CN204098928U - 隧道拱顶二衬前注浆管的定位预埋装置 - Google Patents

隧道拱顶二衬前注浆管的定位预埋装置 Download PDF

Info

Publication number
CN204098928U
CN204098928U CN201420392380.3U CN201420392380U CN204098928U CN 204098928 U CN204098928 U CN 204098928U CN 201420392380 U CN201420392380 U CN 201420392380U CN 204098928 U CN204098928 U CN 204098928U
Authority
CN
China
Prior art keywords
grouting pipe
bracing frame
lining
grouting
tunnel vault
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420392380.3U
Other languages
English (en)
Inventor
柴颖鹏
马小利
曾继光
庄乾理
黄鹏飞
宋勇
张沱
王永奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Original Assignee
Third Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd filed Critical Third Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Priority to CN201420392380.3U priority Critical patent/CN204098928U/zh
Application granted granted Critical
Publication of CN204098928U publication Critical patent/CN204098928U/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

本实用新型公开了一种隧道拱顶二衬前注浆管的定位预埋装置,其技术方案是在二衬台车上固定连接盘及支撑架,调节罗杆穿过二衬台车与连接盘顶在定位盘上,定位盘通过丝扣连接注浆管,注浆管与支撑架相交处设有密封套,注浆管上部固定安装顶板,注浆管内壁设有排气管。本实用新型克服了目前二次注浆设置注浆管所存在的技术难题,在二衬混凝土浇筑前就准确定位预埋好浇筑管,无需二次钻孔,即可在二衬混凝土台车脱模后可以及时注浆,又可保证不会二次伤及防水板,彻底消除了隧道拱顶漏水的安全隐患。

Description

隧道拱顶二衬前注浆管的定位预埋装置
技术领域
本实用新型涉及一种隧道拱顶施工注浆装置,具体是一种隧道拱顶二衬前注浆管的定位预埋装置,可广泛应用于铁路公路等的隧道施工,属于道路施工领域。 
背景技术
随着铁路公路建设的快速发展,国家对隧道工程提出了越来越高的质量标准。在隧道施工流程中,首先是对隧道壁进行喷涂,然后设置防水板,最后浇筑二衬混凝土。由于隧道混凝土施工缺陷的影响和混凝土自身的收缩率,隧道拱顶浇筑的二衬混凝土和防水板之间不可避免的会出现空隙甚至空洞,由于空洞中空气的热胀冷缩作用,严重时会使二衬混凝土出现裂缝,导致隧道顶部漏水,给后续的隧道通车埋下了安全隐患,特别是漏水对高速铁路电网造成的影响更大,安全隐患更严重。为彻底排除这一安全隐患,就需要对二衬混凝土与防水板之间的空洞进行二次注浆,而注浆前必须在二衬混凝土上开有注浆口,目前在二衬混凝土上开注浆口的方法有两种:一是在浇筑二衬混凝土前预埋注浆管,但由于预埋的注浆管需要固定在二衬混凝土钢筋上,在二衬混凝土浇注过程中很容易移位,导致注浆管管口堵塞,使二次注浆无法完成;二是在二衬混凝土浇注完成后再钻孔塞入注浆管,由于二衬混凝土的厚度不能绝对保证均匀,加之人工操作误差,很容易在钻孔的过程中将防水板钻穿,破坏了防水性能,而且不能及时发现,留下了长期的安全隐患。针对目前这一施工难题还没有较好的技术方案进行解决。 
实用新型内容
本实用新型的目的是克服目前隧道施工中在二衬混凝土上设置注浆管所存在的技术难题,而公开一种隧道拱顶二衬前注浆管的定位预埋装置。 
本实用新型的技术方案如下: 
在二衬台车顶部中心设置密封垫,密封垫的上面安装支撑架,连接盘固定在支撑架底部,固定螺钉将支撑架与连接盘固定,调节罗杆通过丝扣穿过二衬台车顶面与连接盘顶在定位盘的中心位置,定位盘上部通过丝扣连接注浆管,注浆管与支撑架相交处设有密封套,注浆管上部固定安装顶板,注浆管内壁设有排气管,排气管的上端口穿过顶板,下端口在密封套下部注浆管的侧壁。
  本实用新型克服了目前隧道施工中在二衬混凝土上二次注浆设置注浆管所存在的技术难题,在二衬混凝土浇筑前就准确定位预埋好浇筑管,使二衬混凝土台车在脱模后可以及时注浆,即保证二次注浆能顺利完成,又可保证不会二次伤及防水板,彻底消除了隧道拱顶漏水的安全隐患,本实用新型对注浆管预埋定位准确标准,无需二次钻孔,不会对防水系统造成任何影响,节约了成本,消除了施工过程中的安全隐患,保证了工程质量,提高了工作效率。 
附图说明
附图1是本实用新型的主视结构剖面示意图。 
 因本实用新型整体结构为旋转体故省略其它视图。 
 附图标记说明如下:支撑架1,连接盘2,固定螺钉3,调节罗杆4, 密封垫5,定位盘6,密封套7,注浆管8,排气管9,顶板10,二衬台车11,隧道二衬12。 
具体实施方式
以下结合附图1对本实用新型做进一步详细描述: 
在二衬台车(11)顶部中心设置密封垫(5),密封垫(5)的上面安装支撑架(1),连接盘(2)固定在支撑架(1)底部,用四个固定螺钉(3)将支撑架(1)与连接盘(2)固定,调节罗杆(4)通过丝扣穿过二衬台车(11)顶面与连接盘(2)顶在定位盘(6)的中心位置,定位盘(6)上部通过丝扣连接注浆管(8),注浆管(8)与支撑架(1)相交处设有密封套(7),注浆管(8)上部固定安装顶板(10),注浆管(8)内壁设有排气管(9),排气管(9)的上端口穿过顶板(10),下端口在密封套(7)下部注浆管(8)的侧壁。
使用时,首先在二衬台车上放置密封垫,在注浆管下端旋装定位盘,将注浆管穿过支撑架上部的密封套,在支撑架下部固定连接盘,然后将支撑架放置在密封垫上,用四个固定螺钉将连接盘固定在二衬台车上,旋装调节罗杆穿过二衬台车顶面与连接盘顶住定位盘,继续旋转调节直到注浆管达到适当高度,保证出浆口能顺利排出混凝土,排气管能顺利排气,在二衬混凝土浇筑完成后,卸掉固定螺钉,旋转下移调节罗杆,待二衬台车前移后,将支撑架向下脱模取出,再旋转取下定位盘,然后将注浆阀门旋装在注浆管上,混凝土通过注浆管进入二衬混凝土与防水板之间的空洞完成二次注浆,顶板可保证顶板不会伤及防水板。 

Claims (2)

1.隧道拱顶二衬前注浆管的定位预埋装置,其特征是:在二衬台车(11)顶部中心设置密封垫(5),密封垫(5)的上面安装支撑架(1),连接盘(2)固定在支撑架(1)底部,用四个固定螺钉(3)将支撑架(1)与连接盘(2)固定,调节罗杆(4)通过丝扣穿过二衬台车(11)顶面与连接盘(2)顶在定位盘(6)的中心位置,定位盘(6)上部通过丝扣连接注浆管(8),注浆管(8)与支撑架(1)相交处设有密封套(7),注浆管(8)上部固定安装顶板(10),注浆管(8)内壁设有排气管(9),排气管(9)的上端口穿过顶板(10),下端口在密封套(7)下部注浆管(8)的侧壁。
2.根据权利要求1所述的隧道拱顶二衬前注浆管的定位预埋装置,其特征在于是用四个固定螺钉(3)将支撑架(1)与连接盘(2)固定。
CN201420392380.3U 2014-05-14 2014-07-16 隧道拱顶二衬前注浆管的定位预埋装置 Expired - Fee Related CN204098928U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420392380.3U CN204098928U (zh) 2014-05-14 2014-07-16 隧道拱顶二衬前注浆管的定位预埋装置

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN201420245709 2014-05-14
CN201420245709.3 2014-05-14
CN201420392380.3U CN204098928U (zh) 2014-05-14 2014-07-16 隧道拱顶二衬前注浆管的定位预埋装置

Publications (1)

Publication Number Publication Date
CN204098928U true CN204098928U (zh) 2015-01-14

Family

ID=52267364

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420392380.3U Expired - Fee Related CN204098928U (zh) 2014-05-14 2014-07-16 隧道拱顶二衬前注浆管的定位预埋装置

Country Status (1)

Country Link
CN (1) CN204098928U (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104895585A (zh) * 2015-04-30 2015-09-09 中铁二十一局集团第四工程有限公司 隧道拱顶预留注浆管的施工方法
CN105422135A (zh) * 2015-12-02 2016-03-23 中建三局第一建设工程有限责任公司 一种预留注浆孔成孔设备及方法
CN105569690A (zh) * 2016-01-11 2016-05-11 西南交通大学 跨活动断层隧道抗粘滑错动的二次衬砌及其建造方法
CN106014454A (zh) * 2016-07-11 2016-10-12 北京鸿锐嘉科技发展有限公司 隧道衬砌拱顶带模注浆装置及注浆工艺
CN107060826A (zh) * 2017-05-09 2017-08-18 北京鸿锐嘉科技发展有限公司 一种隧道台车辅助注浆装置及注浆工艺
CN107762532A (zh) * 2016-08-23 2018-03-06 中铁十局集团第工程有限公司 隧道拱顶带模注浆施工方法
CN108194103A (zh) * 2017-12-29 2018-06-22 中铁十九局集团第二工程有限公司 二衬带模注浆工艺
CN108625878A (zh) * 2018-05-14 2018-10-09 北京铁科首钢轨道技术股份有限公司 一种解决隧道衬砌拱顶脱空问题的工艺
CN111058864A (zh) * 2019-11-29 2020-04-24 中铁九局集团第四工程有限公司 一种隧道拱顶衬砌后方空洞高压注浆辅助装置

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104895585A (zh) * 2015-04-30 2015-09-09 中铁二十一局集团第四工程有限公司 隧道拱顶预留注浆管的施工方法
CN105422135A (zh) * 2015-12-02 2016-03-23 中建三局第一建设工程有限责任公司 一种预留注浆孔成孔设备及方法
CN105569690A (zh) * 2016-01-11 2016-05-11 西南交通大学 跨活动断层隧道抗粘滑错动的二次衬砌及其建造方法
CN106014454A (zh) * 2016-07-11 2016-10-12 北京鸿锐嘉科技发展有限公司 隧道衬砌拱顶带模注浆装置及注浆工艺
CN106014454B (zh) * 2016-07-11 2018-02-06 北京鸿锐嘉科技发展有限公司 隧道衬砌拱顶带模注浆装置及注浆工艺
CN107762532A (zh) * 2016-08-23 2018-03-06 中铁十局集团第工程有限公司 隧道拱顶带模注浆施工方法
CN107762532B (zh) * 2016-08-23 2019-03-01 中铁十一局集团第一工程有限公司 隧道拱顶带模注浆施工方法
CN107060826A (zh) * 2017-05-09 2017-08-18 北京鸿锐嘉科技发展有限公司 一种隧道台车辅助注浆装置及注浆工艺
CN107060826B (zh) * 2017-05-09 2023-10-24 北京鸿锐嘉科技发展有限公司 一种隧道台车辅助注浆装置及注浆工艺
CN108194103A (zh) * 2017-12-29 2018-06-22 中铁十九局集团第二工程有限公司 二衬带模注浆工艺
CN108625878A (zh) * 2018-05-14 2018-10-09 北京铁科首钢轨道技术股份有限公司 一种解决隧道衬砌拱顶脱空问题的工艺
CN111058864A (zh) * 2019-11-29 2020-04-24 中铁九局集团第四工程有限公司 一种隧道拱顶衬砌后方空洞高压注浆辅助装置

Similar Documents

Publication Publication Date Title
CN204098928U (zh) 隧道拱顶二衬前注浆管的定位预埋装置
CN104314314A (zh) 一种灌浆连接施工方法
CN108166517B (zh) 用于超高层高水压深井降水井的封井方法及封井装置
CN207231732U (zh) 一种装配式管廊接头防水测试装置
CN105240024A (zh) 一种平行盾构法扩建施工地铁车站的方法
CN107023032A (zh) 一种综合管廊的现浇方法
CN104295109B (zh) 老旧小区不入户阳台快速加固结构及其施工方法
CN105735616B (zh) 应用于建筑住宅的排烟气道连接器及其对接烟道的方法
CN204059760U (zh) 一种方钢柱柱芯自密实混凝土浇筑施工结构
CN207268009U (zh) 一种基于现行排污渠的地下综合管廊排水系统
CN106759485B (zh) 一种上下分体式预制管廊及安装方法
CN104047423B (zh) 一种穿楼地面板精确预留洞口的模具与施工方法
CN204212422U (zh) 一种用于钢管柱混凝土顶升法施工的混凝土输送装置
CN112081179A (zh) 埋地式一体化箱泵的抗浮泵站
CN204941551U (zh) 一种曲线顶管支护结构扩建盾构施工的地铁车站
CN204551694U (zh) 一种预埋式阳台地漏
CN204662506U (zh) 一种电缆通信井
CN207847399U (zh) 一种住宅的窗结构
CN206986918U (zh) 一种用于风机锚栓基础灌浆的非对称模板
CN203238671U (zh) 一种地下建筑侧壁的自愈式施工缝结构
CN105064217A (zh) 一种桥梁盖梁底模防漏浆装置
CN206554976U (zh) 隧道二衬浇注混凝土自动报警装置
CN214035783U (zh) 富水区域高透水地层补做排水管控制涌水涌砂的装置
CN204098519U (zh) 老旧小区不入户阳台快速加固结构
CN203403445U (zh) 用于地下室管井封堵的钢套筒

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150114

Termination date: 20210716

CF01 Termination of patent right due to non-payment of annual fee