CN203797171U - Continuous production system of thermal insulation pipe - Google Patents

Continuous production system of thermal insulation pipe Download PDF

Info

Publication number
CN203797171U
CN203797171U CN201420163612.8U CN201420163612U CN203797171U CN 203797171 U CN203797171 U CN 203797171U CN 201420163612 U CN201420163612 U CN 201420163612U CN 203797171 U CN203797171 U CN 203797171U
Authority
CN
China
Prior art keywords
pipe
steel pipe
conveyer
rack
machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420163612.8U
Other languages
Chinese (zh)
Inventor
张晏将
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiang Feng Pipeline Group Co ltd
Original Assignee
Jiang Feng Pipeline Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiang Feng Pipeline Group Co ltd filed Critical Jiang Feng Pipeline Group Co ltd
Priority to CN201420163612.8U priority Critical patent/CN203797171U/en
Application granted granted Critical
Publication of CN203797171U publication Critical patent/CN203797171U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Warehouses Or Storage Devices (AREA)

Abstract

The utility model discloses a continuous production system of a thermal insulation pipe. The continuous production system is characterized by comprising a first steel-pipe conveying machine, a shot blasting machine and a second steel-pipe conveying machine, the first-pipe conveying machine, the shot blasting machine and the second steel-pipe conveying machine are in end-to-end connection in sequence and are arranged in a straight line; the continuous production system further comprises a PE (polyethylene)-pipe placing rack, a PE-pipe conveying machine, a pipe-through platform, a goods shelf, a steel-pipe pushing machine, a foaming machine, a finished-goods conveying machine and a stock rack, wherein the PE-pipe placing rack is located on the lateral side of the first steel-pipe conveying machine, the goods shelf is located on the lateral side of the second steel-pipe conveying machine, the steel-pipe pushing machine is located on the lateral side of the goods shelf, the steel-pipe pushing machine is in end-to-end connection with the pipe-through platform, the foaming machine is located on the lateral side of the pipe-through platform, the finished-goods conveying machine is located on the lateral side of the foaming machine, and the stock rack is located on the lateral side of the PE-pipe placing rack and is in end-to-end connection with the finished-goods conveying machine. The continuous production system has the advantages that the whole working process is controlled automatically, continuously and circularly, working efficiency is greatly improved, cost of manual operation is reduced, and labor intensity of workers is alleviated; the machines are arranged reasonably in arrangement, so that space occupation is saved.

Description

Thermal insulation pipe continuous process system
Technical field
The utility model relates to a kind of production system, is specifically related to a kind of thermal insulation pipe continuous process system.
Background technique
Thermal insulation pipe is made up of three-decker conventionally, i.e. the foaming layer of the steel pipe of internal layer, outer field PE pipe, centre.
Existing thermal insulation pipe production system is generally divided into several modules, comprising: deposit material, ball blast, sleeve pipe, foaming, then consign to finished product district.Owing to needing artificial linking between modules, not only cause workman's labor intensity large, and the rising of human cost input, cause manufacturing efficiency low simultaneously.
In addition, also there is the problem that floor space is large in existing thermal insulation pipe production system.
Model utility content
For solving the deficiencies in the prior art, the thermal insulation pipe continuous process system that the purpose of this utility model is to provide a kind of and reduces labor intensity, enhances productivity and floor space is little.
In order to realize above-mentioned target, the utility model adopts following technological scheme:
A kind of thermal insulation pipe continuous process system, is characterized in that, comprising: end-to-end and the first steel pipe conveyer being arranged in a linear, shot-blasting machine, the second steel pipe conveyer successively, and be positioned at the steel pipe rack of the first steel pipe conveyer side; Taking the first steel pipe conveyer, shot-blasting machine, the second steel pipe conveyer place straight line as axis, also be included in axis bilateral symmetry arrange: PE pipe rack, PE pipe conveyer, poling platform, shelf, steel pipe pusher, foaming machine, finished product conveyer, stock rack, aforementioned PE pipe rack is positioned at the side of the first steel pipe conveyer, PE pipe conveyer and PE pipe rack end-to-end, poling platform is positioned at the side of PE pipe conveyer; Aforementioned shelf are positioned at the side of the second steel pipe conveyer, and steel pipe pusher is positioned at the side of shelf, steel pipe pusher and poling platform end-to-end; Aforementioned foaming machine is positioned at the side of poling platform, and finished product conveyer is positioned at the side of foaming machine, stock rack and finished product conveyer end-to-end and be positioned at the side of PE pipe rack.
Aforesaid thermal insulation pipe continuous process system, is characterized in that, aforementioned the first steel pipe conveyer is identical with the structure of the second steel pipe conveyer, includes: support, be arranged on some active rubber tires and driven rubber tire in aforementioned brackets, and drive motor; The both sides of aforementioned active rubber tire are respectively provided with a universal joint, and initiatively parallel between rubber tire and form angle with transmission direction, adjacent active rubber tire connects also transmission, rotation in steel pipe advances on steel pipe conveyer by transmission shaft; Parallel between aforementioned driven rubber tire, and also parallel with active rubber tire.
Aforesaid thermal insulation pipe continuous process system, is characterized in that, aforementioned the first steel pipe conveyer, steel pipe rack, PE pipe rack, stock rack are all positioned at outside factory building wall.
Aforesaid thermal insulation pipe continuous process system, is characterized in that, on aforementioned steel pipe rack, the second steel pipe conveyer, shelf, PE pipe rack, PE pipe conveyer, poling platform, finished product conveyer, is all provided with and turns over pipe device.
Usefulness of the present utility model is: realized automatic, continuous, the whole workflow of loop control, greatly improved working efficiency, reduced the cost of manual work, alleviated workman's labor intensity; Each device location arrangement is reasonable, saves floor occupying area, and steel pipe rack, PE pipe rack, stock rack are all positioned at outside factory building wall, have ensured the cleaning of Production Regional.
Brief description of the drawings
Fig. 1 is the plan view of a specific embodiment of thermal insulation pipe continuous process system of the present utility model;
Fig. 2 is the structural representation of the first steel pipe conveyer in Fig. 1.
The implication of reference character: 1-the first steel pipe conveyer in figure, 2-shot-blasting machine, 3-the second steel pipe conveyer, 4-steel pipe rack, 5-PE pipe rack, 6-PE pipe conveyer, 7-poling platform, 8-shelf, 9-steel pipe pusher, 10-foaming machine, 11-finished product conveyer, 12-stock rack, 101-support, 102-is rubber tire initiatively, the driven rubber tire of 103-, 104-drive motor.
Embodiment
Below in conjunction with the drawings and specific embodiments, the utility model is done to concrete introduction.
With reference to Fig. 1, thermal insulation pipe continuous process system of the present utility model, comprising: end-to-end and the first steel pipe conveyer 1 being arranged in a linear, shot-blasting machine 2, the second steel pipe conveyer 3 successively, and be positioned at the steel pipe rack 4 of the first steel pipe conveyer 1 side.Taking the first steel pipe conveyer 1, shot-blasting machine 2, the second steel pipe conveyer 3 place straight lines as axis, also be included in axis bilateral symmetry arrange: PE pipe rack 5, PE pipe conveyer 6, poling platform 7, shelf 8, steel pipe pusher 9, foaming machine 10, finished product conveyer 11, stock rack 12, wherein, PE pipe rack 5 is positioned at the side of the first steel pipe conveyer 1, PE pipe conveyer 6 and PE pipe rack 5 end-to-ends, poling platform 7 is positioned at the side of PE pipe conveyer 6; Shelf 8 are positioned at the side of the second steel pipe conveyer 3, and steel pipe pusher 9 is positioned at the side of shelf 8, steel pipe pusher 9 and poling platform 7 end-to-ends; Foaming machine 10 is positioned at the side of poling platform 7, and finished product conveyer 11 is positioned at the side of foaming machine 10, stock rack 12 and finished product conveyer 11 end-to-ends and be positioned at the side of PE pipe rack 5.Visible, each device location arrangement is reasonable, has saved floor space.
As the preferred scheme of one, the first steel pipe conveyer 1, steel pipe rack 4, PE pipe rack 5, stock rack 12 are all positioned at outside factory building wall, have not only saved the floor space of factory building, and have ensured that Production Regional is the cleaning in factory building.
Automatic in order to realize, continuous, the whole workflow of loop control, greatly increase work efficiency, reduce the cost of manual work, alleviate workman's labor intensity, as the preferred scheme of one, on steel pipe rack 4, the second steel pipe conveyer 3, shelf 8, PE pipe rack 5, PE pipe conveyer 6, poling platform 7, finished product conveyer 11, be all provided with and turn over pipe device (not shown), automatic pipe turning, has alleviated workman's labor intensity.
In thermal insulation pipe continuous process system of the present utility model, shot-blasting machine 2 is for carrying out ball blast, rust cleaning to the steel pipe of not rust cleaning, if adopt normal transmission band conveying steel pipe, because steel pipe is only axially having movement, and without the action of swaying, this just causes steel pipe ball blast inhomogeneous, thereby has affected the quality of product.With reference to Fig. 2, as the preferred scheme of one, the first steel pipe conveyer 1 and the second steel pipe conveyer 3 all adopt rotary rubber wheeled construction.
Concrete, the first steel pipe conveyer 1 comprises: support 101, be arranged on some active rubber tires 102 and driven rubber tire 103 on support 101, and drive motor 104, wherein, initiatively the both sides of rubber tire 102 are respectively provided with a universal joint, initiatively parallel between rubber tire 102 and form angle with transmission direction, adjacent active rubber tire 102 connects and transmission by transmission shaft, rotation in steel pipe advances on steel pipe conveyer; Parallel between driven rubber tire 103, and also parallel with active rubber tire 102.
Thus, the first steel pipe conveyer 1 is in operation process, steel pipe is subject to the power of two aspects, steel pipe axis around self in advancing is vertically rotated, be that steel pipe rotary enters shot-blasting machine 2 and rotates and transport shot-blasting machine 2 again, steel pipe is rotating and is being eliminated rust in shot-blasting machine 2, and the product ball blast of therefore producing is even, and quality of product is high.
The second steel pipe conveyer 3 is identical with the structure of the first steel pipe conveyer 1, repeats no more.
Thermal insulation pipe continuous process system of the present utility model, its working procedure is as follows:
1, the steel pipe of rust cleaning does not turn over to the first steel pipe conveyer 1 from steel pipe rack 4, the first steel pipe conveyer 1 is sent in shot-blasting machine 2 carries out ball blast, and the steel pipe after rust cleaning is transported to the second steel pipe conveyer 3, and then the steel pipe after rust cleaning overturns to both sides, enter shelf 8, stand-by.
2, PE pipe turns over to PE pipe conveyer 6 from PE pipe rack 5, then turn to poling platform 7, stand-by.
3, the steel pipe that steel pipe pusher 9 promotes on shelf 8 moves to PE pipe place, until steel pipe is inserted in PE pipe, then turn to the processing of foaming in foaming machine 10.
4, the thermal insulation pipe after foaming is delivered to stock rack 12 by finished product conveyer 11, finishes.
It should be noted that, above-described embodiment does not limit the utility model in any form, and all employings are equal to replaces or technological scheme that the mode of equivalent transformation obtains, all drops in protection domain of the present utility model.

Claims (4)

1. thermal insulation pipe continuous process system, is characterized in that, comprising: end-to-end and the first steel pipe conveyer being arranged in a linear, shot-blasting machine, the second steel pipe conveyer successively, and be positioned at the steel pipe rack of the first steel pipe conveyer side; Taking the first steel pipe conveyer, shot-blasting machine, the second steel pipe conveyer place straight line as axis, also be included in axis bilateral symmetry arrange: PE pipe rack, PE pipe conveyer, poling platform, shelf, steel pipe pusher, foaming machine, finished product conveyer, stock rack, described PE pipe rack is positioned at the side of the first steel pipe conveyer, PE pipe conveyer and PE pipe rack end-to-end, poling platform is positioned at the side of PE pipe conveyer; Described shelf are positioned at the side of the second steel pipe conveyer, and steel pipe pusher is positioned at the side of shelf, steel pipe pusher and poling platform end-to-end; Described foaming machine is positioned at the side of poling platform, and finished product conveyer is positioned at the side of foaming machine, stock rack and finished product conveyer end-to-end and be positioned at the side of PE pipe rack.
2. thermal insulation pipe continuous process system according to claim 1, it is characterized in that, described the first steel pipe conveyer is identical with the second steel pipe conveyer structure, includes: support, be arranged on some active rubber tires and driven rubber tire on described support, and drive motor;
The both sides of described active rubber tire are respectively provided with a universal joint, and initiatively parallel between rubber tire and form angle with transmission direction, adjacent active rubber tire connects also transmission, rotation in steel pipe advances on steel pipe conveyer by transmission shaft;
Parallel between described driven rubber tire, and also parallel with active rubber tire.
3. thermal insulation pipe continuous process system according to claim 1 and 2, is characterized in that, described the first steel pipe conveyer, steel pipe rack, PE pipe rack, stock rack are all positioned at outside factory building wall.
4. thermal insulation pipe continuous process system according to claim 1 and 2, is characterized in that, on described steel pipe rack, the second steel pipe conveyer, shelf, PE pipe rack, PE pipe conveyer, poling platform, finished product conveyer, is all provided with and turns over pipe device.
CN201420163612.8U 2014-04-04 2014-04-04 Continuous production system of thermal insulation pipe Expired - Lifetime CN203797171U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420163612.8U CN203797171U (en) 2014-04-04 2014-04-04 Continuous production system of thermal insulation pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420163612.8U CN203797171U (en) 2014-04-04 2014-04-04 Continuous production system of thermal insulation pipe

Publications (1)

Publication Number Publication Date
CN203797171U true CN203797171U (en) 2014-08-27

Family

ID=51379381

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420163612.8U Expired - Lifetime CN203797171U (en) 2014-04-04 2014-04-04 Continuous production system of thermal insulation pipe

Country Status (1)

Country Link
CN (1) CN203797171U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104353978A (en) * 2014-10-17 2015-02-18 格力电器(石家庄)有限公司 Heat preservation pipe penetrating device
CN104668913A (en) * 2015-03-18 2015-06-03 浙江久立泰祜涂层技术有限公司 Manufacturing equipment for stainless steel pipe three-layered polypropylene anticorrosion pipes and manufacturing method of manufacturing equipment
CN109263095A (en) * 2018-11-21 2019-01-25 天津市锦业科技有限公司 Multifunctional polyurethane is continuously poured polytene heat-insulation pipe production line
CN109278236A (en) * 2018-11-21 2019-01-29 天津市锦业科技有限公司 A kind of improved track formula direct-buried thermal insulation pipe production line
CN110421774A (en) * 2018-05-06 2019-11-08 内蒙古君诚兴业管道有限责任公司 A kind of on-line automatic concentricity poling plugging device and automatic foaming production line
CN111196473A (en) * 2020-01-14 2020-05-26 天津市鑫金钰防腐保温钢管有限公司 Discharging system for production of anticorrosive steel pipes

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104353978A (en) * 2014-10-17 2015-02-18 格力电器(石家庄)有限公司 Heat preservation pipe penetrating device
CN104668913A (en) * 2015-03-18 2015-06-03 浙江久立泰祜涂层技术有限公司 Manufacturing equipment for stainless steel pipe three-layered polypropylene anticorrosion pipes and manufacturing method of manufacturing equipment
CN104668913B (en) * 2015-03-18 2017-03-01 浙江久立泰祜涂层技术有限公司 The manufacturing equipment of stainless steel tube three-layer polypropylene anti-corrosion pipe and its using method
CN110421774A (en) * 2018-05-06 2019-11-08 内蒙古君诚兴业管道有限责任公司 A kind of on-line automatic concentricity poling plugging device and automatic foaming production line
CN110421774B (en) * 2018-05-06 2023-11-10 内蒙古君诚兴业管道有限责任公司 Online automatic concentricity poling plugging device and automatic foaming production line
CN109263095A (en) * 2018-11-21 2019-01-25 天津市锦业科技有限公司 Multifunctional polyurethane is continuously poured polytene heat-insulation pipe production line
CN109278236A (en) * 2018-11-21 2019-01-29 天津市锦业科技有限公司 A kind of improved track formula direct-buried thermal insulation pipe production line
CN111196473A (en) * 2020-01-14 2020-05-26 天津市鑫金钰防腐保温钢管有限公司 Discharging system for production of anticorrosive steel pipes

Similar Documents

Publication Publication Date Title
CN203797171U (en) Continuous production system of thermal insulation pipe
CN103203409A (en) Pipe fitting production line
CN106081536A (en) A kind of pallet circulating conveyor
CN110406142A (en) Molding machine and tire moulding method
CN203945474U (en) Mobile base code base plateform system on a kind of rotary kiln
CN202448223U (en) Automatic production line for aerated concrete blocks
CN104175194A (en) Tapered roller bearing inner and outer ring automatic grinding production line and method thereof
CN202162887U (en) Production device for building wallboards
CN204800832U (en) Full -automatic water conservancy project concrete block production line
CN206842341U (en) A kind of organic chemical fertilizer high position conveyer belt
CN209735847U (en) High efficiency epoxy powder automatic spraying equipment
CN205003534U (en) Production warehousing and transportation system
CN206985160U (en) A kind of quick transmission line for being used to suppress front deburring
CN203265382U (en) Production line for machining pipes
WO2019183948A1 (en) Method for preparing movable steel bar
CN106144612A (en) A kind of control method of full-automatic ceramic tile production line
CN103466316B (en) A kind of air-condition heat exchanger core body production operatorless device and using method
CN108748643A (en) A kind of intelligent production line of novel fabricated construction material
CN204280047U (en) The gripping of a kind of fragment of brick secondary frames up compress automatically
CN204751351U (en) Production line of self preservation temperature building block
CN203486558U (en) Automatic device for producing air-conditioning heat exchanger cores
CN204998948U (en) Brick material packing transfer device
CN204802622U (en) Rotatory workstation
JP3221754U (en) Assembly type sequential processing system
CN204184909U (en) Roll transporter

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20140827