CN206070724U - The structure at design large span deep buried metro station is combined using Y shape pillar with uplift pile - Google Patents
The structure at design large span deep buried metro station is combined using Y shape pillar with uplift pile Download PDFInfo
- Publication number
- CN206070724U CN206070724U CN201620900698.7U CN201620900698U CN206070724U CN 206070724 U CN206070724 U CN 206070724U CN 201620900698 U CN201620900698 U CN 201620900698U CN 206070724 U CN206070724 U CN 206070724U
- Authority
- CN
- China
- Prior art keywords
- shape pillar
- uplift pile
- station
- base plate
- large span
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
This utility model belongs to underground engineering construction field, more particularly to a kind of employing Y shape pillar is combined the structure at design large span deep buried metro station with uplift pile, it is characterized in that, the bifurcated top of the Y shape pillar is connected with top board beam, the middle part of the Y shape pillar is connected with the middle plate-girder, the lower end of the Y shape pillar is connected with the floor beams, and the top of the uplift pile is connected with the lower surface of base plate, and the uplift pile is arranged on the Y shape pillar intercolumniation span centre of base plate.Top bifurcated fulcrum when the buried underground structure of subway is designed using y-type structure post reduces underground structure top board span, reduce base plate span using base plate uplift pile, so as to create the method for designing for using space between roof and floor compared with large span, in the case where construction costs is not improved substantially, top board and base arrangement stress are solved rationally, solve the problems, such as that passenger uses space post net intensive again, improve the comfortableness that station uses.
Description
Technical field
This utility model belongs to underground engineering construction field, and this utility model is related to one kind and is tied with uplift pile using Y shape pillar
The structure at design large span deep buried metro station is closed, the top using y-type structure post when subway underground structure is designed is specifically referred to
Part fork fulcrum reduces underground structure top board span, reduces base plate span using base plate uplift pile, so as to create between roof and floor
The method for designing in space is used compared with large span.
Background technology
As the fast development in current city, land supply are nervous, space is wanted increasingly to be taken seriously to underground, it is complete at present
The state overwhelming majority is building or is planning to build subway in big city.
With the expansion of subway construction scale, buried underground station is more and more, and generally such station has larger bottom
Portion's hydraulic pressure and larger top earthing and overburden pressure.If more three layers of underground station bottom hydraulic pressure is up to 220kPa, four layers of car
Bottom hydraulic pressure stand up to 300kPa, top board vertical load includes that deadweight, earthing, overcharge on ground also have 100kPa or so.To solve
So big top/bottom part load, more than the structure design of current subway open-cut station using 8 ~ 10m standard span, structural column adopts
Right cylinder, this span limit the arrangement of space to a certain extent, have larger obstruction to passenger flow, and inter-visibility is poor, perception
Also it is poor.As bottom hydraulic pressure is larger, such buried station generally leans on earthing and dead load meet anti-floating requirement, needs
Other measure of anti float, such as ballast, capping beam, uplift pile, anti-float anchor rod etc. are set, and we generally consider for uplift pile etc. to be located at post
Under, just with uplift pile anti-floating act on, and ignore which can be used as fulcrum force, the cross-cut to base plate under base plate
Effect.
There is other features at the buried station of subway open cut:1st, middle plate stress is less, generally only 5 ~ 10kPa or so, middle plate
The impact that span increase brings is less;2nd, the main use space of passenger is in station hall layer and station layer.
Need badly in sum and open up a kind of new mentality of designing, roof and floor structure can be rationally solved under the conditions of buried and be received
Power problem, can increase station subway concourse again and the passenger of station layer uses space.
Station is had at present by simply significantly increasing roof and floor, beam section size and arrangement of reinforcement to create long-span space,
Structure floor height is sacrificed to a certain extent, and economy is also poor.
Utility model content
Ask to solve station layer and station hall layer larger use space, the larger design load of roof and floor, structural anti-buoyancy
Topic, this utility model provide the structure that a kind of employing Y shape pillar is combined design large span deep buried metro station with uplift pile.
The technical scheme adopted by this utility model for:
A kind of employing Y shape pillar is combined the structure at design large span deep buried metro station with uplift pile, it is characterised in that included
Top board, middle plate, base plate, Y shape pillar, uplift pile, the top board, middle plate, base plate from top to bottom set gradually, the lower section of the top board
Top board beam is provided with, middle plate-girder below the middle plate, is provided with, floor beams, the Y shape pillar below the base plate, is provided with
Bifurcated top connect with top board beam, the middle part of the Y shape pillar is connected with the middle plate-girder, the lower end of the Y shape pillar with it is described
Floor beams connect, and the top of the uplift pile is connected with the lower surface of base plate, and the uplift pile is arranged on the Y shape pillar intercolumniation of base plate
Span centre.
The bifurcation of the Y shape pillar is located at the top of middle plate-girder.
The Y shape pillar is included but is not limited to:Along station longitudinal direction Y shape pillar, along the horizontal Y shape pillar in station, along station longitudinal direction and horizontal stroke
To both direction Y shape pillar;
The material of the Y shape pillar is included but is not limited to:Reinforced column, steel pipe column, steel column, steel core concrete column,
Profile steel concrete column.
The uplift pile is included but is not limited to:Cast-in-situ bored pile, artificial digging pile, steel-pipe pile.
The jag position of the Y shape pillar can be located at any height of subway station station hall layer or mechanical floor.
The beneficial effects of the utility model are:
1st, this utility model is by the way of Y shape pillar is combined with uplift pile, for the stress of the buried open-cut station in underground
Feature, by the innovation of rational component arrangement form, has reached and has made full use of the underground space, the mesh of reasonable distribution structure stress
's;
2nd, this utility model is for the usual top plate earth-covering load of subway underground structure is larger, buried underground station base plate hydraulic pressure
Greatly, common station structure span is little, intensive post net, inconvenient use the characteristics of, adopt Y when the buried underground structure of subway is designed
The top bifurcated fulcrum of type structural column reduces underground structure top board span, reduces base plate span using base plate uplift pile, so as to create
The method for designing for using space between roof and floor compared with large span is made, in the case where construction costs is not improved substantially, is rationally solved
Top board and base arrangement stress, solve the problems, such as that passenger uses space post net intensive again, improve the comfortableness that station uses;
3rd, under the background of subway Large scale construction, this utility model can be rationally and effectively to be provided using the underground space
More preferable thinking.
Description of the drawings
Fig. 1 is that this utility model is a kind of is combined design large span deep buried metro station vertical section using Y shape pillar with uplift pile
Schematic diagram.
Fig. 2 is that this utility model is a kind of is combined design large span deep buried metro station structure horizontal stroke using Y shape pillar with uplift pile
Generalized section.
Specific embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings:
In Fig. 1-2,1. station hall layer, 2. station layer, 3. top board, 4. in plate, 5. base plate, 6.Y type posts, 7. uplift pile,
8th, top board beam, 9. in plate-girder, 10. floor beams.
Embodiment
As shown in Figure 1-2, a kind of employing Y shape pillar is combined the structure at design large span deep buried metro station, bag with uplift pile
Top board 3, middle plate 4, base plate 5, Y shape pillar 6, uplift pile 7 are included, top board 3, middle plate 4, base plate 5 from top to bottom set gradually, top board 3
Lower section is provided with top board beam 8, and the lower section of middle plate 4 is provided with middle plate-girder 9, and the lower section of base plate 5 is provided with floor beams 10, top board 3, in
It is station hall layer 1 between plate 4, is station layer 2 between middle plate 4, base plate 5, the bifurcated top of Y shape pillar 6 is connected with top board beam 8, Y shape pillar
6 middle part is connected with middle plate-girder 9, and the lower end of Y shape pillar 6 is connected with floor beams 10, the top of uplift pile 7 and the lower surface of base plate 5
Connect, uplift pile 7 is arranged on the 6 intercolumniation span centre of Y shape pillar of base plate 5.
The bifurcation of Y shape pillar 6 is located at the top of middle plate-girder 9.
Y shape pillar 6 is included but is not limited to:Along station longitudinal direction Y shape pillar, along the horizontal Y shape pillar in station, along station vertical and horizontal two
Individual direction Y shape pillar;
The material of Y shape pillar 6 is included but is not limited to:Reinforced column, steel pipe column, steel column, steel core concrete column, shaped steel
Concrete column.
Uplift pile 6 is included but is not limited to:Cast-in-situ bored pile, artificial digging pile, steel-pipe pile.
The jag position of Y shape pillar 6 can be located at any height of subway station station hall layer 1 or mechanical floor.
Structure in this utility model is including but not limited to applied in two layers of underground, three layers, four layers, five layers of open cut subway
Stand, station includes but is not limited to single row configuration post, two-row structure post, multiple rows of structural column.
Specific construction mode:
(1)7 real work of uplift pile:Uplift pile 7 generally can be by two kinds of forms of ground construction or foundation ditch bottom application work, when adopting
During with cast-in-situ bored pile, Punching Borehole Cast-in-place Concrete Pile, generally using Ground Operation, then pore-forming operation first hangs steel reinforcement cage, finally fills
Note resistance to plucking pile concrete is to structure base slab 5;When using artificial digging pile form, foundation ditch bottom application work is generally adopted, in foundation ditch
Bottom pore-forming, then lower section steel reinforcement cage, under last concrete perfusion to base plate 5;
(2)Y shape pillar 6 is constructed:Y shape pillar 6 generally using from bottom to up pour mode, first banding steel cage or placement type
Steel reinforcing bar installs steel pipe, then casting concrete vibration compacting;
(3)Overall station construction order:Station construct along doing mode, that is, generally using open cut building enclosure, excavation pit,
Construction uplift pile 7, constructing structure base plate 5, structural column, plate 4 and counter structure post, constructing structure top board 3 in construction.
This utility model is little using 6 top length of support of Y shape pillar, and lower post length of support is big, i.e., top board 3 has less span
It is and middle plate 4 and base plate 5 have compared with large span, big so as to directly solve the problems, such as 3 stress of top board;By arranging uplift pile 7 bottom of at
The intercolumniation span centre of plate 5, can effectively reduce 5 span of base plate, also solve base plate 5 and receive while whole anti-uplift is solved the problems, such as
The big problem of power;Middle plate 4 is less due to stress, can be by 4 size effectively solving of plate-girder 9 or middle plate in appropriate increase, increase
Physical dimension do not affect 2 space of station hall layer 1 and station layer, cost is less.
Above 1 embodiment of the present utility model is described in detail, but the content is only of the present utility model
Preferred embodiment, it is impossible to be considered as limiting practical range of the present utility model.It is all to be made according to this utility model application range
Impartial change with improve etc., still all should belong within patent covering scope of the present utility model.
Claims (6)
1. a kind of employing Y shape pillar is combined the structure at design large span deep buried metro station with uplift pile, it is characterised in that including top
Plate, middle plate, base plate, Y shape pillar, uplift pile, the top board, middle plate, base plate from top to bottom set gradually, and set below the top board
Top board beam is equipped with, middle plate-girder below the middle plate, is provided with, floor beams below the base plate, are provided with, the Y shape pillar
Bifurcated top is connected with top board beam, and the middle part of the Y shape pillar is connected with the middle plate-girder, the lower end of the Y shape pillar and the bottom
Plate-girder connects, and the top of the uplift pile is connected with the lower surface of base plate, the uplift pile be arranged on the Y shape pillar intercolumniation of base plate across
In.
2. a kind of employing Y shape pillar according to claim 1 is combined the knot at design large span deep buried metro station with uplift pile
Structure, it is characterised in that:The bifurcation of the Y shape pillar is located at the top of middle plate-girder.
3. a kind of employing Y shape pillar according to claim 1 is combined the knot at design large span deep buried metro station with uplift pile
Structure, it is characterised in that:The Y shape pillar is included but is not limited to:Indulge along station longitudinal direction Y shape pillar, along the horizontal Y shape pillar in station, along station
To with horizontal both direction Y shape pillar.
4. a kind of employing Y shape pillar according to claim 1 is combined the knot at design large span deep buried metro station with uplift pile
Structure, it is characterised in that:The material of the Y shape pillar is included but is not limited to:Reinforced column, steel pipe column, steel column, steel tube concrete
Earth pillar, profile steel concrete column.
5. a kind of employing Y shape pillar according to claim 1 is combined the knot at design large span deep buried metro station with uplift pile
Structure, it is characterised in that:The uplift pile is included but is not limited to:Cast-in-situ bored pile, artificial digging pile, steel-pipe pile.
6. a kind of employing Y shape pillar according to claim 1 is combined the knot at design large span deep buried metro station with uplift pile
Structure, it is characterised in that:The jag position of the Y shape pillar can be located at any height of subway station station hall layer or mechanical floor.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620900698.7U CN206070724U (en) | 2016-08-19 | 2016-08-19 | The structure at design large span deep buried metro station is combined using Y shape pillar with uplift pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620900698.7U CN206070724U (en) | 2016-08-19 | 2016-08-19 | The structure at design large span deep buried metro station is combined using Y shape pillar with uplift pile |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206070724U true CN206070724U (en) | 2017-04-05 |
Family
ID=58430792
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620900698.7U Active CN206070724U (en) | 2016-08-19 | 2016-08-19 | The structure at design large span deep buried metro station is combined using Y shape pillar with uplift pile |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206070724U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106168053A (en) * | 2016-08-19 | 2016-11-30 | 中铁隧道勘测设计院有限公司 | Y shape pillar is used to be combined the structure at design large span deep buried metro station with uplift pile |
CN107387157A (en) * | 2017-09-10 | 2017-11-24 | 沈阳建筑大学 | A kind of buried large-scale anti-war ball-type Dungeon of taking precautions against natural calamities |
CN109166450A (en) * | 2018-10-25 | 2019-01-08 | 中铁第六勘察设计院集团有限公司 | A kind of subway station transverse structure computation model that pressing board net span calculates |
-
2016
- 2016-08-19 CN CN201620900698.7U patent/CN206070724U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106168053A (en) * | 2016-08-19 | 2016-11-30 | 中铁隧道勘测设计院有限公司 | Y shape pillar is used to be combined the structure at design large span deep buried metro station with uplift pile |
CN107387157A (en) * | 2017-09-10 | 2017-11-24 | 沈阳建筑大学 | A kind of buried large-scale anti-war ball-type Dungeon of taking precautions against natural calamities |
CN109166450A (en) * | 2018-10-25 | 2019-01-08 | 中铁第六勘察设计院集团有限公司 | A kind of subway station transverse structure computation model that pressing board net span calculates |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106168053A (en) | Y shape pillar is used to be combined the structure at design large span deep buried metro station with uplift pile | |
CN103074941B (en) | Assembling regeneration concrete node and the practice of steel bar girder beam are contained in a kind of end | |
CN202831402U (en) | Concrete filled steel tubular column with inner-connected circular pipe and outer-sleeved concrete filled steel tube | |
CN104294753A (en) | Bridge prefabricated hollow pier stud connecting structure and construction method thereof | |
CN101215819B (en) | Separated double-layer bridge-floor cable stayed bridge | |
CN103343548B (en) | Foundation type for power transmission tower and bearing capacity calculation method for same | |
WO2017084573A1 (en) | Upheaval-resisting support structure | |
CN206070724U (en) | The structure at design large span deep buried metro station is combined using Y shape pillar with uplift pile | |
CN103104102B (en) | Construction method for underground storey-addition reconstruction | |
CN205806684U (en) | A kind of across base pit engineering conduit wiring suspension structure | |
CN202809501U (en) | Reinforced load reducing structure of motorway high filling culvert in mountainous area | |
CN103603435A (en) | Assembled concrete seismic beam-column frame and construction method thereof | |
CN202730749U (en) | Prefabricated reinforced concrete H-shaped support pile | |
CN203583674U (en) | Assembly type concrete anti-seismic beam column framework | |
CN210766863U (en) | Multi-arch rib anchoring plate retaining wall | |
CN102392417B (en) | Dual-cantilever bearing support structure for large steel pipe and installation method | |
CN210013239U (en) | Prevent landslide protection retaining wall | |
CN202247719U (en) | Corresponding corrugated pre-stressed anti-sedimentation culvert pipe for bridge | |
CN205242441U (en) | Oval contrary shaft of doing of suspension type | |
CN103981799B (en) | A kind of concrete filled steel tube opens string stiff beam and construction method thereof | |
CN204174527U (en) | The hollow pier stud syndeton of a kind of bridge prefabrication | |
CN203603176U (en) | Historic building foundation overall tray shock insulating and reinforcing structure | |
CN203174626U (en) | Geogrid reinforced wall | |
CN202989942U (en) | Wall foundation structure for soft soil or high backfill soil area | |
CN203429661U (en) | Basement with additional downward layers |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20180611 Address after: 300000 Tianjin free trade zone (Airport Economic Zone), 2-3116 South Road 88. Patentee after: CHINA RAILWAY LIUYUAN GROUP CO., LTD. Address before: 300000 Hongqiao District, Tianjin City, Bridge South East Road Patentee before: Zhongtie Tunnel Survey and Design Inst., Ltd. |