CN203821401U - 坑中坑枕式框梁结构 - Google Patents
坑中坑枕式框梁结构 Download PDFInfo
- Publication number
- CN203821401U CN203821401U CN201420168343.4U CN201420168343U CN203821401U CN 203821401 U CN203821401 U CN 203821401U CN 201420168343 U CN201420168343 U CN 201420168343U CN 203821401 U CN203821401 U CN 203821401U
- Authority
- CN
- China
- Prior art keywords
- pit
- frame beam
- concrete frame
- space enclosing
- bed course
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Foundations (AREA)
Abstract
本实用新型提供一种坑中坑枕式框梁结构,该结构设置在围护结构一侧的地坑顶部,在所述地坑的顶部两侧设置有二根混凝土框梁,二根混凝土框梁的两端分别设有加厚垫层,第一混凝土框梁设在地坑的顶部一侧并紧靠围护结构,第二混凝土框梁设在地坑的顶部另一侧,加厚垫层与第一混凝土框梁和第二混凝土框梁形成在一平面的框梁结构,在所述框梁结构与地坑周边的垫层及工程桩形成整体。本实用新型的效果是该结构使围护结构最大深层位移点位置上移,有效减小围护结构变形1~2cm,施工工艺简单,无需增加围护结构刚度,与常规方法比造价可降低5%~20%,确保基坑施工的安全。
Description
技术领域
本实用新型涉及一种坑中坑枕式框梁结构。
背景技术
软土地区地下水位高,土质软,带有地下结构的建筑在基坑开挖前,需要设置围护结构支挡,才能确保基坑施工的安全。根据建筑功能往往在基坑底设置有集水坑及电梯井坑等坑中坑,其深度为1~3m,长和宽约为2~5m。当坑中坑靠近围护结构时,势必会增加局部基坑开挖深度,给基坑工程施工带来安全风险。
常规做法是采用增加围护桩刚度及长度、坑底被动土加固或地坑单独设置围护结构的处理措施。这些方法施工复杂,且造价较高。
发明内容
针对现有技术中结构上的不足,本实用新型的目的是提供一种坑中坑枕式框梁结构,该结构使围护结构最大深层位移点位置上移,有效减小围护结构变形,施工工艺简单,无需增加围护结构刚度,造价低,确保基坑施工的安全。
为实现上述目的,本实用新型采用的技术方案是提供一种坑中坑枕式框梁结构,该结构设置在围护结构一侧的地坑顶部,其中:在所述地坑的顶部两侧设置有二根混凝土框梁,二根混凝土框梁的两端分别设有加厚垫层,第一混凝土框梁设在地坑的顶部一侧并紧靠围护结构,第二混凝土框梁设在地坑的顶部另一侧,加厚垫层与第一混凝土框梁和第二混凝土框梁形成在一平面的框梁结构,在所述框梁结构与地坑周边的垫层及工程桩形成整体。
本实用新型的效果是该技术使围护结构最大深层位移点位置上移,有效减小围护结构变形1~2cm,施工工艺简单,无需增加围护结构刚度,与常规方法比造价可降低5%~20%,确保基坑施工的安全。
附图说明
图1是本实用新型的坑中坑枕式框梁结构示意图;
图2是图I-I剖视图。
图中:
1、地坑2、围护结构3、第一混凝土框梁4、第二混凝土框梁
5、加厚垫层6、周边垫层7、工程桩
具体实施方式
结合附图对本实用新型的坑中坑枕式框梁施工结构加以说明。
如图1、2所示,本实用新型的坑中坑枕式框梁结构是,该结构设置在围护结构一侧的地坑顶部,在所述地坑的顶部两侧设置有二根混凝土框梁,第一混凝土框梁3设在地坑的顶部一侧并紧靠围护结构2,第二混凝土框梁4设在地坑的顶部另一侧,二根混凝土框梁的两端分别设有加厚垫层5,加厚垫层5与第一混凝土框梁3和第二混凝土框梁4形成在一平面的框梁结构,在所述框梁结构与地坑周边的垫层6及工程桩7形成整体。
所述第一混凝土框梁3和第二混凝土框梁4两端的长度超出加厚垫层5外边缘0.6m,所述加厚垫层5厚度为0.2m,所述地坑周边垫层6施工宽度不小于10m。
本实用新型的坑中坑枕式框梁功能是这样实现的:
在基坑底垫层施工时,围绕地坑增设二根混凝土框梁及加厚垫层,顶标高与垫层顶标高标高一致,并与围护结构2顶严,待混凝土养护达到设计强度后,与工程桩7及周边垫层6形成地坑顶部的水平向约束,再开挖地坑的方法。地坑周边垫层施工宽度应根据基坑开挖深度确定,但不宜小于10m;混凝土框梁的截面尺寸应根据地坑的平面尺寸及深度综合确定,混凝土框梁的长度为超出加厚垫层外边向外0.6m;加厚垫层厚度为0.2m,宽度可根据地坑平面尺寸及深度综合确定。
本实用新型的坑中坑枕式框梁结构有以下优点:
该结构使围护结构最大深层位移点位置上移,有效减小围护结构变形。
该结构施工工艺简单,造价低。
地坑周边增设的混凝土框梁及加厚垫层与垫层形成整体,通过垫层与地基土的摩擦力及工程桩共同工作,抵抗局部坑外土压力,确保基坑施工安全。
Claims (4)
1.一种坑中坑枕式框梁结构,该结构设置在围护结构一侧的地坑顶部,其特征是:在所述地坑的顶部两侧设置有二根混凝土框梁,第一混凝土框梁(3)设在地坑的顶部一侧并紧靠围护结构(2),第二混凝土框梁(4)设在地坑的顶部另一侧,二根混凝土框梁的两端分别设有加厚垫层(5),加厚垫层(5)与第一混凝土框梁(3)和第二混凝土框梁(4)形成在一平面的框梁结构,在所述框梁结构与地坑周边的垫层(6)及工程桩(7)形成整体。
2.根据权利要求1所述的坑中坑枕式框梁结构,其特征是:所述第一混凝土框梁(3)和第二混凝土框梁(4)两端的长度超出加厚垫层(5)外边缘0.6m。
3.根据权利要求1所述的坑中坑枕式框梁结构,其特征是:所述加厚垫层(5)厚度为0.2m。
4.根据权利要求1所述的坑中坑枕式框梁结构,其特征是:所述地坑周边垫层(6)施工宽度不小于10m。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420168343.4U CN203821401U (zh) | 2014-04-09 | 2014-04-09 | 坑中坑枕式框梁结构 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420168343.4U CN203821401U (zh) | 2014-04-09 | 2014-04-09 | 坑中坑枕式框梁结构 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203821401U true CN203821401U (zh) | 2014-09-10 |
Family
ID=51476918
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420168343.4U Expired - Fee Related CN203821401U (zh) | 2014-04-09 | 2014-04-09 | 坑中坑枕式框梁结构 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203821401U (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103898917A (zh) * | 2014-04-09 | 2014-07-02 | 天津一建建筑工程有限公司 | 坑中坑枕式框梁结构 |
-
2014
- 2014-04-09 CN CN201420168343.4U patent/CN203821401U/zh not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103898917A (zh) * | 2014-04-09 | 2014-07-02 | 天津一建建筑工程有限公司 | 坑中坑枕式框梁结构 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204530633U (zh) | 一种分区布置的软岩筑面板堆石坝坝体 | |
CN103669385A (zh) | 利用网状桩基础提高桩群承载力的方法 | |
CN104179201A (zh) | 排水泄压抗浮系统 | |
CN103912134A (zh) | 既有建筑原位地下空间结构及施工方法 | |
CN204000897U (zh) | 一种用于滑坡体上的多用途抗滑桩结构体系 | |
CN105421477A (zh) | 一种塔吊基础的施工方法 | |
CN102797265A (zh) | 顺层边坡桥梁敦台防护结构 | |
CN203821401U (zh) | 坑中坑枕式框梁结构 | |
CN207828981U (zh) | 一种水泥土搅拌墙内设双排及多排微型桩基坑支护结构 | |
CN203383220U (zh) | 一种减小双排桩水平变形的基坑支护结构 | |
CN203905044U (zh) | 架空跨越深基坑的施工电梯梁板式基础结构 | |
CN205296130U (zh) | 一种钢板桩支护结构 | |
CN101775800B (zh) | 一种具有双重作用的水泥土桩及其成形方法 | |
CN204849777U (zh) | 倾斜式压顶板双排桩支护结构 | |
CN103898917B (zh) | 坑中坑枕式框梁结构 | |
CN203977433U (zh) | 软土地区基坑工程复合支护结构 | |
CN203978442U (zh) | 一种公铁合建水下隧道 | |
CN105569050A (zh) | 一种相邻边界侧压力不均衡基坑角撑支护结构设计方法 | |
CN104328794B (zh) | 一种窄基塔四腿联合沉井基础 | |
CN204199321U (zh) | 一种窄基塔四腿联合沉井基础 | |
CN203924072U (zh) | 一种超大超深人工挖孔桩的护壁支护结构 | |
CN107060809A (zh) | 用于治理巷道底臌的组合结构及施工方法 | |
CN102061695A (zh) | 一种排水管桩复合地基处理方法 | |
CN206189428U (zh) | 一种用于深基础施工的钢板桩围堰 | |
CN204298813U (zh) | 一种可液化土中的粉煤灰地基 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140910 Termination date: 20160409 |