CN204080642U - A kind of for installing small bridge precast beam device - Google Patents
A kind of for installing small bridge precast beam device Download PDFInfo
- Publication number
- CN204080642U CN204080642U CN201420545578.0U CN201420545578U CN204080642U CN 204080642 U CN204080642 U CN 204080642U CN 201420545578 U CN201420545578 U CN 201420545578U CN 204080642 U CN204080642 U CN 204080642U
- Authority
- CN
- China
- Prior art keywords
- precast beam
- pinner
- coaster
- abutment
- cushion block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Machines For Laying And Maintaining Railways (AREA)
Abstract
The utility model relates to a kind of for installing small bridge precast beam device, it is characterized in that: it mainly comprises transports coaster, hoist engine, jack, mobile crane and cushion block; Described cushion block is for filling and leading up the groove on abutment between pinner and pinner, and described cushion block and pinner form a horizontal rail jointly; Described transport coaster is placed on the one end in above-mentioned horizontal rail, for transporting precast beam to assigned address; Described mobile crane is positioned at the side of abutment, transports coaster for being hung onto by precast beam; Described hoist engine is fixedly mounted on the abutment of the other end in above-mentioned horizontal rail, for drawing the transport coaster being placed with precast beam; Described jack is placed on the both sides of pinner on abutment, for precast beam jack-up extraction out is transported coaster, is being transferred on pinner by precast beam.This apparatus structure is simple, effectively solves the problem by place restriction when precast beam is installed, and this device can simple, the dismounting of on-site consolidation, and cost is low.
Description
Technical field
The utility model relates to a kind of for installing small bridge precast beam device.
Background technology
Along with the development of China's infrastructure, some small bridges are widely used in urban road construction in recent years.When installing precast beam, traditional method is: directly hang (described large-scale crane refers to that lifting capacity is at more than 50t) or two large-scale cranes with a large-scale crane list and lift and sling by whole precast beam, then be placed on bridge pier.Adopt in this way hoisting prefabricated beam slab time, due to construction plant high-voltage line, the impacts such as viaduct, electric pole electric wire, the safe space that lifting is operated is inadequate; And the large-scale crane bodily form is huge, particularly arm is longer, causes it to operate, and the machinery expenses of large-scale crane is also higher simultaneously.
Summary of the invention
For the problems referred to above, the purpose of this utility model is to provide a kind of for installing small bridge precast beam device, and this apparatus structure is simple, effectively solves the problem by place restriction when precast beam is installed, and this device can simple, the dismounting of on-site consolidation, cost is low.
For achieving the above object, technical solution adopted in the utility model is:
A kind of for installing small bridge precast beam device, it is characterized in that: it mainly comprises transports coaster, hoist engine, jack, mobile crane and cushion block;
Described cushion block is for filling and leading up the groove on abutment between pinner and pinner, and described cushion block and pinner form a horizontal rail jointly;
Described transport coaster is placed on the one end in above-mentioned horizontal rail, for transporting precast beam to assigned address;
Described mobile crane is positioned at the side of abutment, transports coaster for being hung onto by precast beam;
Described hoist engine is fixedly mounted on the abutment of the other end in above-mentioned horizontal rail, for drawing the transport coaster being placed with precast beam;
Described jack is placed on the both sides of pinner on abutment, for precast beam jack-up extraction out is transported coaster, is being transferred on pinner by precast beam.
Described cushion block is upper and lower double-layer structure, and lower floor is sleeper, and upper strata is steel plate.
Described mobile crane lifting capacity is at below 50t.
The beneficial effects of the utility model are:
(1) the utility model make use of equilibrium principle fully, cushion block and pinner is made full use of as the slideway paying beam slab translation in advance in the whole installation process of precast beam, using hoist engine as the power set transporting coaster translation, precast beam is transported to assigned address, in the middle of whole process, mobile crane only transports coaster for being hung onto by precast beam, simple to operate, scope of activities is little, particularly reduces the scope of activities of arm; Effectively solve the inadequate problem in precast beam operation (safety) space, and this device can simple, the dismounting of on-site consolidation, convenient transport (transporting coaster, jack and hoist engine own wt lighter), cost is low;
(2) cushion block in the utility model is that sleeper adds the upper and lower double-layer structure of steel plate, and sleeper plays cushioning effect, and steel plate hardness is large, and transport coaster can be made to smoothly pass;
(3) the mobile crane lifting capacity in the utility model is at below 50t, and overall volume is little, convenient transport and operation, and cost is also low.
Accompanying drawing explanation
Fig. 1 is using state schematic diagram of the present utility model.
Fig. 2 is the schematic diagram after installing jack in the utility model.
Fig. 3 is the side schematic view (namely without right view during mobile crane) of Fig. 1.
In figure: 1-precast beam; 2-transports coaster; 3-steel plate; 4-sleeper; 5-hoist engine; 6-jack; 7-abutment; 8-pinner; 9-mobile crane; 10-lift rope.
Detailed description of the invention
In order to better understand the utility model, below in conjunction with embodiment and accompanying drawing, the utility model is further illustrated.
A kind of for installing small bridge precast beam device, it mainly comprises transports coaster 2, hoist engine 5, jack 6, mobile crane 9 and cushion block;
As shown in Figure 3, for filling and leading up on abutment 7 between pinner 8 and pinner 8 groove, (described abutment 7 upper surface is equidistantly provided with row's pinner 8 to described cushion block, pinner 8 and abutment 7 are all that concreting is shaping), described cushion block and pinner 8 form a horizontal rail (a pair abutment 7 of precast beam 1 to be installed or all abutments 7 all should be provided with horizontal rail) jointly;
As shown in Figure 3, described transport coaster 2 is placed on one end in above-mentioned horizontal rail (a pair horizontal rail of precast beam 1 to be installed is all placed with and transports coaster 2), for transporting precast beam 1 to the assigned address pinner 8 of installation precast beam 1 place (namely refer to need directly over);
As shown in Figure 1, described mobile crane 9 is positioned at the side (mobile crane 9 is selected to lay place according to concrete landform, determines the position of transporting coaster 2 and hoist engine 5 again according to the position of mobile crane 9) of abutment 7, transports coaster 2 for being hung onto by precast beam 1;
As shown in Figure 3, described hoist engine 5 is fixedly mounted on the abutment 7 of the other end in above-mentioned horizontal rail and (a pair horizontal rail of precast beam 1 to be installed is all provided with hoist engine 5; Described hoist engine 5 is by multiple connector temporary consolidation on abutment 7, and connector is the angle steel of the wide 100mm of wing plate, and hoist engine base, by welding between angle steel or by high strength exploitation, is temporarily fixed on abutment 7; The lift rope 10 of hoist engine 5 is connected with transport coaster 2), for drawing the transport coaster 2 being placed with precast beam 1;
As shown in Figure 2, (abutment 7 at precast beam 1 two ends respectively there are four jack 6 both sides that described jack 6 is placed on pinner 8 on abutment 7, two, side), for precast beam 1 jack-up extraction out is transported coaster 2, (between described pinner 8 and precast beam 1, be provided with neoprene bearing) being transferred to by precast beam 1 on pinner 8.
As shown in Figure 3, described cushion block is upper and lower double-layer structure, and lower floor is sleeper 4, and upper strata is that steel plate 3(sleeper 4 is placed in the groove between pinner 8 and pinner 8, and steel plate 3 is placed on sleeper 4).
Described mobile crane 9 lifting capacity is at below 50t.
Using method of the present utility model (as Figure 1-3):
(1) first in the groove between the pinner 8 and pinner 8 of all (or adjacent two) abutments 7, fill out cushion block, and jointly form a horizontal rail with pinner 8; Transport coaster 2 is placed to the one end (near mobile crane 9 one end away from hoist engine 5) in horizontal rail, then transport coaster 2 is connected with hoist engine 5 (hoist engine 5 is all installed and is placed with on all or adjacent two abutments 7 and transports coaster 2);
(2) with mobile crane 9 precast beam 1 is lifted into and transports on coaster 2 (two ends of precast beam 1 are dropped on the transport coaster 2 on adjacent two abutments 7 respectively), by hoist engine 5 at the uniform velocity (corresponding two synchronized tractions of hoist engine 5) draw to the pinner 8 of installation site needed for precast beam 1 by transporting coaster 2;
(3) first with jack 6, the two ends of precast beam 1 are slowly pushed up from transport coaster 2 simultaneously, then transport coaster 2 is dragged away, finally on pinner 8, lay neoprene bearing, the two ends of precast beam 1 after jack 6 release are seated on neoprene bearing, complete installation;
(4) step of above-mentioned (1)-(3) is repeated until all precast beam 1 installation.
The above embodiment is only for absolutely proving the preferred embodiment that the utility model is lifted, and protection domain of the present utility model is not limited to the above embodiments.Obviously, those skilled in the art can carry out various change and distortion to the utility model and not depart from scope and spirit of the present utility model.If these are changed and distortion belongs in the scope of the utility model claim and equivalent technologies thereof, then intention of the present utility model also comprises these changes and distortion.
Claims (3)
1. for installing a small bridge precast beam device, it is characterized in that: it mainly comprises transports coaster (2), hoist engine (5), jack (6), mobile crane (9) and cushion block;
Described cushion block is used for filling and leading up the upper groove between pinner (8) and pinner (8) of abutment (7), and described cushion block and pinner (8) form a horizontal rail jointly;
Described transport coaster (2) is placed on the one end in above-mentioned horizontal rail, for transporting precast beam (1);
Described mobile crane (9) is positioned at the side of abutment (7), transports coaster (2) for being hung onto by precast beam (1);
Described hoist engine (5) is fixedly mounted on the abutment (7) of the other end in above-mentioned horizontal rail, is placed with the transport coaster (2) of precast beam (1) for traction;
Described jack (6) is placed on the both sides of the upper pinner (8) of abutment (7), for precast beam (1) jack-up extraction out is transported coaster (2), is being transferred on pinner (8) by precast beam (1).
2. one according to claim 1 is for installing small bridge precast beam device, it is characterized in that: described cushion block is upper and lower double-layer structure, and lower floor is sleeper (4), and upper strata is steel plate (3).
3. one according to claim 1 is for installing small bridge precast beam device, it is characterized in that: described mobile crane (9) lifting capacity is at below 50t.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420545578.0U CN204080642U (en) | 2014-09-22 | 2014-09-22 | A kind of for installing small bridge precast beam device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420545578.0U CN204080642U (en) | 2014-09-22 | 2014-09-22 | A kind of for installing small bridge precast beam device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204080642U true CN204080642U (en) | 2015-01-07 |
Family
ID=52173377
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420545578.0U Active CN204080642U (en) | 2014-09-22 | 2014-09-22 | A kind of for installing small bridge precast beam device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204080642U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108981590A (en) * | 2018-06-13 | 2018-12-11 | 中铁隧道集团二处有限公司 | A kind of high-speed rail precast beam positioning system |
-
2014
- 2014-09-22 CN CN201420545578.0U patent/CN204080642U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108981590A (en) * | 2018-06-13 | 2018-12-11 | 中铁隧道集团二处有限公司 | A kind of high-speed rail precast beam positioning system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103669216A (en) | Steel box girder scattered-splicing sliding device and installation method | |
CN203855866U (en) | Large-span frame bridge overhead roof with beams convenient to construct | |
CN102139832B (en) | Gantry crane device with lengthways and transverse traveling functions and hoisting method | |
CN203794498U (en) | Built-in self-elevating tower crane device | |
CN102817329B (en) | Process for erecting construction auxiliary girder on existing railway | |
CN102852095B (en) | Prefabricated bridge abutment multifunctional lifting system and construction procedure thereof | |
CN110258352A (en) | The steel reinforced concrete combined bridge construction method that two bridgings are done | |
CN203320425U (en) | Cast-in-situ box girder construction apparatus with slidingly movable side mold | |
CN103774841A (en) | Track type sliding formwork device | |
CN204080642U (en) | A kind of for installing small bridge precast beam device | |
CN106276602B (en) | A kind of across high ferro Business Line beam body hangs method | |
CN103174141A (en) | Intertidal zone beam lower supporting frame steel pipe pile pulling-out device and method | |
CN203361028U (en) | Railway and magnetic levitation pushing system for high speed railway combination bridge | |
CN203755173U (en) | Formwork device used for hydraulic climbing of bridge high pier | |
CN203807900U (en) | Plate changing device for high-speed railway ballastless track | |
CN106677076A (en) | Simple and rapid method and device for mounting box girder at the top of adjacent bent cap by using span pier gantry crane | |
CN203359822U (en) | Indoor GIS (geographic information system) transport in-place device | |
CN207158647U (en) | A kind of Lift-on/Lift-off System for sound barrier panel | |
CN204530506U (en) | End bay closing device | |
CN204434174U (en) | Self-control electric hoisting device | |
CN203247591U (en) | Deep foundation pit steel support | |
CN204224995U (en) | Fortune frame railway D beam one chassis | |
CN203976242U (en) | A kind of generator unit stator associating hanging apparatus | |
CN202296886U (en) | Hoisting device for installing oversized radial gate of hydropower station | |
CN201962596U (en) | Movable support device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |