CN203782544U - 一种高架桥跨河段组合支架 - Google Patents

一种高架桥跨河段组合支架 Download PDF

Info

Publication number
CN203782544U
CN203782544U CN201420197707.1U CN201420197707U CN203782544U CN 203782544 U CN203782544 U CN 203782544U CN 201420197707 U CN201420197707 U CN 201420197707U CN 203782544 U CN203782544 U CN 203782544U
Authority
CN
China
Prior art keywords
steel pipe
pipe pile
bailey
river
shellfish thunder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420197707.1U
Other languages
English (en)
Inventor
李柏青
武子荐
徐世钦
王来顺
周小峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Construction Co Ltd
Original Assignee
Beijing Municipal Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Construction Co Ltd filed Critical Beijing Municipal Construction Co Ltd
Priority to CN201420197707.1U priority Critical patent/CN203782544U/zh
Application granted granted Critical
Publication of CN203782544U publication Critical patent/CN203782544U/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

本实用新型涉及一种高架桥跨河段组合支架,其包括钢管桩、防撞系梁、钢板挡土墙、水上贝雷平台、贝雷分配梁、贝雷架以及碗扣支架;其中,所述防撞系梁设置在钢管桩的内侧;所述钢板挡土墙设置在钢管桩的外侧;所述水上贝雷平台支承在钢管桩的顶部;所述贝雷分配梁支承在水上贝雷平台的顶部;所述贝雷架支承在贝雷分配梁的顶部;所述碗扣支架搭设于贝雷架上。本实用新型的高架桥跨河段组合支架具有承重能力好,安全系数高,用钢量小,成本低等诸多优点。

Description

一种高架桥跨河段组合支架
【技术领域】
本实用新型涉及一种建筑支架,尤其涉及一种高架桥跨河段组合支架,属于建筑工程技术领域。
【背景技术】
现浇箱梁施工主要有以下几种常规施工方法:(1)对地基进行处理,搭设碗扣式或扣件式满堂支架;(2)浇筑临时扩大基础,采用型钢或贝雷梁式支架;(3)浇筑混凝土桩基础,采用梁柱式支架;(4)振动插打临时钢管桩基础,采用梁柱式组合支架;(5)采用挂篮或移动模架施工。
当工程位于海港引河区域,施工期间不能进行封航,因此不能采用方法(1)进行围堰施工时;采用方法(3)施工,施工成本较高且后期混凝土桩基础将很难拆除,对河道通航留下很大的安全隐患;采用方法(5)进行挂篮施工,施工工期长,需与设计院联系进行设计变更,且本工程工期很紧,不适合采用挂篮施工。由于受箱梁变宽段及梁体变高段的影响,且跨河段现浇箱梁孔数较少,采用移动模架施工,技术难度大且经济效益很差。
而采用方法(2)和(4)相结合的方式施工有利于钢管桩的多次周转和减少钢管桩拔桩时的材料损耗,有利于日后梁柱式组合支架的拆除。
因此,为解决上述技术问题,确有必要提供一种新型的高架桥跨河段组合支架,以克服现有技术中的所述缺陷。
【实用新型内容】
为解决上述问题,本实用新型的目的在于提供一种承重能力好,安全系数高,用钢量小,成本低的高架桥跨河段组合支架。
为实现上述目的,本实用新型采取的技术方案为:一种高架桥跨河段组合支架,其包括钢管桩、防撞系梁、钢板挡土墙、水上贝雷平台、贝雷分配梁、贝雷架以及碗扣支架;其中,所述防撞系梁设置在钢管桩的内侧;所述钢板挡土墙设置在钢管桩的外侧;所述水上贝雷平台支承在钢管桩的顶部;所述贝雷分配梁支承在水上贝雷平台的顶部;所述贝雷架支承在贝雷分配梁的顶部;所述碗扣支架搭设于贝雷架上。
本实用新型的高架桥跨河段组合支架进一步设置为:于所述贝雷架的两端底部设有辅助钢管桩。
本实用新型的高架桥跨河段组合支架进一步设置为:所述钢管桩的直径为630mm,其上连接有剪刀撑。
本实用新型的高架桥跨河段组合支架还设置为:所述碗扣支架的两端延伸至贝雷架的下方,并支撑于地面上。
与现有技术相比,本实用新型具有如下有益效果:本实用新型的高架桥跨河段组合支架具有承重能力好,安全系数高,用钢量小,成本低等诸多优点。
【附图说明】
图1是本实用新型的高架桥跨河段组合支架的结构示意图。
【具体实施方式】
请参阅说明书附图1所示,本实用新型为一种高架桥跨河段组合支架,其设置在一高架桥9的底部,其由钢管桩1、防撞系梁2、钢板挡土墙3、水上贝雷平台4、贝雷分配梁5、贝雷架6以及碗扣支架7等几部分组成。
其中,所述钢管桩1的直径为630mm,其上连接有剪刀撑8,从而使该钢管桩1结构稳定。
所述防撞系梁2设置在钢管桩1的内侧,其能避免过往的船只碰撞钢管桩1。
所述钢板挡土墙3设置在钢管桩1的外侧,其能阻挡河道的污泥向钢管桩1倾覆。
所述水上贝雷平台4支承在钢管桩1的顶部;所述贝雷分配梁5支承在水上贝雷平台4的顶部。
所述贝雷架6支承在贝雷分配梁5的顶部。于所述贝雷架6的两端底部设有辅助钢管桩10,从而能够进一步支撑贝雷架6。
所述碗扣支架7搭设于贝雷架6上。所述碗扣支架7的两端延伸至贝雷架6的下方,并支撑于地面11上,使河道两侧的地面11也能支撑碗扣支架7。
以上的具体实施方式仅为本创作的较佳实施例,并不用以限制本创作,凡在本创作的精神及原则之内所做的任何修改、等同替换、改进等,均应包含在本创作的保护范围之内。

Claims (4)

1.一种高架桥跨河段组合支架,其特征在于:包括钢管桩、防撞系梁、钢板挡土墙、水上贝雷平台、贝雷分配梁、贝雷架以及碗扣支架;其中,所述防撞系梁设置在钢管桩的内侧;所述钢板挡土墙设置在钢管桩的外侧;所述水上贝雷平台支承在钢管桩的顶部;所述贝雷分配梁支承在水上贝雷平台的顶部;所述贝雷架支承在贝雷分配梁的顶部;所述碗扣支架搭设于贝雷架上。
2.如权利要求1所述的高架桥跨河段组合支架,其特征在于:于所述贝雷架的两端底部设有辅助钢管桩。
3.如权利要求1所述的高架桥跨河段组合支架,其特征在于:所述钢管桩的直径为630mm,其上连接有剪刀撑。
4.如权利要求1所述的高架桥跨河段组合支架,其特征在于:所述碗扣支架的两端延伸至贝雷架的下方,并支撑于地面上。
CN201420197707.1U 2014-04-21 2014-04-21 一种高架桥跨河段组合支架 Expired - Fee Related CN203782544U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420197707.1U CN203782544U (zh) 2014-04-21 2014-04-21 一种高架桥跨河段组合支架

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420197707.1U CN203782544U (zh) 2014-04-21 2014-04-21 一种高架桥跨河段组合支架

Publications (1)

Publication Number Publication Date
CN203782544U true CN203782544U (zh) 2014-08-20

Family

ID=51318747

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420197707.1U Expired - Fee Related CN203782544U (zh) 2014-04-21 2014-04-21 一种高架桥跨河段组合支架

Country Status (1)

Country Link
CN (1) CN203782544U (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107245953A (zh) * 2017-07-14 2017-10-13 北京市市政建设工程有限责任公司 一种多层桥梁结构的排架装置及交叉施工方法
CN110016866A (zh) * 2019-04-08 2019-07-16 中国铁建大桥工程局集团有限公司 一种城市桥梁上跨管廊的现浇施工方法
CN113235452A (zh) * 2021-06-11 2021-08-10 杭州萧宏建设环境集团有限公司 一种复杂工况下跨河钢管大跨径多线叠加用支架

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107245953A (zh) * 2017-07-14 2017-10-13 北京市市政建设工程有限责任公司 一种多层桥梁结构的排架装置及交叉施工方法
CN107245953B (zh) * 2017-07-14 2018-12-28 北京市市政一建设工程有限责任公司 一种多层桥梁结构的交叉施工方法
CN110016866A (zh) * 2019-04-08 2019-07-16 中国铁建大桥工程局集团有限公司 一种城市桥梁上跨管廊的现浇施工方法
CN113235452A (zh) * 2021-06-11 2021-08-10 杭州萧宏建设环境集团有限公司 一种复杂工况下跨河钢管大跨径多线叠加用支架

Similar Documents

Publication Publication Date Title
CN203925895U (zh) 用于风力发电塔的锚栓可更换式基础
CN106149768B (zh) 一种围护桩结合冠梁的地下结构的抗浮结构及其施工方法
CN104213717B (zh) 多层住宅一体化改造建造方法
CN205242848U (zh) 一种采用高强螺栓连接的预制装配式钢-混凝土组合梁
CN101235649A (zh) 一种盖挖基坑系统
CN202787271U (zh) 一种基坑支护用叠加式内支撑结构
CN203782544U (zh) 一种高架桥跨河段组合支架
CN103352471A (zh) 集装箱式活动房装配式型钢混凝土单双柱基础及施工方法
CN207608812U (zh) 一种板式橡胶支座防脱空装置
CN203924703U (zh) 倒棱台柱帽模板
CN202369930U (zh) 用于多层混凝土箱梁的门洞式承重排架装置
CN107313551A (zh) 一种钢筋桁架混凝土预制墙板及结构体系及其施工方法
CN205024719U (zh) 桩基础与地下连续墙一体化的逆作法施工竖向支撑体系
CN103981799B (zh) 一种钢管混凝土张弦劲性梁及其施工方法
CN204510989U (zh) 多级混凝土塔筒一体化结构
CN107620301B (zh) 一种地质加固装置
CN201169781Y (zh) 一种盖挖基坑结构
CN102535748A (zh) 加设工字型肋板矩形钢管混凝土柱及作法
CN202989942U (zh) 一种针对于软弱土或高回填土区围墙基础构造
CN205908089U (zh) 一种可抵抗泥石流的新型框架结构
CN205134352U (zh) 一种窄基塔独柱联合挖孔桩基础
CN204139190U (zh) 一种可吊装预制砖胎膜
CN203755781U (zh) 一种分段式中心立柱
CN206800435U (zh) 一种沿竖向发育狭长溶洞下压的交叉型承台结构
CN205804278U (zh) 一种装配式高桩码头上部结构体系

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140820

Termination date: 20150421

EXPY Termination of patent right or utility model