CN203654194U CN201320838002.9U CN201320838002U CN203654194U CN 203654194 U CN203654194 U CN 203654194U CN 201320838002 U CN201320838002 U CN 201320838002U CN 203654194 U CN203654194 U CN 203654194U
Authority
CN
China
Prior art keywords
bridge
groove
hole
bent cap
construction structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320838002.9U
Other languages
Chinese (zh)
Inventor
李荣生
霍恒玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Dafang Special Vehicle Co Ltd
Original Assignee
Suzhou Dafang Special Vehicle Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Dafang Special Vehicle Co Ltd filed Critical Suzhou Dafang Special Vehicle Co Ltd
Priority to CN201320838002.9U priority Critical patent/CN203654194U/en
Application granted granted Critical
Publication of CN203654194U publication Critical patent/CN203654194U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a quick construction structure for a bridge. The quick construction structure comprises a plurality of bridge units, wherein each bridge unit comprises a bridge pier embedded into the ground surface, a bridge pillar fixed to the upper part of the bridge pier, a cover beam fixed to the upper part of the bridge pillar and a large beam fixed to the upper part of the cover beam; a first hole/groove is formed in the lower end part of each bridge pillar; a second hole/groove is formed in the lower part of the cover beam; when each bridge pier, each bridge pillar and each cover beam are connected in sequence, each first hole/groove in the lower end part of the corresponding bridge pillar is sleeved with the upper part of the corresponding bridge pier; the second hole/groove in the lower part of each cover beam is sleeved with the upper part of the corresponding bridge pillar. Through the prefabrication of the bridge piers, the bridge pillars and the cover beams and the mounting of the bridge piers, the bridge pillars and the cover beams in the field in a sleeving manner, the quick construction structure for the bridge has a simple structure, convenience in installation, short construction period and low influence on an existing road.

Description

Bridge rapid construction structure
Technical field
the utility model relates to a kind of bridge rapid construction structure.
Background technology
be accompanied by the high speed development of China's economic, domestic each big and medium-sized cities population, vehicle rapid growth, cause road traffic flow to increase severely, and road imbalance between supply and demand is more sharp-pointed.Increase city existing road autos only ability and mainly change the measures such as grade separation, overhead and tunnel multilevel traffic by existing road widening upgrading, level crossing, construction method routinely, all there is long construction period in the civil engineering of various measures above, floor space is large, cause traffic not smooth, affect the current of pedestrian and vehicle, larger on traffic and surrounding enviroment impact.Therefore need one efficient, quick, and do not affect access bridge beam construction method.
Summary of the invention
an object of the present utility model is to provide a kind of bridge rapid construction structure.
for achieving the above object, the technical solution adopted in the utility model is:
a kind of bridge rapid construction structure, comprise multiple bridges unit, described bridge unit comprises the bridge pier that is embedded in ground, is fixed on the bridge post on described bridge pier top, is fixed on the bent cap on described bridge post top and is fixed on the crossbeam on described bent cap top, the bottom of described bridge post offers the first hole/groove, and the bottom of described bent cap offers the second hole/groove; When described bridge pier, bridge post and bent cap connects, the first hole/groove of described bridge post bottom is socketed in the top of described bridge pier, and the second hole/groove of described bent cap bottom is socketed in the top of described bridge post.
preferably, multiple described bridge unit set gradually, and the crossbeam of multiple described bridge unit is in turn connected to form track.
preferably, the position of burying described bridge pier on ground underground offers ground slots, and the socket part of described bridge pier and bridge post is positioned at described ground slots.
further preferably, in described ground slots, being provided with filler fills.
preferably, on described bent cap, be provided with cushion block, described crossbeam is fixed on described cushion block.
because technique scheme is used, the utility model compared with prior art has following advantages and effect:
the utility model is by prefabricated bridge pier, bridge post and bent cap, and the installation being socketed at the scene, and it is simple in structure, easy for installation, and short construction period is little on the impact of existing road.
Accompanying drawing explanation
accompanying drawing 1 is structural representation of the present utility model;
accompanying drawing 2 is the fractionation schematic diagram of the utility model Bridge unit.
wherein: 1, bridge unit; 10, bridge pier; 11, bridge post; 110, the first hole/groove; 12, crossbeam; 13, bent cap; 130, the second hole/groove; 2, ground slots; 3, cushion block; 4, ground; 5, filler.
The specific embodiment
below in conjunction with accompanying drawing and case study on implementation, the utility model is further described:
a kind of bridge rapid construction structure as shown in Figure 1, 2, comprise multiple bridges unit 1, bridge unit 1 comprises the bridge pier 10, the bridge post 11 that is fixed on bridge pier 10 tops that are embedded in ground 4, is fixed on the bent cap 13 on bridge post 11 tops and is fixed on the crossbeam 12 on bent cap 13 tops.Wherein:
the bottom of bridge post 11 offers the first hole/groove 110, and the bottom of bent cap 13 offers the second hole/groove 130; When bridge pier 10, bridge post 11 and bent cap 13 connect, the first hole/groove 110 of bridge post 10 bottoms is socketed in the top of bridge pier 10, and the second hole/groove 130 of bent cap 13 bottoms is socketed in the top of bridge post 11.The position of burying bridge pier 11 on ground 4 underground offers ground slots 2, and the socket part of bridge pier 10 and bridge post 11 is positioned at ground slots 2, and in ground slots 2, is provided with filler 5 and fills.
in addition, be provided with cushion block 3 on bent cap 13 tops, crossbeam 12 is fixed on cushion block 3.
the following specifically describes down the Fast Installation engineering method of this bridge construction:
bridge pier 10, bridge post 11 and the bent cap 13 of said structure are prefabricated in the factory; Squeeze into the position of bridge pier 10 on ground 4 and carry out milling ground slots 2, bridge pier 10 is vertically driven underground ground slots 2 is interior, bridge post 11 is vertically sling, made the first hole/groove 110 of bridge post 11 bottoms be socketed in the top of bridge pier 11, and at the interior filling filler 5 of ground slots 2, it is fixed;
bent cap 13 is installed on top at bridge post 11, and concrete is: bent cap 13 is sling, made the second hole/groove 130 of bent cap 13 bottoms be socketed in the top of bridge post 11 and fix; Cushion block 3 is installed on top at bent cap 13, and crossbeam 12 is fixed on cushion block 3.
when multiple bridges unit 1 sets gradually, the crossbeam 12 of multiple bridges unit 1 is in turn connected to form track.
above-described embodiment is only explanation technical conceive of the present utility model and feature, and its object is to allow person skilled in the art can understand content of the present utility model and implement according to this, can not limit protection domain of the present utility model with this.All equivalences of doing according to the utility model Spirit Essence change or modify, within all should being encompassed in protection domain of the present utility model.

Claims (5)

1. a bridge rapid construction structure, comprise multiple bridges unit, described bridge unit comprises the bridge pier that is embedded in ground, is fixed on the bridge post on described bridge pier top, is fixed on the bent cap on described bridge post top and is fixed on the crossbeam on described bent cap top, it is characterized in that: the bottom of described bridge post offers the first hole/groove, and the bottom of described bent cap offers the second hole/groove; When described bridge pier, bridge post and bent cap connects, the first hole/groove of described bridge post bottom is socketed in the top of described bridge pier, and the second hole/groove of described bent cap bottom is socketed in the top of described bridge post.
2. bridge rapid construction structure according to claim 1, is characterized in that: multiple described bridge unit set gradually, and the crossbeam of multiple described bridge unit is in turn connected to form track.
3. bridge rapid construction structure according to claim 1, is characterized in that: the position of burying described bridge pier on ground underground offers ground slots, and the socket part of described bridge pier and bridge post is positioned at described ground slots.
4. bridge rapid construction structure according to claim 3, is characterized in that: in described ground slots, be provided with filler and fill.
5. bridge rapid construction structure according to claim 1, is characterized in that: on described bent cap, be provided with cushion block, described crossbeam is fixed on described cushion block.
CN201320838002.9U 2013-12-18 2013-12-18 Quick construction structure for bridge Expired - Lifetime CN203654194U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320838002.9U CN203654194U (en) 2013-12-18 2013-12-18 Quick construction structure for bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320838002.9U CN203654194U (en) 2013-12-18 2013-12-18 Quick construction structure for bridge

Publications (1)

Publication Number Publication Date
CN203654194U true CN203654194U (en) 2014-06-18

Family

ID=50920601

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320838002.9U Expired - Lifetime CN203654194U (en) 2013-12-18 2013-12-18 Quick construction structure for bridge

Country Status (1)

Country Link
CN (1) CN203654194U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669221A (en) * 2013-12-18 2014-03-26 苏州大方特种车股份有限公司 Bridge rapid construction method and structure
CN105803925A (en) * 2016-03-17 2016-07-27 浙江大学 Quick connection method for prefabricated steel pipe constraint type steel concrete pier columns and cover beam
CN107059589A (en) * 2017-04-24 2017-08-18 陆厚铭 A kind of stake beam bridge overall structure and construction technology and construction machinery

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669221A (en) * 2013-12-18 2014-03-26 苏州大方特种车股份有限公司 Bridge rapid construction method and structure
CN105803925A (en) * 2016-03-17 2016-07-27 浙江大学 Quick connection method for prefabricated steel pipe constraint type steel concrete pier columns and cover beam
CN105803925B (en) * 2016-03-17 2017-05-17 浙江大学 Quick connection method for prefabricated steel pipe constraint type steel concrete pier columns and cover beam
CN107059589A (en) * 2017-04-24 2017-08-18 陆厚铭 A kind of stake beam bridge overall structure and construction technology and construction machinery

Similar Documents

Publication Publication Date Title
CN201850498U (en) Steel trestle in water
CN203654194U (en) Quick construction structure for bridge
CN101922158B (en) Device and method for integrally underpinned vibration isolation device of subway underpass building foundation
CN202543953U (en) Supporting structure for shallow tunnel in overpass operation
CN203654193U (en) Quick bridge construction structure
CN102912701B (en) Multi-functional left-turn directional interchange overpass
CN103696370B (en) A kind of Quick bridge construction method and structure
CN103147386B (en) Approach bridge vehicle
CN103669221A (en) Bridge rapid construction method and structure
CN203284750U (en) Cast-in-place concrete anti-collision guardrail
CN103578346B (en) A kind of simply supported girder bridge teaching simulation structure
CN2913433Y (en) Tridimensional traffic lines and elevated track utilizing road middle and edge space
CN206070724U (en) The structure at design large span deep buried metro station is combined using Y shape pillar with uplift pile
CN202181504U (en) Box beam
CN204151675U (en) The bogie of earth anchored suspension bridge cat road track cable
CN204356602U (en) A kind of intersection constructed parking garage structure
CN203200773U (en) Integral type prefabricated bridge pier and foundation structure
CN202214676U (en) Bridge extension device
CN103147387A (en) Double-spliced type combining bridge structure
CN205711696U (en) A kind of drag-line and the overpass encircleing combined system
CN201169781Y (en) Cap digging pit structure
CN204626641U (en) A kind of suspension type building body
CN103147460B (en) Integrated prefabricated pier and foundation structure
CN203200643U (en) Double-splicing mode combined bridge structure
CN203807903U (en) Three-layer flyover

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20140618