CN203589536U - GW6-type disconnecting switch fast-assembling maintenance support - Google Patents

GW6-type disconnecting switch fast-assembling maintenance support Download PDF

Info

Publication number
CN203589536U
CN203589536U CN201320817314.1U CN201320817314U CN203589536U CN 203589536 U CN203589536 U CN 203589536U CN 201320817314 U CN201320817314 U CN 201320817314U CN 203589536 U CN203589536 U CN 203589536U
Authority
CN
China
Prior art keywords
steel pipe
plate base
steel
steel plate
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320817314.1U
Other languages
Chinese (zh)
Inventor
郭希军
王从军
朱孔达
陈静
李锑
王伟哲
徐志波
刘海涛
肖雪峰
钟振东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Linyi Power Supply Co of State Grid Shandong Electric Power Co Ltd
State Grid Corp of China SGCC
Original Assignee
Linyi Power Supply Co of State Grid Shandong Electric Power Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Linyi Power Supply Co of State Grid Shandong Electric Power Co Ltd, State Grid Corp of China SGCC filed Critical Linyi Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority to CN201320817314.1U priority Critical patent/CN203589536U/en
Application granted granted Critical
Publication of CN203589536U publication Critical patent/CN203589536U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Ladders (AREA)

Abstract

本实用新型公开了一种GW6型隔离开关快装检修支架,其要点是它包括通过螺栓与槽钢相互固定连接的钢板底座;所述钢板底座上固定设有钢管支架;所述钢管支架上插接有顶端带吊装鼻的L型吊装钢管;所述钢管支架上设有攀爬梯。本实用新型结构合理、设计新颖,由于钢板底座可以通过螺栓和槽钢固定在电力设备的支架上,支撑强度高,无需使用吊车,准备时间短,减少了不必要的开支;同时,L型吊装钢管与钢管支架相互插接,吊装鼻可以吊装母线,操作人员可以轻松的进行安装和更换作业。本实用新型解决了现有技术准备时间长、劳动强度大、成本高和工作效率低的技术问题。

The utility model discloses a GW6 type isolating switch quick-installation maintenance bracket, the main point of which is that it includes a steel plate base which is fixedly connected with channel steel through bolts; the steel plate base is fixed with a steel pipe bracket; An L-shaped hoisting steel pipe with a hoisting nose on the top is connected; a climbing ladder is provided on the steel pipe bracket. The utility model has reasonable structure and novel design. Since the steel plate base can be fixed on the support of electric equipment through bolts and channel steel, the supporting strength is high, no crane is needed, the preparation time is short, and unnecessary expenses are reduced; at the same time, L-shaped hoisting The steel pipe and the steel pipe support are inserted into each other, the lifting nose can lift the busbar, and the operator can easily perform installation and replacement operations. The utility model solves the technical problems of long preparation time, high labor intensity, high cost and low work efficiency in the prior art.

Description

GW6型隔离开关快装检修支架GW6 type isolating switch quick installation maintenance bracket

技术领域  technical field

本实用新型属于电力设备检修器具技术领域,具体涉及一种GW6型隔离开关快装检修支架。  The utility model belongs to the technical field of electric equipment maintenance equipment, and in particular relates to a GW6 type isolating switch quick-installation maintenance bracket. the

背景技术 Background technique

 现有技术中,在对变电站运行刀闸进行检修时,由于刀闸由上、下两节瓷瓶组成,高度较高,检修难度大,需要安装并使用检修支架甚至使用吊车来操作,安装、拆除检修支架通常需要6人两个小时才能完成,由于准备工作时间长,拆装工作量大,劳动强度加大,人力、物力费用高的原因,严重影响了工作进度。  In the prior art, when overhauling the operating knife switch of the substation, since the knife switch is composed of upper and lower porcelain vases, the height is relatively high, and maintenance is difficult. It is necessary to install and use maintenance brackets or even use a crane to operate, install and dismantle It usually takes 6 people and two hours to complete the maintenance of the bracket. Due to the long preparation time, heavy disassembly and assembly workload, increased labor intensity, and high manpower and material costs, the work progress has been seriously affected. the

发明内容  Invention content

本实用新型专利的目的是解决现有技术存在准备时间长、劳动强度大、成本高和工作效率低的技术问题,提供一种GW6型隔离开关快装检修支架。  The purpose of this utility model patent is to solve the technical problems of long preparation time, high labor intensity, high cost and low work efficiency in the prior art, and provide a GW6 type isolating switch quick installation and maintenance bracket. the

本实用新型一种GW6型隔离开关快装检修支架,其要点是它包括通过螺栓与槽钢相互固定连接的钢板底座;所述钢板底座上固定设有钢管支架;所述钢管支架上插接有顶端带吊装鼻的L型吊装钢管;所述钢管支架上设有攀爬梯。  The utility model is a GW6 type isolating switch fast-installation and maintenance support, and its main point is that it includes a steel plate base fixedly connected to the channel steel through bolts; the steel plate base is fixed with a steel pipe support; the steel pipe support is plugged with An L-shaped hoisting steel pipe with a hoisting nose at the top; a climbing ladder is provided on the steel pipe bracket. the

为了提高支撑强度,所述钢管支架通过支撑杆与钢板底座固定连接,所述钢管支架与钢板底座的连接处设有加强筋。  In order to improve the support strength, the steel pipe support is fixedly connected with the steel plate base through the support rod, and the connection between the steel pipe support and the steel plate base is provided with reinforcing ribs. the

本实用新型结构合理、设计新颖,由于钢板底座可以通过螺栓和槽钢固定在电力设备的支架上,支撑强度高,无需使用吊车,准备时间短,减少了不必要的开支;同时,L型吊装钢管与钢管支架相互插接,吊装鼻可以吊装母线,操作人员可以轻松的进行安装和更换作业。本实用新型解决了现有技术准备时间长、劳动强度大、成本高和工作效率低的技术问题。  The utility model has reasonable structure and novel design. Since the steel plate base can be fixed on the bracket of the electric equipment through bolts and channel steel, the supporting strength is high, no crane is needed, the preparation time is short, and unnecessary expenses are reduced; at the same time, the L-shaped hoisting The steel pipe and the steel pipe support are inserted into each other, the lifting nose can lift the busbar, and the operator can easily perform installation and replacement operations. The utility model solves the technical problems of long preparation time, high labor intensity, high cost and low work efficiency in the prior art. the

附图说明 Description of drawings

附图是本实用新型的结构示意图。  Accompanying drawing is the structural representation of the utility model. the

图中1、吊装鼻 2、L型吊装钢管 3、攀爬梯 4、钢管支架 5、支撑杆 6、螺栓 7、槽钢 8、加强筋 9、钢板底座  In the figure 1, hoisting nose 2, L-shaped hoisting steel pipe 3, climbing ladder 4, steel pipe bracket 5, support rod 6, bolt 7, channel steel 8, reinforcing rib 9, steel plate base

具体实施方式 Detailed ways

 根据附图,本实用新型一种GW6型隔离开关快装检修支架,它包括通过螺栓6与槽钢7相互固定连接的钢板底座9;所述钢板底座9上固定设有钢管支架4;所述钢管支架4上插接有顶端带吊装鼻1的L型吊装钢管2;所述钢管支架4上设有攀爬梯3;所述钢管支架4通过支撑杆5与钢板底座9固定连接,钢管支架4与钢板底座9的连接处设有加强筋8。  According to the accompanying drawings, the utility model is a GW6 type isolating switch quick installation and maintenance bracket, which includes a steel plate base 9 that is fixedly connected to each other through a bolt 6 and a channel steel 7; the steel plate base 9 is fixedly provided with a steel pipe support 4; The steel pipe support 4 is plugged with an L-shaped hoisting steel pipe 2 with a lifting nose 1 at the top; the steel pipe support 4 is provided with a climbing ladder 3; 4 and the connection of the steel plate base 9 are provided with reinforcing ribs 8 . the

本实用新型的制作成本低,只需通过螺栓和槽钢将钢板底座固定在电力设备的支架上即可固定,且支撑强度高,安全性高;并且,L型吊装钢管参考吊车吊臂的设计原理,使得操 作人员可以轻松的将母线固定在吊装鼻上,以便进行安装和更换作业;操作人员在高空作业时,可以将安全绳索拴在攀爬梯上进行打结,提高了操作人员的安全性。  The utility model has low production cost, and only needs to fix the steel plate base on the bracket of the electric equipment through bolts and channel steel, and it can be fixed, and the support strength is high, and the safety is high; moreover, the L-shaped hoisting steel pipe refers to the design of the crane arm The principle allows the operator to easily fix the busbar on the lifting nose for installation and replacement operations; when the operator is working at heights, he can tie the safety rope to the climbing ladder for knotting, which improves the operator's safety safety. the

本实用新型设计合理,与使用吊车作业相比,大大降低了维修成本;并且,准备时间也大大缩短,提高了工作效率。  The utility model has a reasonable design, and compared with the crane operation, the maintenance cost is greatly reduced; moreover, the preparation time is also greatly shortened, and the work efficiency is improved. the

Claims (2)

1. a GW6 type isolating switch fast-assembling maintenance support, is characterized in that it comprises the steel plate base being mutually permanently connected by bolt and channel-section steel; On described steel plate base, be fixed with steel pipe support; On described steel pipe support, be plugged with the L-type lifting steel pipe of top band lifting nose; Described steel pipe support is provided with ladder stand.
2. a kind of GW6 type isolating switch fast-assembling maintenance support according to claim 1, is characterized in that described steel pipe support is fixedly connected with steel plate base by support bar, and the junction of described steel pipe support and steel plate base is provided with reinforcement.
CN201320817314.1U 2013-12-05 2013-12-05 GW6-type disconnecting switch fast-assembling maintenance support Expired - Fee Related CN203589536U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320817314.1U CN203589536U (en) 2013-12-05 2013-12-05 GW6-type disconnecting switch fast-assembling maintenance support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320817314.1U CN203589536U (en) 2013-12-05 2013-12-05 GW6-type disconnecting switch fast-assembling maintenance support

Publications (1)

Publication Number Publication Date
CN203589536U true CN203589536U (en) 2014-05-07

Family

ID=50587389

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320817314.1U Expired - Fee Related CN203589536U (en) 2013-12-05 2013-12-05 GW6-type disconnecting switch fast-assembling maintenance support

Country Status (1)

Country Link
CN (1) CN203589536U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105470839A (en) * 2015-11-25 2016-04-06 国网河南洛宁县供电公司 Support used for isolation switch overhauling

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105470839A (en) * 2015-11-25 2016-04-06 国网河南洛宁县供电公司 Support used for isolation switch overhauling

Similar Documents

Publication Publication Date Title
CN102040166A (en) Hoisting tool for equipment on pillar
CN201450254U (en) Power switch installation hanger
CN201517022U (en) Lifting tools for pole-mounted equipment
CN203998604U (en) The be threaded vertical reinforcement erecting equipment of form of employing
CN203359893U (en) Portable lift
CN102946065B (en) Employing electric substation pipe bus bar column insulator more changing device realizes the method for post insulator replacing
CN201656340U (en) High voltage pipe busbar support insulator replacement tool
CN201737616U (en) Double-lifting pole
CN203284128U (en) Hoisting tool of main mechanism of switch blade
CN203589536U (en) GW6-type disconnecting switch fast-assembling maintenance support
CN204237458U (en) The laborsaving lifting utensil of a kind of electrical equipment
CN103332608B (en) GW6 disconnecting link porcelain knob is changed special pole and is hung
CN203461720U (en) Simple cantilever hoisting machine
CN203284094U (en) Rod hanger special for GW6 knife switch porcelain column replacement
CN202856246U (en) Insulator replacement device
CN105366559A (en) Small hoisting machine fixed on channel steel framework
CN204224152U (en) A kind of simple machine hoisting device safeguarded for electrical equipment
CN204384733U (en) Bus plug-in strip Lift-on/Lift-off System
CN209306856U (en) Small-sized separation type electrical hoisting apparatus
CN102570325B (en) A kind of light hoisting device for converting station
CN202864797U (en) Portable assembly and disassembly frame
CN203545559U (en) Electric meter box hoisting tool
CN203288976U (en) Isolating switch hoisting device
CN202657875U (en) Novel porcelain insulator displacement device
CN203415877U (en) Hoisting tool for replacing isolation switch

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140507

Termination date: 20141205

EXPY Termination of patent right or utility model