CN204212162U CN201420544377.9U CN201420544377U CN204212162U CN 204212162 U CN204212162 U CN 204212162U CN 201420544377 U CN201420544377 U CN 201420544377U CN 204212162 U CN204212162 U CN 204212162U
Authority
CN
China
Prior art keywords
hole
side slope
criss
grouting
grouting reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420544377.9U
Other languages
Chinese (zh)
Inventor
袁新和
李博
李证吉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau Fifth Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau Fifth Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau Fifth Construction Engineering Co Ltd filed Critical China Construction Fourth Bureau Fifth Construction Engineering Co Ltd
Priority to CN201420544377.9U priority Critical patent/CN204212162U/en
Application granted granted Critical
Publication of CN204212162U publication Critical patent/CN204212162U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model discloses a kind of side slope grouting reinforcement structure, it is drilled with the hole be criss-cross arranged in side slope, in the hole that these are criss-cross arranged, be inserted with grouting tube form network, after being extracted by floral tube after floral tube grouting reinforcement, again linked network reinforcing bar and anchor spraying concrete are set on side slope surface; The described hole be criss-cross arranged comprises vertical hole (1) and horizontal cross hole (2).The novel this structure of ability is by means of being anchored in the soil body after injecting grout through steel perforated pipe, become as a whole after suspended net shotcrete, the pulling force produced sliding area passes to stable region, and then improve the shear strength of soil layer, and the passive earth pressure that reinforcement material can provide by means of soil layer on slide plane, generation shearing and moment of flexure, to resist the slip of active region, reach the object of stable excavation face.

Description

A kind of side slope grouting reinforcement structure
Technical field
The utility model relates to a kind of side slope grouting reinforcement structure, belongs to slope retaining technical field in construction work.
Background technology
The problem of slope retaining is often run in civil engineering, conventional support pattern mainly anchor pole, soil nailing, anchor rope lattice beam, castinplace pile, retaining wall or other combination supporting method, but this kind of support pattern is used for backfill side slope, construction plant is nervous, top, slope (toe) is close to the harsh foundation ditch condition of other buildings (building foundation) and inapplicable, for backfill, above-mentioned support pattern compliance is all poor, and the existence of network of underground also make retaining wall or castinplace pile lack scope for their abilities, therefore, slope retaining problem under the harsh foundation ditch conditions such as backfill side slope still fails to find a kind of technical solution preferably.
Utility model content
The purpose of this utility model is to provide a kind of side slope grouting reinforcement structure, is close to slope retaining problem under the harsh foundation ditch conditions such as other buildings (building foundation) to solve, top, slope (toe) nervous in backfill side slope, construction plant.
The utility model is a kind of side slope grouting reinforcement structure, it is drilled with the hole be criss-cross arranged in side slope, in the hole that these are criss-cross arranged, be inserted with grouting tube form network, after being extracted by floral tube after floral tube grouting reinforcement, again linked network reinforcing bar and anchor spraying concrete are set on side slope surface; The described hole be criss-cross arranged comprises vertical hole and horizontal cross hole.
The principle that general principle of the present utility model and anchor pole stablize the soil body is similar.Namely by means of being anchored in the soil body after injecting grout through steel perforated pipe, become as a whole after suspended net shotcrete, the pulling force produced sliding area passes to stable region, and then improve the shear strength of soil layer, and the passive earth pressure that reinforcement material can provide by means of soil layer on slide plane, generation shearing and moment of flexure, to resist the slip of active region, reach the object of stable excavation face.The uneven soil pressure in active area produced during soil mass of foundation pit excavation is by concrete pavement and steel floral tube anchoring body, finally bear by steel floral tube anchor pole, the pit accident of excavation slope and resistance to overturning also realize the reinforcing of the soil body eventually through steel floral tube, thus solve, slope top (toe) nervous in backfill side slope, construction plant and be close to slope retaining problem under the harsh foundation ditch conditions such as other buildings (building foundation).The utility model structure is simple, and it is convenient to implement, and is worthy to be popularized.
Accompanying drawing explanation
Fig. 1 is vertical hole, wall top arrangement diagram;
Fig. 2 is that wall front level is to hole arrangement diagram;
Fig. 3 is duct, wall side arrangement diagram;
Fig. 4 is slope retaining structure phantom drawing;
Fig. 5 is construction process figure.
The vertical hole of being labeled as in accompanying drawing: 1-; 2-horizontal cross hole.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is described in further detail.
As Figure 1-4, this structure of the present utility model is in side slope, be drilled with the staggered hole of solid crossbar, comprise the vertical hole 1 and horizontal cross hole 2 arranged in groups, grouting tube is plugged in hole, each duct organizing vertical hole 1 and horizontal cross hole 2 ensures at grade, forms a kind of lattice and supports.First carry out the construction in vertical hole 1 when construction, then carry out the construction in horizontal cross hole 2.
During the utility model construction, as shown in Figure 5, need before construction first to carry out Slope Design and cloth hole, determining hole position and pitch of holes, then carry out being drilled with of vertical hole 1 and horizontal cross hole 2 by group successively.First measurement and positioning during boring, then by place for rig telephone-moving and start boring, after having holed, steel floral tube is stretched in hole, on the other hand simultaneously, water, cement, fine sand are formed slurries after stirring and filtering, and being in the milk to floral tube in the scene delivered to by slurries, extracts floral tube after being in the milk, slurries and slope soil are consolidated, namely complete this hole after reaching design grout standard and construct and carry out next hole construction.This work at grade, forms a kind of lattice and supports.First vertical hole is carried out when construction
Certainly, more than just embody rule example of the present utility model, the technical scheme that the utility model also has other embodiment, all employings to be equal to replacement or equivalent transformation to be formed, all drops within the protection domain required by the utility model.

Claims (1)

1. a side slope grouting reinforcement structure, it is characterized in that: it is drilled with the hole be criss-cross arranged in side slope, in the hole that these are criss-cross arranged, be inserted with grouting tube form network, after being extracted by floral tube after floral tube grouting reinforcement, again linked network reinforcing bar and anchor spraying concrete are set on side slope surface; The described hole be criss-cross arranged comprises vertical hole (1) and horizontal cross hole (2).
CN201420544377.9U 2014-09-22 2014-09-22 A kind of side slope grouting reinforcement structure Expired - Fee Related CN204212162U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420544377.9U CN204212162U (en) 2014-09-22 2014-09-22 A kind of side slope grouting reinforcement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420544377.9U CN204212162U (en) 2014-09-22 2014-09-22 A kind of side slope grouting reinforcement structure

Publications (1)

Publication Number Publication Date
CN204212162U true CN204212162U (en) 2015-03-18

Family

ID=52980848

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420544377.9U Expired - Fee Related CN204212162U (en) 2014-09-22 2014-09-22 A kind of side slope grouting reinforcement structure

Country Status (1)

Country Link
CN (1) CN204212162U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104947694A (en) * 2015-05-18 2015-09-30 兰泽民 Earth slope grouting reinforcement construction method
CN107419734A (en) * 2017-06-26 2017-12-01 深圳宏业基岩土科技股份有限公司 The netted retaining structure of deep welding with filler wire
CN108625894A (en) * 2018-06-25 2018-10-09 山东科技大学 The waste filling solid grouting construction method of the flat working face of shortwall lane water acquisition
CN108661705A (en) * 2018-06-25 2018-10-16 山东科技大学 Item adopts goaf quaternity comprehensive treatment construction method
CN113152419A (en) * 2021-01-12 2021-07-23 四川省交通建设集团股份有限公司 Method for reinforcing roadbed at transition section behind bridge and culvert abutment by using miniature steel pipe piles

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104947694A (en) * 2015-05-18 2015-09-30 兰泽民 Earth slope grouting reinforcement construction method
CN107419734A (en) * 2017-06-26 2017-12-01 深圳宏业基岩土科技股份有限公司 The netted retaining structure of deep welding with filler wire
CN107419734B (en) * 2017-06-26 2020-12-11 深圳宏业基岩土科技股份有限公司 Netted retaining structure of deep side slope that bankets
CN108625894A (en) * 2018-06-25 2018-10-09 山东科技大学 The waste filling solid grouting construction method of the flat working face of shortwall lane water acquisition
CN108661705A (en) * 2018-06-25 2018-10-16 山东科技大学 Item adopts goaf quaternity comprehensive treatment construction method
CN113152419A (en) * 2021-01-12 2021-07-23 四川省交通建设集团股份有限公司 Method for reinforcing roadbed at transition section behind bridge and culvert abutment by using miniature steel pipe piles

Similar Documents

Publication Publication Date Title
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
CN204212162U (en) A kind of side slope grouting reinforcement structure
CN103422501B (en) Anti-floating anchor rod structure in sand seam geology and construction method thereof
CN105155550B (en) Construction method for digging deep foundation pit in large-thickness highly weathered sandstone stratum in combined supporting mode
CN102518135A (en) Foundation pit support construction method combining horizontal rotary jet-grouting soil bolting and bore concrete piles
CN106948340B (en) A kind of construction method of the Manual excavated pile structure of high polymer grouting protection
CN104532868B (en) High abrupt change shape sloped region bridge anchor pull-type high cap pile group basis construction method
CN102864781A (en) Foundation pit supporting method utilizing inclined piles
CN109930609A (en) A kind of campshed composite supporting construction and its construction method for upper-soft lower-hard ground
CN105421445A (en) Construction method for non-prestressed centrifugal high-strength concrete pile planted pile
CN102330436B (en) Composite retaining structure and composite retaining method for half geotechnical layer ultradeep round spiral flow tank
CN104131566B (en) A kind of basement is without the construction method of horizontal support foundation ditch
WO2021004007A1 (en) Foundation reinforcement method for conventional building
CN205954638U (en) Half semi -rigid flexible supporting construction of deep basal pit lateral wall
CN110397059A (en) A kind of compound tree root pile constructing process of preexisting hole stiffness
CN205576957U (en) Stake end pilework
CN208996052U (en) The drilling tool of supporting construction and use that foundation pit anchor wall draws anchor supporting to be formed
CN216515701U (en) Miniature stake raft board combination foundation structure
CN203684222U (en) Pile-anchor combined supporting structure with rotary jet enlarging head pre-stressed anchor rods
CN102943480A (en) Loess foundation pit supporting method
CN106638611A (en) Micro steel pipe pile-anchor combined support construction method
CN101818495A (en) Construction method for retaining and protecting foundation excavation and supporting structure thereof
CN108914947A (en) Foundation pit anchor wall draws the construction method of anchor supporting and its supporting construction of drilling tool and formation
CN205296177U (en) Dado bearing structure suitable for hole friction pile stake hole is dug in manual work
CN107447775A (en) Landslide disaster body makes ground draining reinforced earth retaining wall structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150318