CN204151701U - Single column pier bridge adds steel structure support overturning or slip resistance analysis bracing means - Google Patents
Single column pier bridge adds steel structure support overturning or slip resistance analysis bracing means Download PDFInfo
- Publication number
- CN204151701U CN204151701U CN201420603900.0U CN201420603900U CN204151701U CN 204151701 U CN204151701 U CN 204151701U CN 201420603900 U CN201420603900 U CN 201420603900U CN 204151701 U CN204151701 U CN 204151701U
- Authority
- CN
- China
- Prior art keywords
- wedge
- steel structure
- column pier
- single column
- bracket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 51
- 239000010959 steel Substances 0.000 title claims abstract description 51
- 239000000126 substance Substances 0.000 claims abstract description 13
- 238000000034 method Methods 0.000 abstract description 11
- 238000010276 construction Methods 0.000 abstract description 10
- 230000002787 reinforcement Effects 0.000 abstract description 10
- 238000009415 formwork Methods 0.000 abstract description 3
- 239000003351 stiffener Substances 0.000 description 7
- 238000010586 diagram Methods 0.000 description 4
- 238000006073 displacement reaction Methods 0.000 description 4
- 238000009434 installation Methods 0.000 description 4
- 238000003466 welding Methods 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000000246 remedial effect Effects 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
本实用新型公开了一种独柱墩桥梁附加钢结构支撑抗倾覆加固装置,包括钢结构牛腿和支座顶升装置;钢结构牛腿增设于独柱墩两侧,并通过化学锚栓与独柱墩连接形成扁担梁,其上安装支座顶升装置和桥梁支座。钢结构牛腿由钢板焊接组合而成,可工厂制作现场安装,能保证制作的质量和精度,钢结构牛腿与独柱墩用化学锚栓连接,施工过程不需立模,简单的脚手架即可施工,且不影响正常交通。支座顶升装置安装简便易行,免去了千斤顶顶升梁体安装桥梁支座的繁琐过程,一个扳手即可将桥梁支座安装就位。
The utility model discloses an additional steel structure supporting anti-overturning reinforcement device for a single-column pier bridge, which comprises a steel structure corbel and a support jacking device; The single-column piers are connected to form a pole beam, on which the support jacking device and bridge support are installed. The steel structure corbel is welded and combined by steel plates, which can be manufactured and installed on site, which can ensure the quality and precision of the production. The steel structure corbel and the single-column pier are connected by chemical anchor bolts. The construction process does not require formwork, and simple scaffolding can Construction is possible without affecting normal traffic. The support lifting device is easy to install, eliminating the cumbersome process of jacking up the beam body to install the bridge support, and the bridge support can be installed in place with a wrench.
Description
技术领域technical field
本实用新型涉及一种桥梁加固装置,尤其是能防止独柱墩桥梁倾覆的加固装置。The utility model relates to a bridge reinforcement device, in particular to a reinforcement device capable of preventing single-pillar pier bridges from overturning.
背景技术Background technique
独柱墩桥梁以占据桥下净空小,外形简洁流畅、轻巧美观等特点,被广泛应用于互通立交处,但由于结构本身抗倾覆性能不良,在超载偏心荷载作用下,独柱墩桥梁可能发生整体横向失稳从而导致梁体倾覆。独柱墩桥梁在使用过程中已发生多起倾覆事故,造成了人员伤亡和经济损失,为了采取补救措施,近两年我国对大量独柱墩桥梁进行了抗倾覆加固。Single column pier bridges are widely used in interchanges because of their small clearance under the bridge, simple and smooth appearance, and light and beautiful appearance. However, due to the poor anti-overturning performance of the structure itself, single column pier bridges may occur The overall lateral instability caused the beam body to overturn. There have been many overturning accidents of bridges with single-pillar piers during their use, resulting in casualties and economic losses. In order to take remedial measures, a large number of bridges with single-pillar piers have been reinforced against overturning in the past two years.
为了保证现有独柱墩桥梁的结构安全,应采取有效手段消除独柱墩结构发生倾覆的安全隐患。常见的方法有两种:一种是将独柱墩改为壁式实体墩,然后顶升梁体,在原支座两侧各安装一个附加支座,以达到抗倾覆的效果;第二种是将独柱墩改造为3柱墩,顶升梁体,在新墩柱上安装附加支座。以上两种方法均需立模浇筑混凝土,甚至需要打桩,施工工艺复杂,施工时间长,且受桥下净空的限制,特别是斜交的情况下,改为3柱墩几乎不可能。另外,附加支座需采取梁体顶升工艺才能安装就位,施工过程需中断交通,这使得现有独柱墩桥梁的抗倾覆加固变得复杂且容易受到应用范围的限制。In order to ensure the structural safety of existing single-pillar pier bridges, effective measures should be taken to eliminate the potential safety hazards of single-pillar pier structure overturning. There are two common methods: one is to change the single-column pier into a wall-type solid pier, then lift the beam body, and install an additional support on both sides of the original support to achieve the anti-overturning effect; the second is Transform the single-column pier into a three-column pier, jack up the beam body, and install additional supports on the new pier columns. Both of the above two methods require vertical casting of concrete, and even piling. The construction process is complicated, the construction time is long, and it is limited by the clearance under the bridge. Especially in the case of oblique intersection, it is almost impossible to change to a three-column pier. In addition, the additional support needs to be installed in place by beam jacking process, and the traffic needs to be interrupted during the construction process, which makes the anti-overturning reinforcement of existing single-pillar bridges complicated and easily limited by the scope of application.
发明内容Contents of the invention
为了克服现有独柱墩桥梁在超载偏心荷载作用下容易发生倾覆的不足,本实用新型提供了一种独柱墩桥梁附加钢结构支撑抗倾覆加固装置,该装置不仅能够有效抵抗偏载引起的倾覆力矩,而且结构简单、安装便捷,施工过程不影响正常交通。In order to overcome the disadvantage that existing single-pillar bridges are prone to overturning under the action of overload and eccentric loads, the utility model provides an additional steel structure support anti-overturning reinforcement device for single-pillar bridges. The overturning moment, and the structure is simple, the installation is convenient, and the construction process does not affect the normal traffic.
为了解决上述技术问题,本实用新型采用的如下技术方案:In order to solve the problems of the technologies described above, the utility model adopts the following technical solutions:
一种独柱墩桥梁附加钢结构支撑抗倾覆加固装置,其特征是:所述加固装置包括钢结构牛腿1和支座顶升装置2;钢结构牛腿1增设于独柱墩两侧,并通过化学锚栓9与独柱墩连接形成扁担梁,其上安装支座顶升装置2和桥梁支座3。An additional steel structure support anti-overturning reinforcement device for a single-column pier bridge, characterized in that: the reinforcement device includes a steel structure corbel 1 and a support jacking device 2; the steel structure corbel 1 is added on both sides of the single-column pier, And through the chemical anchor bolt 9 is connected with the single-column pier to form a pole beam, on which the support jacking device 2 and the bridge support 3 are installed.
作为优选,所述的钢结构牛腿1由牛腿腹板4、牛腿翼缘板5和牛腿加劲肋6焊接组合而成,牛腿腹板4上开有化学锚栓孔8,钢结构牛腿1通过化学锚栓9固定在独柱墩上,牛腿联系板7将两侧钢结构牛腿1联接成整体。。As a preference, the steel structure corbel 1 is welded and combined by corbel web 4, corbel flange plate 5 and corbel stiffener 6, chemical anchor holes 8 are opened on the corbel web 4, the steel structure The corbel 1 is fixed on the single-column pier through chemical anchor bolts 9, and the corbel connecting plate 7 connects the steel structure corbels 1 on both sides into a whole. .
所述支座顶升装置由支座板、楔形块装置和楔形块支撑肋板组成,通过转动调节螺栓,可调整楔形块的位置,进而抬升支座板,顶升桥梁支座。The support jacking device is composed of a support plate, a wedge block device and a wedge support rib plate. By turning the adjusting bolt, the position of the wedge block can be adjusted, and then the support plate is lifted to lift the bridge support.
所述的支座板由支座垫板10和垫板底楔形肋11焊接组成,两者通过焊接连接,顶升桥梁支座3时,座板挡板14将限制支座板的水平位移,支座板只能竖向移动,施工过程中桥梁支座3不会产生剪切变形。The support plate is composed of the support plate 10 and the wedge-shaped rib 11 at the bottom of the support plate, and the two are connected by welding. When the bridge support 3 is lifted, the seat plate baffle 14 will limit the horizontal displacement of the support plate. The bearing plate can only move vertically, and the bridge bearing 3 will not produce shear deformation during the construction process.
所述的楔形块装置由楔形块、调节螺栓16和座板挡板14组成;楔形块为格构式结构,由楔形肋12、楔形板限位块13和楔形块加劲肋15焊接组成,楔形板限位块13焊接在楔形肋12内侧,长度稍短于楔形肋12之间的净间距;调节螺栓16焊接在楔形块侧面,座板挡板14焊接在钢结构牛腿1端部。The wedge block device is composed of a wedge block, an adjusting bolt 16 and a seat plate baffle 14; the wedge block is a lattice structure, and is composed of a wedge rib 12, a wedge plate limit block 13 and a wedge stiffener 15 welded, and the wedge shape The plate limit block 13 is welded on the inner side of the wedge-shaped rib 12, and the length is slightly shorter than the net distance between the wedge-shaped ribs 12; the adjustment bolt 16 is welded on the side of the wedge-shaped block, and the seat plate baffle 14 is welded on the end of the steel structure corbel 1.
所述的楔形块支撑肋板17焊接于钢结构牛腿1顶部,用于支撑楔形块并起到限位作用。The wedge supporting ribs 17 are welded to the top of the steel structure corbel 1 for supporting the wedge and playing a position-limiting role.
独柱墩两侧的牛腿腹板4间浇筑有混凝土,与钢结构牛腿1形成完整的抗倾覆受力体系。Concrete is poured between the four corbel webs on both sides of the single-column pier, forming a complete anti-overturning force system with the steel structure corbel 1.
本实用新型是在独柱墩桥梁的梁底横桥向设置钢结构支撑,用以抵抗偏载引起的倾覆力矩。具体措施如下:在独柱墩两侧横桥向增设钢结构牛腿,钢结构牛腿与独柱墩通过化学锚栓连接形成扁担梁,并在其上安装支座顶升装置和桥梁支座;两侧牛腿腹板之间应浇筑混凝土,以增加钢结构牛腿的刚度,形成完整的抗倾覆受力体系;最后通过支座顶升装置将桥梁支座安装到位。In the utility model, a steel structure support is arranged at the bottom of the beam of the single-pillar pier bridge in the transverse direction to resist the overturning moment caused by the eccentric load. The specific measures are as follows: Add steel structure corbels on both sides of the single-column pier in the direction of the bridge, the steel structure corbels and the single-column pier are connected by chemical anchor bolts to form a pole beam, and the support jacking device and bridge support are installed on it Concrete should be poured between the webs of the corbels on both sides to increase the rigidity of the corbels of the steel structure and form a complete anti-overturning force system; finally, the bridge support is installed in place by the support lifting device.
本实用新型关键点是支座的顶升装置,主要原理是将螺杆的水平拉力通过楔形块转化为竖向顶升力。螺杆的水平拉力由调节螺栓施加的扭矩转化而来,再通过楔形块巧妙的将螺杆的水平拉力转化为竖向顶升力,用普通的扳手即可完成对桥梁附加支座的安装。支座压力则由橡胶支座的压缩量来控制。The key point of the utility model is the jacking device of the support, and the main principle is to convert the horizontal pulling force of the screw rod into the vertical jacking force through the wedge block. The horizontal pulling force of the screw is converted from the torque applied by the adjusting bolt, and then the horizontal pulling force of the screw is cleverly converted into a vertical lifting force through the wedge block, and the installation of the additional support of the bridge can be completed with an ordinary wrench. The bearing pressure is controlled by the compression of the rubber bearing.
本实用新型的有益效果是:可以在不影响正常交通的前提下,对独柱墩桥梁进行抗倾覆加固,是一种结构简单、安装便捷且施工过程不受应用范围限制的独柱墩桥梁抗倾覆加固装置。该装置所有部件均可在工厂预制,既保证了产品的质量和精度,又大大减少了现场施工的时间。由于该附加支撑为钢结构,钢结构牛腿的牛腿腹板和牛腿翼缘板都可作为浇筑混凝土的模板,因而不需搭设额外的模板来浇筑混凝土,只需简单的脚手架即可施工。桥梁支座的安装采用楔形块顶升安装工艺,通过楔形块装置完成从扭矩到竖向顶升力的转化,安装过程简便易行,不再依赖千斤顶来顶升梁体,一个扳手即可将支座安装就位。The beneficial effect of the utility model is that the single-pillar pier bridge can be reinforced against overturning without affecting the normal traffic, and it is a single-pillar pier bridge anti-overturning reinforcement with simple structure, convenient installation, and the construction process is not limited by the scope of application. Overturning reinforcement. All parts of the device can be prefabricated in the factory, which not only ensures the quality and precision of the product, but also greatly reduces the construction time on site. Since the additional support is a steel structure, both the corbel web and the corbel flange plate of the steel structure corbel can be used as a formwork for pouring concrete, so there is no need to set up an additional formwork to pour concrete, and only simple scaffolding can be used for construction. The installation of the bridge support adopts the wedge-shaped block lifting installation process. The conversion from torque to vertical lifting force is completed through the wedge-shaped block device. The seat is installed in place.
附图说明Description of drawings
图1是本实用新型的一种结构示意图;Fig. 1 is a kind of structural representation of the utility model;
图2是本实用新型图1的Ⅰ-Ⅰ俯视图;Fig. 2 is the top view of I-I of Fig. 1 of the utility model;
图3是本实用新型钢结构牛腿的立面图;Fig. 3 is the elevation view of the utility model steel structure corbel;
图4是本实用新型图3所示钢结构牛腿的俯视图;Fig. 4 is a top view of the steel structure corbel shown in Fig. 3 of the utility model;
图5是本实用新型图3所示钢结构牛腿的侧视图;Fig. 5 is a side view of the steel structure corbel shown in Fig. 3 of the utility model;
图6是本实用新型支座顶升装置的相对关系示意图;Fig. 6 is a schematic diagram of the relative relationship of the support jacking device of the present invention;
图7是本实用新型支座板示意图;Fig. 7 is a schematic diagram of the utility model bearing plate;
图8是本实用新型图7所示结构的仰视图;Fig. 8 is a bottom view of the structure shown in Fig. 7 of the utility model;
图9是本实用新型楔形块装置示意图;Fig. 9 is a schematic diagram of a wedge block device of the present invention;
图10是本实用新型图9所示结构的俯视图;Fig. 10 is a top view of the structure shown in Fig. 9 of the utility model;
图11是本实用新型楔形块支撑肋板的结构示意图;Fig. 11 is a structural schematic diagram of a wedge-shaped block supporting rib plate of the present invention;
图12是本实用新型图11所示结构的俯视图;Fig. 12 is a top view of the structure shown in Fig. 11 of the utility model;
图中:1、钢结构牛腿,2、支座顶升装置,3、桥梁支座,4、牛腿腹板,5、牛腿翼缘板,6、牛腿加劲肋,7、牛腿联系板,8、化学锚栓孔,9、化学锚栓,10、支座垫板,11、垫板底楔形肋,12、楔形肋,13、楔形板限位块,14、座板挡板,15、楔形块加劲肋,16、调节螺栓,17、楔形块支撑肋板。In the figure: 1. Steel structure corbel, 2. Support jacking device, 3. Bridge support, 4. Corbel web, 5. Corbel flange plate, 6. Corbel stiffener, 7. Corbel Contact plate, 8, chemical anchor bolt hole, 9, chemical anchor bolt, 10, support backing plate, 11, backing plate bottom wedge-shaped rib, 12, wedge-shaped rib, 13, wedge-shaped plate limit block, 14, seat plate baffle , 15, wedge-shaped block stiffeners, 16, adjusting bolts, 17, wedge-shaped block support ribs.
具体实施方式Detailed ways
下面通过具体实施例,并结合附图,对本实用新型的技术方案作进一步说明。The technical solutions of the present utility model will be further described below through specific embodiments and in conjunction with the accompanying drawings.
实施例:如图1-12所示的独柱墩桥梁附加钢结构支撑抗倾覆加固装置,只要包括钢结构牛腿1和支座顶升装置2;钢结构牛腿1增设于独柱墩两侧,并通过化学锚栓9与独柱墩连接形成扁担梁,其上安装支座顶升装置2和桥梁支座3。Embodiment: As shown in Figure 1-12, the additional steel structure support anti-overturning reinforcement device for a single-column pier bridge, as long as it includes a steel structure corbel 1 and a support jacking device 2; side, and through the chemical anchor bolt 9 connected with the single-column pier to form a pole beam, on which the support jacking device 2 and the bridge support 3 are installed.
整个结构可分为两个部分,第一部分是钢结构牛腿1,第二部分是支座顶升装置2。钢结构牛腿1由牛腿腹板4、牛腿翼缘板5和牛腿加劲肋6焊接组合而成,牛腿腹板4上开有化学锚栓孔8,利用化学锚栓9将钢结构牛腿1固定在墩柱上,再用牛腿联系板7将两侧钢结构牛腿1联系成整体。The whole structure can be divided into two parts, the first part is the steel structure corbel 1, and the second part is the support jacking device 2. The steel structure corbel 1 is welded and combined by corbel web 4, corbel flange plate 5 and corbel stiffener 6. The corbel web 4 is provided with chemical anchor holes 8, and the steel structure is fixed by using chemical anchor bolts 9. The corbel 1 is fixed on the pier column, and then the steel structure corbels 1 on both sides are connected into a whole by the corbel connecting plate 7 .
支座顶升装置各部分相对位置见图6,由三部分组成:支座板、楔形块装置和楔形块支撑肋板。支座板由支座垫板10和垫板底楔形肋11焊接组成。楔形块装置由楔形块、调节螺栓16和座板挡板14组成,其中楔形块为格构式结构,由楔形肋12、楔形板限位块13和楔形块加劲肋15焊接组成;楔形板限位块13焊接在楔形肋12内侧,长度稍短于楔形肋11之间的净间距,主要作用是当楔形块滑动时限制其与支座板的横向位移;楔形块加劲肋15焊接于楔形肋12和楔形板限位块13之间,用于加强楔形装置的刚度;调节螺栓16焊接于楔形板限位块13侧面,主要作用是通过扳手将扭矩转化成对螺杆的水平拉力;座板挡板14焊接于钢结构牛腿1端部,主要作用是限制支座板的水平位移,只允许其竖向位移;楔形块支撑肋板17焊接于钢结构牛腿1顶部,用于支撑楔形块并起到限位作用。The relative position of each part of the support jacking device is shown in Figure 6, which consists of three parts: the support plate, the wedge block device and the wedge block support rib. The bearing plate is composed of the bearing backing plate 10 and the wedge-shaped rib 11 at the bottom of the backing plate. The wedge block device is made up of wedge block, adjusting bolt 16 and seat plate baffle plate 14, and wherein wedge block is lattice type structure, is formed by welding of wedge-shaped rib 12, wedge-shaped plate limit block 13 and wedge-shaped block stiffener 15; The bit block 13 is welded on the inner side of the wedge-shaped rib 12, and the length is slightly shorter than the net distance between the wedge-shaped ribs 11. The main function is to limit the lateral displacement between the wedge-shaped block and the support plate when the wedge-shaped block slides; the wedge-shaped block stiffener 15 is welded to the wedge-shaped rib Between 12 and the wedge-shaped plate limit block 13, it is used to strengthen the rigidity of the wedge-shaped device; the adjustment bolt 16 is welded to the side of the wedge-shaped plate limit block 13, and its main function is to convert the torque into a horizontal pull to the screw rod through a wrench; The plate 14 is welded to the end of the steel structure corbel 1, and its main function is to limit the horizontal displacement of the support plate, only allowing its vertical displacement; the wedge support rib 17 is welded to the top of the steel structure corbel 1 to support the wedge And play a limiting role.
实施步骤:Implementation steps:
(1)工厂预制钢结构牛腿;(1) Factory prefabricated steel structure corbels;
(2)现场搭设脚手架并在独柱墩上钻孔;(2) Set up scaffolding on site and drill holes on the single-column pier;
(3)安装钢结构牛腿并焊接牛腿联系板;(3) Install the steel structure corbel and weld the corbel connecting plate;
(4)焊接楔形块支撑肋板和座板挡板;(4) Welding wedge support ribs and seat baffles;
(5)组装支座顶升装置;(5) Assemble the support jacking device;
(5)在牛腿腹板间浇筑混凝土;(5) Pouring concrete between the corbel webs;
(6)待混凝土达到预定强度后,将桥梁支座安放到支座板上,拧动调节螺栓顶升支座;(6) After the concrete reaches the predetermined strength, place the bridge support on the support plate, and turn the adjusting bolt to lift the support;
以上所述的实施例只是本实用新型的一种较佳方案,并非对本实用新型作任何形式上的限制,在不超出权利要求所记载的技术方案前提下还有其它的变体及改型。The above-mentioned embodiment is only a preferred solution of the utility model, and does not limit the utility model in any form, and there are other variations and modifications under the premise of not exceeding the technical solution described in the claims.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420603900.0U CN204151701U (en) | 2014-10-17 | 2014-10-17 | Single column pier bridge adds steel structure support overturning or slip resistance analysis bracing means |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420603900.0U CN204151701U (en) | 2014-10-17 | 2014-10-17 | Single column pier bridge adds steel structure support overturning or slip resistance analysis bracing means |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204151701U true CN204151701U (en) | 2015-02-11 |
Family
ID=52509829
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201420603900.0U Expired - Lifetime CN204151701U (en) | 2014-10-17 | 2014-10-17 | Single column pier bridge adds steel structure support overturning or slip resistance analysis bracing means |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204151701U (en) |
Cited By (13)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104727235A (en) * | 2015-03-31 | 2015-06-24 | 吴本刚 | Bridge overall strengthening device |
| CN105421250A (en) * | 2015-11-17 | 2016-03-23 | 上海市政工程设计研究总院(集团)有限公司 | Anti-overturning structure for single-pier bridge girder |
| CN105421224A (en) * | 2015-11-17 | 2016-03-23 | 上海市政工程设计研究总院(集团)有限公司 | Intelligent supporting base |
| CN105970799A (en) * | 2016-05-18 | 2016-09-28 | 清华大学 | Structure for preventing bridge from overturning transversely and construction method of structure |
| CN109338892A (en) * | 2018-11-17 | 2019-02-15 | 湖南金海钢结构有限公司 | A kind of steel structure bridge installation segmentation line style adjustment and integral bridge descending device |
| CN109736181A (en) * | 2019-01-18 | 2019-05-10 | 上海市城市建设设计研究总院(集团)有限公司 | Girder steel anti-overturning devices |
| CN110700122A (en) * | 2019-10-08 | 2020-01-17 | 上海市政工程设计研究总院(集团)有限公司 | A antidumping reinforced structure for rectangle single-column mound bridge |
| CN110792042A (en) * | 2019-10-08 | 2020-02-14 | 上海市政工程设计研究总院(集团)有限公司 | An anti-overturning reinforcement method for rectangular single-column pier bridges |
| CN113187116A (en) * | 2021-04-27 | 2021-07-30 | 重庆永昂实业有限公司 | Automatic energy dissipation and shock absorption structure of overhead single-column station |
| CN113931089A (en) * | 2021-11-17 | 2022-01-14 | 中交第一公路勘察设计研究院有限公司 | Limiting device for bridge anti-overturning and anti-pulling reinforcement and construction method thereof |
| CN114411536A (en) * | 2021-12-21 | 2022-04-29 | 江苏宁靖盐高速公路有限公司 | Bridge support with displacement measurable and height adjustable and installation method thereof |
| CN116695592A (en) * | 2023-05-22 | 2023-09-05 | 中建八局第三建设有限公司 | Truss structure double-spliced adjustable bridge anti-overturning construction method |
| CN119121812A (en) * | 2024-10-08 | 2024-12-13 | 广东工业大学 | A device for preventing bridge deck from falling |
-
2014
- 2014-10-17 CN CN201420603900.0U patent/CN204151701U/en not_active Expired - Lifetime
Cited By (15)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104727235A (en) * | 2015-03-31 | 2015-06-24 | 吴本刚 | Bridge overall strengthening device |
| CN105421250A (en) * | 2015-11-17 | 2016-03-23 | 上海市政工程设计研究总院(集团)有限公司 | Anti-overturning structure for single-pier bridge girder |
| CN105421224A (en) * | 2015-11-17 | 2016-03-23 | 上海市政工程设计研究总院(集团)有限公司 | Intelligent supporting base |
| CN105970799A (en) * | 2016-05-18 | 2016-09-28 | 清华大学 | Structure for preventing bridge from overturning transversely and construction method of structure |
| CN105970799B (en) * | 2016-05-18 | 2018-04-10 | 清华大学 | A kind of construction for preventing bridge lateral from toppling and its construction method |
| CN109338892A (en) * | 2018-11-17 | 2019-02-15 | 湖南金海钢结构有限公司 | A kind of steel structure bridge installation segmentation line style adjustment and integral bridge descending device |
| CN109736181A (en) * | 2019-01-18 | 2019-05-10 | 上海市城市建设设计研究总院(集团)有限公司 | Girder steel anti-overturning devices |
| CN109736181B (en) * | 2019-01-18 | 2024-02-06 | 上海市城市建设设计研究总院(集团)有限公司 | Steel beam anti-overturning device |
| CN110700122A (en) * | 2019-10-08 | 2020-01-17 | 上海市政工程设计研究总院(集团)有限公司 | A antidumping reinforced structure for rectangle single-column mound bridge |
| CN110792042A (en) * | 2019-10-08 | 2020-02-14 | 上海市政工程设计研究总院(集团)有限公司 | An anti-overturning reinforcement method for rectangular single-column pier bridges |
| CN113187116A (en) * | 2021-04-27 | 2021-07-30 | 重庆永昂实业有限公司 | Automatic energy dissipation and shock absorption structure of overhead single-column station |
| CN113931089A (en) * | 2021-11-17 | 2022-01-14 | 中交第一公路勘察设计研究院有限公司 | Limiting device for bridge anti-overturning and anti-pulling reinforcement and construction method thereof |
| CN114411536A (en) * | 2021-12-21 | 2022-04-29 | 江苏宁靖盐高速公路有限公司 | Bridge support with displacement measurable and height adjustable and installation method thereof |
| CN116695592A (en) * | 2023-05-22 | 2023-09-05 | 中建八局第三建设有限公司 | Truss structure double-spliced adjustable bridge anti-overturning construction method |
| CN119121812A (en) * | 2024-10-08 | 2024-12-13 | 广东工业大学 | A device for preventing bridge deck from falling |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN204151701U (en) | Single column pier bridge adds steel structure support overturning or slip resistance analysis bracing means | |
| WO2022142999A1 (en) | Hoisting device for bridge water surface pile tie beam and construction method therefor | |
| CN204282199U (en) | Pile-column concrete hollow pile bridge pier structure | |
| CN103452126B (en) | Light combined hanging box with recyclable baseplate steels and construction technology thereof | |
| CN104480922B (en) | Space truss formwork system and construction method thereof | |
| CN105780923A (en) | Assembly structure of prefabricated concrete beam and concrete-filled steel tube column | |
| CN103866693B (en) | A kind of mounting method of steel concrete bowstring arch bridge arch rib | |
| CN114781026B (en) | A construction control method for a single-tilted-tower cable-stayed bridge | |
| CN107869195A (en) | A kind of shaped steel steel column and column cap sizing punching block construction method | |
| CN103469735B (en) | The installation method of the formwork of the solid section of the pier top of the hollow column and slab pier with curved superelevation | |
| CN102505849B (en) | Construction method of membrane shell ribbed floor formwork supporting system | |
| CN104358213B (en) | Consider the firm structure limited bracket of concrete triangle of battered leg effect of contraction with to pull bar combination constructing method thereof | |
| CN206204766U (en) | Single column pier bridge antidumping diagonal brace bracing means | |
| CN204455856U (en) | A kind of pressure mechanism in place of prefabricated pier | |
| CN101694127B (en) | Formwork support system for steel frame structure cast-in-place concrete floorslabs | |
| CN203238950U (en) | Concrete beam formwork supported by trusses suspended in air | |
| CN205604312U (en) | High -rise building jacking horizontal spacing structure of rectifying | |
| CN205637120U (en) | Assembly structure of precast concrete beam and steel core concrete column | |
| CN203034799U (en) | Tower hoist standard knot bearing overhead support formwork steel platform structure | |
| CN207998793U (en) | A kind of multifunctional box shaped steel bracket structure | |
| CN110700122A (en) | A antidumping reinforced structure for rectangle single-column mound bridge | |
| CN211498483U (en) | Hollow wall pier tie beam formwork system | |
| CN220266305U (en) | Box girder formwork supporting device | |
| CN207277211U (en) | Large steel pipe truss for bent cap cast-in-place construction | |
| CN201826526U (en) | Device for supporting template of steel frame structure cast-in-situ concrete floor slab |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CX01 | Expiry of patent term |
Granted publication date: 20150211 |
|
| CX01 | Expiry of patent term |