reduced the danger of breaking out of fire, thereby ensured site operation personnel's safety.
Description of drawings
Fig. 1 is the utility model structural representation;
Fig. 2 is a jig structural representation at the bottom of the beam;
Fig. 3 is beam group jig structural representation;
Fig. 4 is stupefied support structure schematic diagram for the right angle is equipped with;
Fig. 5 is stupefied jig structural representation for activity is equipped with;
Fig. 6 is the Bolt with latching action structural representation.
The specific embodiment
The beam combined clamp appts as shown in Figure 1, comprises that jig 1 at the bottom of the beam, beam group jig 3, right angle are equipped with stupefied support 2, activity is equipped with stupefied jig 4 and Bolt with latching action 5, and jig 1 and beam group jig 3 are mutual vertical and be fixed together by Bolt with latching action 5 at the bottom of the beam; The right angle is equipped with stupefied support 2 two ends and helps jig 3 to be connected by Bolt with latching action 5 with jig at the bottom of the beam 1 and beam respectively; Activity is equipped with stupefied jig 4 and is installed on the beam group jig 3.
As shown in Figure 2, jig 1 comprises at the bottom of two beams that square tube 6 is parallel to each other at the bottom of the square tube 6 and 7, two beams of tube connector at the bottom of the beam, is connected and fixed by tube connector 7 between the square tube 6 at the bottom of two beams, and square tube 6 is provided with installing hole at the bottom of the beam, and installing hole is a through hole.
As shown in Figure 3, beam group jig 3 comprises beam group square tube 9 and is equipped with stupefied groove 12 that the cross section of beam group square tube 9 is a rectangle; Wide of beam group square tube 9 is provided with high surely hole 10, and leptoprosopy is provided with tie rod hole 11; Fixed high hole 10 and tie rod hole 11 are respectively through hole, are equipped with stupefied groove 12 and are the L shaped steel plate, are equipped with the end that stupefied groove 12 1 ends are fixed on beam group square tube 9; Bolt with latching action 5 passes respectively that square tube 6 is fixed together at the bottom of square tube 9 and beam are helped with beam in the Fixed width hole 8 of square tube 6 at the bottom of the fixed high hole 10 of beam group square tube 9 and the beam.
As shown in Figure 4, the right angle is equipped with stupefied support 2 and comprises short tube support 13 and be connected clamp 14, short tube support 13 is the square tube of rectangle for the cross section, short tube supports the fixedly connection clamp 14 of pair of L type of 13 1 termination portion both sides, the other end is provided with connecting hole 16 at the bottom of the beam, connection clamp 14 front ends are provided with beam group connecting hole 15, and short tube support 13 is connected with jig at the bottom of the beam 1 by Bolt with latching action 5, and connection clamp 14 passes through Bolt with latching action 5 and beam group jig 3 is connected.
As shown in Figure 5, activity is equipped with stupefied jig 4 and comprises square tube skeleton and two-sided inserted link 20, the square tube skeleton is by rectangular pipe 17, short square tube 19 and be connected square tube 18 and form, connecting square tube 18 two ends is connected with short square tube 19 vertical fixing with rectangular pipe 17 respectively, the length of rectangular pipe 17 is greater than the length of short square tube 19, the two-sided inserted link 20 vertical weak point square tubes 19 of inserting, stretch out outside the short square tube 19 at two-sided inserted link 20 two ends.
As shown in Figure 6, Bolt with latching action 5 comprises bolt rod 21 and locking bar 22, bolt rod 21 adopts the round steel of L type structure to make, bolt rod 21 heads are provided with gap, the bolt rod 21 of gap upper and lower is provided with pin-and-hole 23, locking bar 22 adopts round steel to make, and locking bar 22 heads are platy structure and are provided with bar shaped groove 24, is connected and fixed in the gap of locking bar 22 heads insertion bolt rod 21 heads and by steady pin and bolt rod 21.
During use, help jig 3 to be put at the bottom of two beams of jig 11 at the bottom of the beam in the space between the square tube 6 on beam, note being equipped with the direction of stupefied groove 12 simultaneously, according to the wide of beam with highly select eyelet and together insert Bolt with latching action 5, again the right angle is equipped with at the bottom of the stupefied support 2 corresponding beams and beam group jig 3 corresponding holes and insert Bolt with latching action 5, beam group has just formed up and down that twice are equipped with stupefied groove 12 like this, when the higher needs of beam are equipped with when stupefied again, activity is equipped with stupefied jig 4 is inserted in the beam group jig 3 corresponding fixed high holes 10 and can finishes.

Claims (6)

1. the beam combined clamp appts is characterized in that, comprises that jig at the bottom of the beam, beam group jig, right angle are equipped with stupefied support, activity is equipped with stupefied jig and Bolt with latching action, and jig is mutual vertical with beam group jig and be fixed together by Bolt with latching action at the bottom of the beam; The right angle is equipped with stupefied support two ends and helps jig to be connected by Bolt with latching action with jig at the bottom of the beam and beam respectively; Activity is equipped with stupefied jig and is installed on the beam group jig.
2. beam combined clamp appts according to claim 1 is characterized in that, jig comprises square tube and tube connector at the bottom of two beams at the bottom of the described beam, square tube is parallel to each other at the bottom of two beams, be connected and fixed by tube connector between the square tube at the bottom of two beams, square tube is provided with installing hole at the bottom of the beam, and installing hole is a through hole.
3. beam combined clamp appts according to claim 1 and 2 is characterized in that, described beam is helped jig to comprise beam group's square tube and is equipped with stupefied groove, and the cross section of beam group square tube is a rectangle; Wide of beam group square tube is provided with high surely hole, and leptoprosopy is provided with tie rod hole; Fixed high hole and tie rod hole are respectively through hole, and being equipped with stupefied groove is the L shaped steel plate, are equipped with the end that stupefied groove one end is fixed on beam group square tube; Bolt with latching action passes respectively that square tube is fixed together at the bottom of square tube and beam are helped with beam in the Fixed width hole of square tube at the bottom of the fixed high hole of beam group square tube and the beam.
4. beam combined clamp appts according to claim 1, it is characterized in that, described right angle is equipped with stupefied support and comprises the short tube support and be connected clamp, the short tube support is the square tube of rectangle for the cross section, short tube supports the fixedly connection clamp of pair of L type of termination portion both sides, and the other end is provided with connecting hole at the bottom of the beam, and the Connection Card front edge of board is provided with beam group connecting hole, the short tube support is connected with jig at the bottom of the beam by Bolt with latching action, connects clamp and helps jig to be connected by Bolt with latching action and beam.
5. beam combined clamp appts according to claim 1, it is characterized in that, described activity is equipped with stupefied jig and comprises square tube skeleton and two-sided inserted link, the square tube skeleton is by rectangular pipe, short square tube and be connected square tube and form, connecting the square tube two ends is connected with short square tube vertical fixing with rectangular pipe respectively, the length of rectangular pipe is greater than the length of short square tube, and two-sided inserted link vertically inserts short square tube, and stretch out outside the short square tube at two-sided inserted link two ends.
6. beam combined clamp appts according to claim 1, it is characterized in that, described Bolt with latching action comprises bolt rod and locking bar, bolt rod adopts the round steel of L type structure to make, the bolt rod head is provided with gap, and the bolt rod of gap upper and lower is provided with pin-and-hole, and locking bar adopts round steel to make, the locking bar head is platy structure and is provided with the bar shaped groove, is connected and fixed in the gap of locking bar head insertion bolt rod head and by steady pin and bolt rod.
CN2011200009239U 2011-01-04 2011-01-04 Combined fixture of beam Expired - Fee Related CN201991229U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011200009239U CN201991229U (en) 2011-01-04 2011-01-04 Combined fixture of beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011200009239U CN201991229U (en) 2011-01-04 2011-01-04 Combined fixture of beam

Publications (1)

Publication Number Publication Date
CN201991229U true CN201991229U (en) 2011-09-28

Family

ID=44667718

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011200009239U Expired - Fee Related CN201991229U (en) 2011-01-04 2011-01-04 Combined fixture of beam

Country Status (1)

Country Link
CN (1) CN201991229U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104153574A (en) * 2014-07-04 2014-11-19 张梁 Quick beam formwork supporting die
CN105888240A (en) * 2016-06-01 2016-08-24 山东兴华建设集团有限公司 Reinforcing clamping apparatus for building cross beam
CN106351442A (en) * 2016-08-30 2017-01-25 福州市第三建筑工程公司 Beam-side double-cantilever short column frame
CN111022765A (en) * 2019-12-13 2020-04-17 深圳海油工程水下技术有限公司 Installation frame for sea pipe maintenance equipment

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104153574A (en) * 2014-07-04 2014-11-19 张梁 Quick beam formwork supporting die
CN105888240A (en) * 2016-06-01 2016-08-24 山东兴华建设集团有限公司 Reinforcing clamping apparatus for building cross beam
CN106351442A (en) * 2016-08-30 2017-01-25 福州市第三建筑工程公司 Beam-side double-cantilever short column frame
CN106351442B (en) * 2016-08-30 2019-02-26 福州市第三建筑工程公司 A kind of beam side is double to choose short column frame
CN111022765A (en) * 2019-12-13 2020-04-17 深圳海油工程水下技术有限公司 Installation frame for sea pipe maintenance equipment
CN111022765B (en) * 2019-12-13 2021-05-28 深圳海油工程水下技术有限公司 Installation frame for sea pipe maintenance equipment

Similar Documents

Publication Publication Date Title
CN202380713U (en) Connecting structure of scaffold and scaffold adopting same
CN201991229U (en) Combined fixture of beam
CN205476441U (en) Concrete wall template structure
CN103362298A (en) Mobile tower scaffold with circular disc connecting device
CN202064635U (en) Formwork forming fastener
CN204938791U (en) A kind of support connecting structure of tower crane support beam
CN202767483U (en) Multifunctional bailey piece
CN202430823U (en) Detachable steel bar processing protective shed
CN203403537U (en) Beam column connection structure
CN210260903U (en) Assembled type safety passage for tower crane driver to walk
CN203834686U (en) Corrugated web H-shaped steel beam and column connecting structure
CN203403539U (en) Novel beam column connecting structure
CN210827837U (en) Beam column connecting structure
CN202689560U (en) Fixing device and vertical template system
CN201857755U (en) Interlocking combined type concrete plate formwork support grid
CN203403576U (en) Assembly-type parking lot floor plate of full steel structure
CN205846443U (en) Low-voltage complete switch equipment column connecting tee structure
CN210508535U (en) Large steel truss
CN204690956U (en) A kind of high-strength steel structure support beam
CN215888579U (en) Roof girder steel connected node structure
CN204552069U (en) A kind of novel combination type scaffold
CN204590617U (en) The universal connection boots of large form support system
CN203569880U (en) Scaffold connecting mechanism
CN210977255U (en) Assembled steel structure ladder frame
CN203654745U (en) Stiff structure formwork bolt pull rod connecting piece

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110928

Termination date: 20150104

EXPY Termination of patent right or utility model