CN203022761U - Novel vertical shaft formwork - Google Patents

Novel vertical shaft formwork Download PDF

Info

Publication number
CN203022761U
CN203022761U CN2012206865444U CN201220686544U CN203022761U CN 203022761 U CN203022761 U CN 203022761U CN 2012206865444 U CN2012206865444 U CN 2012206865444U CN 201220686544 U CN201220686544 U CN 201220686544U CN 203022761 U CN203022761 U CN 203022761U
Authority
CN
China
Prior art keywords
formwork
template
dual
port
right angle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2012206865444U
Other languages
Chinese (zh)
Inventor
赵永生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Aerospace Construction Group Co Ltd
Zhonghangtian Construction Engineering Co Ltd
Original Assignee
China Aerospace Construction Group Co Ltd
Zhonghangtian Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Aerospace Construction Group Co Ltd, Zhonghangtian Construction Engineering Co Ltd filed Critical China Aerospace Construction Group Co Ltd
Priority to CN2012206865444U priority Critical patent/CN203022761U/en
Application granted granted Critical
Publication of CN203022761U publication Critical patent/CN203022761U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

A novel vertical shaft is formed by a dual-port formwork, spacing-determined reinforcing steel bars, a formwork dead shore, bolts, a right-angle triangle bracket and a wood wedge. The dual-port formwork is formed by a formwork body with double main notches and formwork bodies with double auxiliary notches. The formwork body with the double main notches and the formwork bodies with double auxiliary notches achieve self-locking of the dual-port formwork through notches. The lower section of the dual-port formwork is arranged on the triangle bracket. The dual-port formwork is fixed on a shaft wall through the spacing-determined reinforcing steel bars. Two ends of the formwork dead shore are respectively fixedly arranged on the dual-port formwork, and the formwork dead shore remains horizontal. The bolts are embedded in the shaft wall. One right-angle side of the right-angle triangle bracket is fixed on the shaft wall through the bolts. A protruding baffle is arranged on the other right-angle side. The wood wedge is arranged between the dual-port formwork and the protruding baffle of the right-angle triangle bracket and used for fixing the dual-port formwork. The novel vertical shaft has the advantages of being simple in construction, favorable for coordination and cross operation of various types of work, high in construction speed, and capable of shortening the construction period and effectively ensuring that errors of various parameters of a poured reinforced concrete shaft wall are small.

Description

A kind of Novel silo template
Technical field
The utility model belongs to building field, relates to a kind of Novel silo template system.
Background technology
Small diameter deep well is as underground structure, have the advantages that bore is little, the degree of depth is dark, this kind well is after excavation is completed, need to process processing to the deep-well wall, as carry out building of steel concrete, in some cases, the steel concrete that the borehole wall is built is had relatively high expectations, as thickness, intensity and the circularity etc. of the borehole wall.
During at present construction, set up the cylinder frame with conventional template and scaffold in deep-well, and fix with scaffold, but that this kind mode is built thickness, intensity and the circularity equal error of reinforced concrete shaft lining is larger.
Summary of the invention
The purpose of this utility model is for the deficiencies in the prior art, proposes a kind of Novel silo template system, and the application of this template can guarantee effectively that the steel essence concrete walling parameters of building has less error, and the characteristics of easy construction.
A kind of Novel silo template by twoport template, spacing reinforcing bar, template shore, bolt, right angle trigonometry support and timber wedge form; Described twoport template is comprised of two female mouths and two kinds of templates of Shuangzi mouth, realize the template self-locking with the Shuangzi mouth template by otch for two female mouthful, the hypomere of template is placed on the right angle trigonometry support, template is fixed on the borehole wall by the spacing reinforcing bar, and template is shored two ends and is fixed on respectively on template and the maintenance level; Described bolt embedment is in the borehole wall; A straight flange of described right angle trigonometry support is bolted on the borehole wall, on an other right-angle side, a protruding baffle plate is arranged; Described timber wedge is placed between the protruding baffle plate of template and right angle trigonometry support, is used for fixed form.
It is simple that the advantage of a kind of Novel silo template described in the utility model is to have construction, be conducive to each work post and coordinate, cross-operation, speed of application is fast, save the duration, can effectively guarantee that the steel essence concrete walling parameters of building has less error simultaneously.
Description of drawings
Fig. 1 a kind of Novel silo formwork integral structural representation described in the utility model;
Fig. 2 a kind of Novel silo formwork structure schematic diagram described in the utility model;
Fig. 3 a kind of Novel silo template A-frame structural representation described in the utility model;
In figure: 1 pair of female mouth, 2 Shuangzi mouths, 3 spacing reinforcing bars, 4, template are shored, the protruding baffle plate of 5 bolts, 6 right angle trigonometry supports, 7 timber wedges, 8 right angle trigonometry supports.
The specific embodiment
As Fig. 1, Fig. 2 and shown in Figure 3, a kind of Novel silo template by twoport template, spacing reinforcing bar 3, template shore 4, bolt 5, right angle trigonometry support 6 and timber wedge 7 form; Described twoport template is comprised of two female mouths 1 and 2 two kinds of templates of Shuangzi mouth, realize the template self-locking with Shuangzi mouth 2 templates by otch for two female mouthful 1, the hypomere of template is placed on right angle trigonometry support 6, template is fixed on the borehole wall by spacing reinforcing bar 3, and template is shored 4 two ends and is fixed on respectively on template and the maintenance level; Described bolt 5 is embedded in the borehole wall; A straight flange of described right angle trigonometry support 6 is fixed on the borehole wall by bolt 5, and a protruding baffle plate 8 is arranged on an other right-angle side; Described timber wedge 7 is placed between the protruding baffle plate 8 of template and right angle trigonometry support, is used for fixed form.
Described triangular support bracket mounting means is: template is installed the right angle trigonometry support need not be installed first, after the template installation, on template top by the pre-buried erection bolt of design scheme, after concreting is completed, treat that concrete reaches strength of mould stripping, tear place's template open before with the female dismounting of pre-embedded bolt bolt, then stripping is transported to the template cut-back region, treat next step construction use, except first, other each time template is installed all need first install the right angle trigonometry support; At first the right angle trigonometry support is installed the nut that will remove before form removal and is connected with screw rod in being embedded in concrete, connection should be tight, sufficient length is arranged, then the right angle trigonometry support is passed prepared screw-bolt hole, by pad and big nut, the right angle trigonometry support is fixed on concrete structure.Should ensure in installation process that the bracing frame supporting surface is on same absolute altitude.
For template, should the brushing release agent before template is installed; Template is installed and is directly installed on sole plate first, utilize bottom the earth anchorage template, so the installation form position should strict levelling when concreting, other step template is installed and is installed on the right angle trigonometry support, utilize bottom the bracing frame fixed form, the right angle trigonometry support is answered levelling before template is installed.Template is installed should first determine every template position, spell in other zone examination, to every template numbering, use crane lifting during installation, first lift standard form, install in turn, install at last and tear lifting plate open, should strictly control formwork elevation measuring and verticality according to the absolute altitude line in the template installation process, every template answers assembly unit closely, vertically, otherwise template can't be closed.After template is substantially in place, hang mold plate verticality with line pendant, guarantee that template is vertical, with timber wedge, that the template bottom is fixing, template top holds out against with jacking, and a side withstands on bank protection, and a side to on face die plate, is guaranteed form stable, firmly to the top.Report supervisor to check and accept after the template installation, can carry out the next procedure construction after acceptance(check).
Installation for bolt, after formwork reinforcement is completed, right angle trigonometry support pre-embedded bolt is installed in preformed hole position, template top, pre-embedded bolt is fixed on template, when conflict with reinforcement location in the preformed hole position, suitably adjust bolt position or pry open reinforcing bar so that erection bolt with crowbar.The pre-embedded bolt nut should the brushing release agent, in order to remove.

Claims (1)

1. Novel silo template, by twoport template, spacing reinforcing bar, template shore, bolt, right angle trigonometry support and timber wedge form; Described twoport template is comprised of two female mouths and two kinds of templates of Shuangzi mouth, realize the template self-locking with the Shuangzi mouth template by otch for two female mouthful, the hypomere of template is placed on the right angle trigonometry support, template is fixed on the borehole wall by the spacing reinforcing bar, and template is shored two ends and is fixed on respectively on template and the maintenance level; Described bolt embedment is in the borehole wall; A straight flange of described right angle trigonometry support is bolted on the borehole wall, on an other right-angle side, a protruding baffle plate is arranged; Described timber wedge is placed between the protruding baffle plate of template and right angle trigonometry support, is used for fixed form.
CN2012206865444U 2012-12-13 2012-12-13 Novel vertical shaft formwork Expired - Lifetime CN203022761U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012206865444U CN203022761U (en) 2012-12-13 2012-12-13 Novel vertical shaft formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012206865444U CN203022761U (en) 2012-12-13 2012-12-13 Novel vertical shaft formwork

Publications (1)

Publication Number Publication Date
CN203022761U true CN203022761U (en) 2013-06-26

Family

ID=48646752

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012206865444U Expired - Lifetime CN203022761U (en) 2012-12-13 2012-12-13 Novel vertical shaft formwork

Country Status (1)

Country Link
CN (1) CN203022761U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107725055A (en) * 2017-10-16 2018-02-23 中国恩菲工程技术有限公司 The fixed structure and its construction method of vertical shaft
CN109869153A (en) * 2019-02-26 2019-06-11 中铁十局集团第一工程有限公司 The whole of rapid construction vertical shaft lining cutting promotes cantilever form device and construction method
CN113187484A (en) * 2021-05-27 2021-07-30 中电建十一局工程有限公司 Pressure regulating well rollover construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107725055A (en) * 2017-10-16 2018-02-23 中国恩菲工程技术有限公司 The fixed structure and its construction method of vertical shaft
CN109869153A (en) * 2019-02-26 2019-06-11 中铁十局集团第一工程有限公司 The whole of rapid construction vertical shaft lining cutting promotes cantilever form device and construction method
CN113187484A (en) * 2021-05-27 2021-07-30 中电建十一局工程有限公司 Pressure regulating well rollover construction method

Similar Documents

Publication Publication Date Title
CN101886466B (en) Construction method for support structure of coal tower template for tamping type coke oven
CN104141383B (en) A kind of Bailey beam pendent form support system and construction thereof
CN104631512B (en) Hang modulus method after-pouring band beam-slab construction method
CN204151701U (en) Single column pier bridge adds steel structure support overturning or slip resistance analysis bracing means
CN104790676A (en) Rapid leveling and alignment device and method for installation of prefabricated wallboards
CN102900024B (en) Using method for overturning die plate for large-scale concrete structure and
CN204570711U (en) A kind of assembled steel reinforced concrete cofferdam
CN203022761U (en) Novel vertical shaft formwork
CN203961238U (en) Bolt anchor slab adjustable tool formula builder's jack
CN208235575U (en) A kind of assembly concrete retaining wall having enough to meet the need
CN109869153A (en) The whole of rapid construction vertical shaft lining cutting promotes cantilever form device and construction method
CN203452375U (en) Hydraulic self-jacking oblique creeping formwork
CN203238950U (en) Concrete beam formwork supported by trusses suspended in air
CN103243731B (en) Mould supporting method for trapezoid cross section base of shear wall
CN102767378A (en) Method for constructing distyle tunnel portal by framed bent
CN215484618U (en) A pour template structure for assembled shear force wall and post
CN104746860A (en) Water tank cast-in-site method of inverted conical shell water tower cable-stayed formwork in air
CN114134820A (en) Formwork support and construction method for I-shaped composite beam cast-in-place bridge deck
CN203924652U (en) The operation platform of periphery shear wall between a kind of precast stair
CN204081468U (en) A kind of shear-wall strengthening formwork structure
CN208219667U (en) Foundation pit supporting construction based on campshed and inner support
CN110817688A (en) Hoisting device and installation method for prefabricated beam of inclined roof with prefabricated concrete structure
CN206693614U (en) A kind of one side hydraulic slip-form device
CN205100546U (en) Movement joint shear wall template structure
CN204238244U (en) Deep foundation pit construction structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CHINA AEROSPACE CONSTRUCTION ENGINEERING CO., LTD.

Free format text: FORMER NAME: CHINA AEROSPACE CONSTRUCTION GROUP CO., LTD.

CP03 Change of name, title or address

Address after: 100071 No. 83 South Fourth Ring Road, Beijing

Patentee after: ZHONG HANG TIAN CONSTRUCTION ENGINEERING Co.,Ltd.

Patentee after: China Aerospace Construction Group Co.,Ltd.

Address before: 100071 Beijing West Fourth Ring Road, Fengtai District, No. 83

Patentee before: China Aerospace Construction Group Co.,Ltd.

Patentee before: ZHONG HANG TIAN CONSTRUCTION ENGINEERING Co.,Ltd.

CX01 Expiry of patent term

Granted publication date: 20130626

CX01 Expiry of patent term