CN105421224A - Intelligent supporting base - Google Patents

Intelligent supporting base Download PDF

Info

Publication number
CN105421224A
CN105421224A CN201510789814.2A CN201510789814A CN105421224A CN 105421224 A CN105421224 A CN 105421224A CN 201510789814 A CN201510789814 A CN 201510789814A CN 105421224 A CN105421224 A CN 105421224A
Authority
CN
China
Prior art keywords
bearing
intelligent
mounting assembly
intelligent bearing
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510789814.2A
Other languages
Chinese (zh)
Inventor
韩鹏
李攀
马玉龙
盛勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201510789814.2A priority Critical patent/CN105421224A/en
Publication of CN105421224A publication Critical patent/CN105421224A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses an intelligent supporting base. The height of the intelligent supporting base arranged between steel brackets and the bottom of a bridge girder is adjustable, and it is ensured that the upper surface of the intelligent supporting base is tightly attached to the bottom of the bridge girder and the lower surface of the intelligent supporting base is tightly attached to the steel brackets. According to the intelligent supporting base, the anti-overturning performance of the single-pier bridge girder is improved; the intelligent supporting base has good construction convenience, wide applicability and excellent economy.

Description

Intelligent bearing
Technical field
The present invention relates to a kind of intelligent bearing.
Background technology
Current, the many employings of curve bridge only post Cast-in-Situ Continuous Beam form of structure such as China's city intersection, high speed ring road, the substructure form of this kind of bridge has minimizing occupation of land, the increase visual field and bridge advantage attractive in appearance.But China's load-carrying vehicle ubiquity overloading at present, individual vehicle overload even reaches 200% ~ 300%, causes the bridge of this kind of form of structure in use a lot of capsizing case to occur.
The bending resistance focusing on bridge that current bridge design person pays close attention to, shear resistant capacity aspect, the concern for the accidental overload effect of bias is not enough.Recent year Single column pier Continuous Box Girder Bridge capsizing case frequently occurs, and causes the self-examination of related personnel gradually.Trace it to its cause, most accident bridge pier column direction across bridge adopts single fulcrum support, under overloaded vehicle uneven loading action, the horizontal anti-overturning of structure is poor, especially the bridge floor of sharp radius curve only post ring road box girder bridge is narrow, conducts oneself with dignity little, and the ratio of vehicular load shared by Load Combination is great.Simultaneously because of the regulation that existing the standard of highway bridge is not correlated with for transverse overturning stability, be in space state, often can ignore again the bridge lateral Stability Numerical Analysis under eccentric accidentally overload effect during design, the structure under accidental action be used and brings hidden danger.
It is more complicated Mechanics Phenomenon that structure is toppled, and belongs to the category of bearing nonlinear analysis.Before structure is toppled, first will inevitably produce bearing bias voltage and even to come to nothing phenomenon.After seat empty, the bearing come to nothing loses the supporting role to structure, only remaining bearing remaining produces constraint to structure, this will inevitably cause the distribution again of end reaction, will inevitably occur in this process that such as bearing vertical pressure exceedes susceptor design intensity and causes support damage, the excessive caused girder slippage phenomenon of bearing corner distortion in process of toppling, therefore whether structure is toppled to lose efficacy with seat supports effect and is closely related.
Summary of the invention
The invention provides a kind of intelligent bearing, improve the overturning or slip resistance analysis performance of Single column pier bridge, there is convenience of constructing preferably, wider applicability and excellent economy.
In order to achieve the above object, the invention provides a kind of intelligent bearing for Single column pier bridge, this intelligent bearing settlement at the bottom of steel corbel and Bridge Beam between, the height adjustable of this intelligent bearing, ensure to fit tightly at the bottom of the upper surface of this intelligent bearing and Bridge Beam, soffit and steel corbel fit tightly.
The described intelligent bearing for Single column pier bridge comprises: mounting assembly and to be arranged on below mounting assembly and be mechanically connected mounting assembly heighten assembly, this heightens the height that assembly regulates mounting assembly, precompression is applied to mounting assembly, thus ensure to fit tightly at the bottom of the upper surface of intelligent bearing and Bridge Beam, soffit and steel corbel fit tightly.
Described mounting assembly comprises:
Support body;
Piezoelectric ceramics, it is arranged on support body inside, and be electrically connected controller, this piezoelectric ceramics is electrically not aobvious in a free state, discharges under compression, charges under extended state, piezoelectric ceramics utilizes piezo-electric effect to produce the signal of telecommunication, and by electric signal transmission to controller, the signal of telecommunication that controller produces according to piezoelectric ceramics, judges whether intelligent bearing occurs coming to nothing and conjugating.
Described mounting assembly also comprises:
Be arranged on the bearing top board on support body top;
And, be arranged on the base-plate of support body bottom.
Described assembly of heightening comprises:
Bearing, its one end is placed on steel corbel, and the other end is fixedly connected with base-plate;
Heighten gad, it contacts base-plate, and can move up and down along bearing;
Heighten part, gad is heightened in its connection, makes to heighten gad and moves up and down along bearing, thus drives mounting assembly to move up and down.
Invention increases the overturning or slip resistance analysis performance of Single column pier bridge, there is convenience of constructing preferably, wider applicability and excellent economy.
Accompanying drawing explanation
Fig. 1 is the structural representation of Single column pier bridge overturning or slip resistance analysis structure.
Fig. 2 be in Fig. 1 A-A to sectional view.
Fig. 3 is the structural representation of intelligent bearing.
Fig. 4 is the flow chart of the overturning or slip resistance analysis reinforced construction method for Single column pier bridge.
Detailed description of the invention
Following according to Fig. 1 ~ Fig. 4, illustrate preferred embodiment of the present invention.
As depicted in figs. 1 and 2, the invention provides a kind of intelligent bearing, this intelligent bearing settlement is in Single column pier bridge overturning or slip resistance analysis structure, and this Single column pier bridge overturning or slip resistance analysis structure comprises:
Steel hoop structure, it is set on pier column 101, this steel hoop structure comprises the identical steel hoop 2 of two structures, and be arranged on the some to drawing high strength bolt 201 of junction 203 on steel hoop 2, with the some anchor bolts 202 be arranged on steel hoop 2 in preformed hole position, this makes steel hoop 2 be combined into an overall steel hoop structure to drawing high strength bolt 201, and this anchor bolt 202 fixes steel hoop mechanism and pier column 101;
Two steel corbels 1, it is welded to connect with two steel hoops 2 respectively;
Intelligent bearing 3, it is arranged at the bottom of steel corbel 1 and Bridge Beam between 104, and at the bottom of the upper surface of this intelligent bearing 3 and Bridge Beam, 104 fit tightly, and soffit and steel corbel 1 fit tightly;
As shown in Figure 3, described intelligent bearing 3 comprises: mounting assembly and to be arranged on below mounting assembly and be mechanically connected mounting assembly heighten assembly, this heightens the height that assembly regulates mounting assembly, precompression is applied to mounting assembly, thus to ensure at the bottom of the upper surface of intelligent bearing 3 and Bridge Beam that 104 fit tightly, soffit and steel corbel 1 fit tightly, and unlikely appearance comes to nothing;
Described mounting assembly comprises:
Support body 302;
Piezoelectric ceramics (not shown), it is inner that it is arranged on support body 302, and be electrically connected controller, this piezoelectric ceramics is not aobvious at steady state does not electrically produce the signal of telecommunication, and in compression process, electric discharge produces positive charge signal, and in drawing process, charging produces negative electrical charge signal, piezoelectric ceramics utilizes piezo-electric effect to produce the signal of telecommunication, and by electric signal transmission to controller, the signal of telecommunication that controller produces according to piezoelectric ceramics, judges whether intelligent bearing 3 occurs coming to nothing and conjugating;
Be arranged on the bearing top board 301 on support body 302 top;
And, be arranged on the base-plate 303 of support body 302 bottom;
Described assembly of heightening comprises:
Bearing 306, its one end is placed on steel corbel 1, and the other end is fixedly connected with base-plate 303;
Heighten gad 305, it contacts base-plate 303, and can move up and down along bearing 306;
Heighten part 304, gad 305 is heightened in its connection, makes to heighten gad 305 and moves up and down along bearing 306, thus drives mounting assembly to move up and down.
As shown in Figure 4, adopt Single column pier bridge overturning or slip resistance analysis structure provided by the invention for the overturning or slip resistance analysis reinforcement means of Single column pier bridge, comprise following steps:
Step S1, by steel hoop and steel corbel pre-assembled integrated steel-structure;
The steel hoop welded together and steel corbel are transported to engineering site;
Utilize pier cap (as shown in Figure 1) as work plane, two steel hoops are placed in the both sides of pier column respectively, the junction of two steel hoops contacts with each other, some high-strength bolts are tentatively screwed into the junction of two steel hoops, make two steel hoops form an overall steel hoop structure around bridge pier;
Step S2, utilize lifting means by steel hoop and steel corbel composition integrated steel-structure be promoted to pier column top, pier column top now has been provided with bridge pad (as shown in Figure 1);
Step S3, by steel hoop and steel corbel composition integrated steel-structure be fixed on pier column top;
Some anchor bolts are planted in the preformed hole position on steel hoop;
Tighten the force value of high-strength bolt to designing requirement at steel anchor ear connection place;
Tighten anchor bolt;
Structure glue is injected the gap between steel hoop and pier column;
The gap between steel hoop and pier column is filled up by note structure glue, make both closely connected, to provide powerful anchor ear power and bonding force, but owing to filling up gap between steel hoop and pier column by note structure glue, need more complicated operation and larger operating platform, for the engineering of circumstance complication residing for Single column pier, also can by setting up the sheet rubber of 3 ~ 5mm between steel hoop and pier column, both are fitted tightly, with the anchor ear power providing steel hoop powerful;
Step S4, be placed on steel corbel by some intelligent bearings, the intelligent bearing of bridge pad and both sides forms " seesaw " structure, regulates the height of intelligent bearing, and make to fit tightly at the bottom of its upper surface and Bridge Beam, soffit and steel corbel fit tightly;
In the present embodiment, suppose that the elemental height of intelligent bearing is 20cm, regulate the height of intelligent bearing, make to fit tightly at the bottom of its upper surface and Bridge Beam, soffit and steel corbel fit tightly, now intelligent bearing be highly compressed to 15cm, when the height of intelligent bearing maintains 15cm, intelligent bearing is in stable state, do not show and electrically do not produce the signal of telecommunication, if under overloaded vehicle uneven loading action, bridge beam body run-off the straight, according to seesaw principle, the intelligent bearing pressurized (larger than the pressure be subject to before in other words) of bridge pad side, height is compressed to 10cm from 15cm, in compression process, electric discharge produces positive charge signal, the intelligent seat empty of bridge pad opposite side (does not stress in other words, stressed less than original in other words), height is stretched to 20cm from 15cm, in drawing process, charging produces negative electrical charge signal,
The signal of telecommunication that in the intelligent bearing of step S5, Real-time Collection, piezoelectric ceramics produces, judges whether intelligent bearing occurs coming to nothing and conjugating.
The present invention has the following advantages:
1, by the anchor ear power of steel hoop, adhesion stress and anchor bolt, the integrated steel-structure that pier column and steel hoop and steel corbel form is connected as one;
2, mainly through anchor ear power, realize steel hoop and be connected with pier column with the integrated steel-structure that steel corbel forms, plastic simplicity, from heavy and light, the welding of steel work opening construction and late maintaining convenience, strong adaptability, easily to promote;
3, intelligent adjustable-height bearing is adopted, set up piezoelectric ceramics intellectual material in the holder, there is direct piezoelectric effect and reversed piezoelcetric effect, by online acquisition and patrol and examine the collection signal of telecommunication, implement to transmit data to mobile phone or computer terminal through cloud platform, judge whether intelligent bearing occurs coming to nothing, conjugating by data analysis.
Although content of the present invention has done detailed introduction by above preferred embodiment, will be appreciated that above-mentioned description should not be considered to limitation of the present invention.After those skilled in the art have read foregoing, for multiple amendment of the present invention and substitute will be all apparent.Therefore, protection scope of the present invention should be limited to the appended claims.

Claims (5)

1. an intelligent bearing, it is characterized in that, this intelligent bearing (3) to be arranged at the bottom of steel corbel (1) and Bridge Beam between (104), the height adjustable of this intelligent bearing (3), ensure that at the bottom of the upper surface of this intelligent bearing (3) and Bridge Beam, (104) fit tightly, soffit and steel corbel (1) fit tightly.
2. intelligent bearing as claimed in claim 1, it is characterized in that, described intelligent bearing (3) comprises: mounting assembly and to be arranged on below mounting assembly and be mechanically connected mounting assembly heighten assembly, this heightens the height that assembly regulates mounting assembly, precompression is applied to mounting assembly, thus ensureing that at the bottom of the upper surface of intelligent bearing (3) and Bridge Beam, (104) fit tightly, soffit and steel corbel (1) fit tightly.
3. intelligent bearing as claimed in claim 2, is characterized in that, described mounting assembly comprises:
Support body (302);
Piezoelectric ceramics, it is inner that it is arranged on support body (302), and be electrically connected controller, this piezoelectric ceramics is not aobvious at steady state does not electrically produce the signal of telecommunication, in compression process, electric discharge produces positive charge signal, and in drawing process, charging produces negative electrical charge signal, piezoelectric ceramics by electric signal transmission to controller, the signal of telecommunication that controller produces according to piezoelectric ceramics, judges whether intelligent bearing (3) occurs coming to nothing and conjugating.
4. intelligent bearing as claimed in claim 3, is characterized in that, described mounting assembly also comprises:
Be arranged on the bearing top board (301) on support body (302) top;
And, be arranged on the base-plate (303) of support body (302) bottom.
5. intelligent bearing as claimed in claim 2, is characterized in that, described assembly of heightening comprises:
Bearing (306), its one end is placed on steel corbel (1), and the other end is fixedly connected with base-plate (303);
Heighten gad (305), its contact base-plate (303), and can move up and down along bearing (306);
Heighten part (304), gad (305) is heightened in its connection, makes to heighten gad (305) and moves up and down along bearing (306), thus drives mounting assembly to move up and down.
CN201510789814.2A 2015-11-17 2015-11-17 Intelligent supporting base Pending CN105421224A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510789814.2A CN105421224A (en) 2015-11-17 2015-11-17 Intelligent supporting base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510789814.2A CN105421224A (en) 2015-11-17 2015-11-17 Intelligent supporting base

Publications (1)

Publication Number Publication Date
CN105421224A true CN105421224A (en) 2016-03-23

Family

ID=55499739

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510789814.2A Pending CN105421224A (en) 2015-11-17 2015-11-17 Intelligent supporting base

Country Status (1)

Country Link
CN (1) CN105421224A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106436557A (en) * 2016-10-26 2017-02-22 上海市政工程设计研究总院(集团)有限公司 Method for improving overturning resistance of single-column pier bridge
CN107142855A (en) * 2017-05-17 2017-09-08 广州市精特建筑工程有限公司 Bridge single pier bearing replacement, maintenance jacking anchor ear
CN107893369A (en) * 2017-11-22 2018-04-10 武汉海润工程设备有限公司 One kind is used for the adjustable bridle iron of magnetic-levitation access bridge depth of beam
CN111877189A (en) * 2020-07-31 2020-11-03 上海应用技术大学 Anti-overturning energy consumption reinforcing device for single-column pier bridge

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001317589A (en) * 2000-05-09 2001-11-16 Yokohama Rubber Co Ltd:The Slide support structure
CN104034248A (en) * 2014-06-05 2014-09-10 同济大学 Real-time wireless monitoring apparatus for early-warning on integral overturn of bridge
CN204151701U (en) * 2014-10-17 2015-02-11 浙江省交通工程建设集团有限公司 Single column pier bridge adds steel structure support overturning or slip resistance analysis bracing means
CN104562924A (en) * 2014-12-31 2015-04-29 郑州航空工业管理学院 Self-elevating base plate change method for bridge support
CN204551248U (en) * 2015-03-17 2015-08-12 长安大学 A kind of bridge plate-type bearing overturning or slip resistance analysis prior-warning device
CN205313969U (en) * 2015-11-17 2016-06-15 上海市政工程设计研究总院(集团)有限公司 Intelligent support

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001317589A (en) * 2000-05-09 2001-11-16 Yokohama Rubber Co Ltd:The Slide support structure
CN104034248A (en) * 2014-06-05 2014-09-10 同济大学 Real-time wireless monitoring apparatus for early-warning on integral overturn of bridge
CN204151701U (en) * 2014-10-17 2015-02-11 浙江省交通工程建设集团有限公司 Single column pier bridge adds steel structure support overturning or slip resistance analysis bracing means
CN104562924A (en) * 2014-12-31 2015-04-29 郑州航空工业管理学院 Self-elevating base plate change method for bridge support
CN204551248U (en) * 2015-03-17 2015-08-12 长安大学 A kind of bridge plate-type bearing overturning or slip resistance analysis prior-warning device
CN205313969U (en) * 2015-11-17 2016-06-15 上海市政工程设计研究总院(集团)有限公司 Intelligent support

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106436557A (en) * 2016-10-26 2017-02-22 上海市政工程设计研究总院(集团)有限公司 Method for improving overturning resistance of single-column pier bridge
CN106436557B (en) * 2016-10-26 2023-12-01 上海市政工程设计研究总院(集团)有限公司 Method for improving anti-overturning performance of single-pier bridge
CN107142855A (en) * 2017-05-17 2017-09-08 广州市精特建筑工程有限公司 Bridge single pier bearing replacement, maintenance jacking anchor ear
CN107893369A (en) * 2017-11-22 2018-04-10 武汉海润工程设备有限公司 One kind is used for the adjustable bridle iron of magnetic-levitation access bridge depth of beam
CN111877189A (en) * 2020-07-31 2020-11-03 上海应用技术大学 Anti-overturning energy consumption reinforcing device for single-column pier bridge
CN111877189B (en) * 2020-07-31 2022-05-27 上海应用技术大学 Anti-overturning energy consumption reinforcing device for single-column pier bridge

Similar Documents

Publication Publication Date Title
CN205313989U (en) Single -column mound bridge antidumping structure
CN105421250A (en) Anti-overturning structure for single-pier bridge girder
CN105442460A (en) Anti-overturning strengthening method for single-column pier bridge
CN105421224A (en) Intelligent supporting base
CN108532474B (en) Overturn-preventing reinforcing device and installation method for single-column pier bridge
CN203096598U (en) Outer cladding type steel-concrete combined structure beam bridge overturn-resistant device
CN205313969U (en) Intelligent support
CN203639095U (en) Inner-side-column lifting device for reverse installation method
CN202131003U (en) Segmental-block dwarf lifting tool capable of adjusting gestures
CN204177466U (en) Electric power wheel self-discharging vehicle weighing device
CN203602253U (en) Double-beam portal crane
CN201366968Y (en) Semi-trailer tank
CN206279440U (en) A kind of pull rod device for improving Single column pier bridge anti-overturning energy
CN201045095Y (en) Pot-type container
CN212175513U (en) Counter-force supporting and adjusting device for mounting assembled bridge pier cap
CN210684444U (en) Structure of pier is consolidated to steel sheet antidetonation
CN220598129U (en) Structure for increasing wind resistance stability of steel structure pipe supporting bridge
CN202787923U (en) Movable scaffold
CN207129003U (en) Composite component is strengthened in the installation of electrocar car door hinge
CN209140861U (en) Detachable mobile tooling shelf is adjusted
CN105417364A (en) Crane frame beam
CN216474538U (en) A combination formula staple bolt for pier stud bent cap construction
CN217193533U (en) Steel case roof beam welding appurtenance
CN213142767U (en) Steel structure reinforcing device of single-column pier bent bridge
CN202517319U (en) Auxiliary device for overturning large-size plate girder component

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160323

RJ01 Rejection of invention patent application after publication