CN203345999U - Special multifunctional lifting frame for busbar bridge - Google Patents

Special multifunctional lifting frame for busbar bridge Download PDF

Info

Publication number
CN203345999U
CN203345999U CN 201320273259 CN201320273259U CN203345999U CN 203345999 U CN203345999 U CN 203345999U CN 201320273259 CN201320273259 CN 201320273259 CN 201320273259 U CN201320273259 U CN 201320273259U CN 203345999 U CN203345999 U CN 203345999U
Authority
CN
China
Prior art keywords
base
column
busbar
construction
hoisting frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201320273259
Other languages
Chinese (zh)
Inventor
肖立建
张玉亮
杨立民
刘鑫
刘忠顺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Cangzhou Power Supply Co of State Grid Hebei Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Cangzhou Power Supply Co of State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Hebei Electric Power Co Ltd, Cangzhou Power Supply Co of State Grid Hebei Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN 201320273259 priority Critical patent/CN203345999U/en
Application granted granted Critical
Publication of CN203345999U publication Critical patent/CN203345999U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

一种母线桥专用多功能吊装架,其技术方案是:它包括横梁和两支架,所述各支架由立柱和底座组成,立柱固定在底座上,所述横梁两侧由螺栓分别固定在各立柱上端,横梁上设置U形挂件。本实用新型使用时,底座可与母线槽匹配固定,根据吊装作业位置,在横梁上的U形挂件悬挂滑轮,设备则可由地面施工人员吊装到母线桥上。本实用新型轻巧灵活、安装方便,使用时省时、省力,节约施工成本,特别是它还可以起到护栏的作用,与施工人员的安全带形成了双重保护,确保施工人员的安全。

A special multifunctional hoisting frame for busbar bridges, the technical solution of which is: it includes a beam and two brackets, each bracket is composed of a column and a base, the column is fixed on the base, and the two sides of the beam are respectively fixed to each column by bolts On the upper end, a U-shaped pendant is arranged on the beam. When the utility model is in use, the base can be matched and fixed with the busway. According to the hoisting operation position, the U-shaped pendant on the beam hangs the pulley, and the equipment can be hoisted on the busbar bridge by the ground construction personnel. The utility model is light and flexible, easy to install, saves time and labor in use, and saves construction costs. In particular, it can also play the role of a guardrail, forming double protection with the safety belts of construction workers to ensure the safety of construction workers.

Description

一种母线桥专用多功能吊装架A special multifunctional hoisting frame for busbar bridges

技术领域 technical field

本实用新型涉及一种用于电缆工程的施工装置,特别是便于设备搬运、安装的母线桥专用多功能吊装架。  The utility model relates to a construction device for cable engineering, in particular to a special multifunctional hoisting frame for busbar bridges which is convenient for equipment handling and installation. the

背景技术 Background technique

随着电力建设的快速发展,新建变电站不断增加。在新建变电项目施工过程,母线桥设备安装是整个工程中占用人力资源较多、工期较长的施工项目。主变母线桥上面没有任何遮拦,安装支持绝缘子、硬母线、穿墙套管等设备时,施工人员只能站在几米高的母线桥槽钢上面依靠人力,用绳索一间一件的传送,十分费力,若使用设备吊装,则施工成本较高。在设备安装时既要保证自身安全,还要确保设备的安全,尤其在冬季,施工人员着装笨重,操作起来更为不便,耗时耗力又存有诸多不安全因素,进而影响到工程施工进度。  With the rapid development of power construction, new substations are increasing. In the construction process of new substation projects, the installation of busbar bridge equipment is a construction project that occupies more human resources and has a longer construction period in the entire project. There is no obstruction on the busbar bridge of the main transformer. When installing support insulators, hard busbars, wall bushings and other equipment, the construction personnel can only stand on the channel steel of the busbar bridge several meters high and rely on manpower to transfer one by one with ropes. It is very laborious, and if equipment is used for hoisting, the construction cost will be higher. When installing the equipment, it is necessary to ensure the safety of the equipment itself and the safety of the equipment. Especially in winter, the construction personnel wear heavy clothes, which makes the operation more inconvenient, time-consuming and labor-intensive, and there are many unsafe factors, which will affect the construction progress of the project. . the

实用新型内容 Utility model content

本实用新型的目的在于针对现有技术之弊端,提供一种便于设备搬运、有效提高施工效率的母线桥专用设备吊装架。  The purpose of this utility model is to provide a special equipment hoisting frame for busbar bridges, which is convenient for equipment handling and effectively improves construction efficiency, aiming at the disadvantages of the prior art. the

本实用新型所述问题是以下述技术方案实现的:  Problem described in the utility model is realized with following technical scheme:

一种母线桥专用多功能吊装架,特别之处是,它包括横梁和两支架,所述各支架由立柱和底座组成,立柱固定在底座上,所述横梁两侧由螺栓分别固定在各立柱上端,横梁上设置U形挂件。 A special multifunctional hoisting frame for a bus bridge, in particular, it includes a beam and two brackets, each bracket is composed of a column and a base, the column is fixed on the base, and the two sides of the beam are respectively fixed to each column by bolts On the upper end, a U-shaped pendant is arranged on the beam.

上述母线桥专用多功能吊装架,所述底座为立方体形,底座中部设有底座安装孔,底座安装孔为矩形截面的通孔,底座上部设有底座紧固螺栓。  The above-mentioned multifunctional hoisting frame for the busbar bridge has a cube-shaped base, a base installation hole is provided in the middle of the base, the base installation hole is a through hole with a rectangular cross-section, and a base fastening bolt is provided on the upper part of the base. the

上述母线桥专用多功能吊装架,所述各立柱上部设有立柱挂件。  The above-mentioned multifunctional hoisting frame dedicated to the busbar bridge is provided with a column hanger on the upper part of each column. the

上述母线桥专用多功能吊装架,所述横梁上设置的U形挂件为1-5个。  For the multifunctional hoisting frame dedicated to the busbar bridge, 1-5 U-shaped pendants are arranged on the beam. the

本实用新型针对变电站母线桥项目施工中,设备搬运耗时费力的问题而设计了一种专用于母线桥安装时的设备搬运吊装架。所述吊装架包括底座、立柱和横梁,底座与立柱固定,横梁由立柱支撑,在横梁上设置了多个U形挂件。本实用新型使用时,底座可与母线槽匹配固定,根据吊装作业位置,在横梁上的U形挂件悬挂滑轮,设备则可由地面施工人员吊装到母线桥上。本实用新型轻巧灵活、安装方便,使用时省时、省力,节约施工成本,特别是它还可以起到护栏的作用,与施工人员的安全带形成了双重保护,确保施工人员的安全。  The utility model aims at the problem of time-consuming and labor-intensive equipment handling in the construction of the substation bus bridge project, and designs an equipment handling and hoisting frame specially used for the installation of the bus bridge. The hoisting frame includes a base, a column and a beam, the base is fixed to the column, the beam is supported by the column, and a plurality of U-shaped pendants are arranged on the beam. When the utility model is in use, the base can be matched and fixed with the busway. According to the hoisting operation position, the U-shaped pendant on the beam hangs the pulley, and the equipment can be hoisted on the busbar bridge by the ground construction personnel. The utility model is light and flexible, easy to install, saves time and labor in use, and saves construction costs. In particular, it can also play the role of a guardrail, forming double protection with the safety belts of construction workers to ensure the safety of construction workers. the

附图说明 Description of drawings

下面结合附图对本实用新型作进一步说明。  Below in conjunction with accompanying drawing, the utility model is further described. the

图1是本实用新型结构示意图;  Fig. 1 is a structural representation of the utility model;

图2是图1的左视图。 Fig. 2 is a left side view of Fig. 1 .

图中各标号清单为:1、底座,2、底座紧固螺栓,3、立柱,4、横梁,5、U形挂件,6、立柱挂件,7、底座安装孔。  The list of each label in the figure is: 1. Base, 2. Base fastening bolts, 3. Column, 4. Beam, 5. U-shaped pendant, 6. Column pendant, 7. Base mounting hole. the

具体实施方式 Detailed ways

参看图1、图2,本实用新型由两个支架和由两支架支撑的横梁组成。支架由立柱3和底座1组成,立柱固定焊接在底座上。底座1是在母线桥上安装所述吊装架的基础,底座为立方体形,它采用槽钢和角铁焊接而成,在底座中部设有底座安装孔7,底座安装孔为矩形截面的通孔,底座安装孔的尺寸与母线桥上平铺槽钢的尺寸匹配。安装底座时,平铺槽钢直接插入底座安装孔内,再由底座上部设置的底座紧固螺栓2紧固,即可将实现底座稳定可靠的安装。底座安装完成后即可装配横梁4。横梁采用角钢制作,横梁的两侧由螺栓分别固定在各立柱上端,在横梁上设置数个U形挂件5,U形挂件5用于悬挂滑轮,可以根据吊装作业的位置,在横梁上的U形挂件悬挂滑轮。吊装架安装好后,由地面作业人员利用绳索和滑轮配合,把绝缘子等部件平稳传递给母线桥上的施工人员。  Referring to Fig. 1, Fig. 2, the utility model is made up of two supports and the beam supported by two supports. The bracket is composed of a column 3 and a base 1, and the column is fixedly welded on the base. The base 1 is the basis for installing the lifting frame on the busbar bridge. The base is in the shape of a cube. It is welded by channel steel and angle iron. There is a base mounting hole 7 in the middle of the base. The base mounting hole is a through hole with a rectangular cross section. , the size of the base mounting hole matches the size of the flat channel steel on the busbar bridge. When installing the base, the flat channel steel is directly inserted into the mounting hole of the base, and then fastened by the base fastening bolts 2 provided on the upper part of the base, so that the base can be installed stably and reliably. After the base installation is completed, the beam 4 can be assembled. The beam is made of angle steel, and the two sides of the beam are respectively fixed on the upper ends of the columns by bolts. Several U-shaped pendants 5 are arranged on the beam. The U-shaped pendants 5 are used to hang pulleys. Shaped pendant suspension pulley. After the hoisting frame is installed, the ground workers use ropes and pulleys to smoothly transfer the insulators and other components to the construction workers on the busbar bridge. the

仍参看图1、图2,本实用新型还可以作为安全护栏使用,与施工人员的安全带形成了双重保护,确保施工人员的安全。  Still referring to Fig. 1 and Fig. 2, the utility model can also be used as a safety guardrail, forming a double protection with the safety belt of the construction personnel to ensure the safety of the construction personnel. the

参看图2,在各立柱3上部设有立柱挂件6,立柱挂件可以供施工人员悬挂工具或设备部件,避免这些物品由高空坠落。  Referring to Fig. 2, a column hanger 6 is provided on each column 3 top, and the column hanger can hang tools or equipment parts for construction personnel to prevent these items from falling from a high altitude. the

现场测试,在某110kV变电站施工中采用本实用新型,该变电站母线桥长8米,共有支持绝缘子45只。首先是在母线桥上安装所述吊装架,用时5分钟;施工时,由地面作业人员利用绳索和滑轮配合,把支持绝缘子平稳传递给了母线桥上人员,待支持绝缘子固定好后,拆开绳索,保证了支持绝缘子安全就位。因横梁上装有多个U形挂件,一次可连续完成12只绝缘子的吊装。45只支持绝缘子不到两小时就完成了安装。此前,完成该项工作全部依靠人力,需四小时才能完成,而且很费力。使用本实用新型,可以提高工作效率近一倍,并减轻了施工人员的工作强度。  On-site test, the utility model is adopted in the construction of a 110kV substation, the busbar bridge of the substation is 8 meters long, and there are 45 supporting insulators in total. The first is to install the hoisting frame on the busbar bridge, which takes 5 minutes; during construction, the ground workers use ropes and pulleys to smoothly pass the supporting insulators to the personnel on the busbar bridge. After the supporting insulators are fixed, they are disassembled. The ropes keep the support insulators securely in place. Because there are multiple U-shaped pendants on the beam, the hoisting of 12 insulators can be completed continuously at one time. The 45 support insulators were installed in less than two hours. Previously, the completion of this work was all dependent on manpower, and it took four hours to complete, and it was very laborious. By using the utility model, the work efficiency can be nearly doubled, and the work intensity of construction personnel can be reduced. the

Claims (4)

1.一种母线桥专用多功能吊装架,其特征在于,它包括横梁和两支架,所述各支架由立柱(3)和底座(1)组成,立柱固定在底座上,所述横梁(4)两侧由螺栓分别固定在各立柱上端,横梁上设置U形挂件(5)。 1. A special multifunctional hoisting frame for busbar bridges, characterized in that it includes a beam and two brackets, each bracket is composed of a column (3) and a base (1), the column is fixed on the base, and the beam (4 ) both sides are respectively fixed on the upper ends of the columns by bolts, and U-shaped pendants (5) are arranged on the beams. 2.根据权利要求1所述的母线桥专用多功能吊装架,其特征在于,所述底座(1)为立方体形,底座中部设有底座安装孔(7),底座安装孔为矩形截面的通孔,底座上部设有底座紧固螺栓(2)。 2. The special multifunctional hoisting frame for busbar bridge according to claim 1, characterized in that, the base (1) is in the shape of a cube, and the middle part of the base is provided with a base mounting hole (7), and the base mounting hole is a through-hole with a rectangular cross-section. holes, and base fastening bolts (2) are provided on the upper part of the base. 3.根据权利要求2所述的母线桥专用多功能吊装架,其特征在于,所述各立柱(3)上部设有立柱挂件(6)。 3. The special multifunctional hoisting frame for busbar bridges according to claim 2, characterized in that, each column (3) is provided with a column hanger (6) on the upper part. 4.根据权利要求3所述的母线桥专用多功能吊装架,其特征在于,所述横梁(4)上设置的U形挂件为1-5个。 4. The special multifunctional hoisting frame for busbar bridges according to claim 3, characterized in that there are 1-5 U-shaped pendants arranged on the beam (4).
CN 201320273259 2013-05-20 2013-05-20 Special multifunctional lifting frame for busbar bridge Expired - Fee Related CN203345999U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320273259 CN203345999U (en) 2013-05-20 2013-05-20 Special multifunctional lifting frame for busbar bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320273259 CN203345999U (en) 2013-05-20 2013-05-20 Special multifunctional lifting frame for busbar bridge

Publications (1)

Publication Number Publication Date
CN203345999U true CN203345999U (en) 2013-12-18

Family

ID=49745923

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320273259 Expired - Fee Related CN203345999U (en) 2013-05-20 2013-05-20 Special multifunctional lifting frame for busbar bridge

Country Status (1)

Country Link
CN (1) CN203345999U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104779545A (en) * 2015-04-28 2015-07-15 国家电网公司 10 kV and 35 kV switch room bridge hoisting tool
CN109835625A (en) * 2017-11-28 2019-06-04 太仓中集特种物流装备有限公司 Container

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104779545A (en) * 2015-04-28 2015-07-15 国家电网公司 10 kV and 35 kV switch room bridge hoisting tool
CN109835625A (en) * 2017-11-28 2019-06-04 太仓中集特种物流装备有限公司 Container
CN109835625B (en) * 2017-11-28 2024-01-26 太仓中集特种物流装备有限公司 Container

Similar Documents

Publication Publication Date Title
CN204138210U (en) A kind of regularization tower crane service platform and escape way
CN103437283B (en) A kind of hanging basket truss of energy rapid-assembling
CN204767097U (en) High altitude construction safety belt linkage
CN203345999U (en) Special multifunctional lifting frame for busbar bridge
CN207211918U (en) Internally lifting pole
CN201918653U (en) High-voltage isolating switch maintenance protection bracket
CN203284128U (en) Hoisting tool of main mechanism of switch blade
CN102664377B (en) Double-cross arm assembler for single lever and double-cross arm mounting method
CN204689451U (en) A kind of power transformation device simple and easy hoisting erecting frame
CN204732751U (en) On-load tap-changer of transformer service kit
CN103318745A (en) Lightweight special-purposed spreader and mounting method thereof
CN107558793B (en) A method for lifting and installing multi-layer cross-arms on overhead line poles and special tools thereof
CN203022328U (en) Climbing operation platform
CN103323224B (en) A kind of anti-falling safe pick-up unit
CN107069533A (en) A kind of super UHV Overhead Transmission Line tangent tower ground wire lifting tool
CN206712336U (en) Shaft tower cable platform work protective cradle
CN203345912U (en) Portable special suspension tool
CN202961564U (en) Convenient-to-assemble type safety belt hanging frame
CN202467221U (en) Power plant main workshop steel roof truss hoisting lifting device
CN202026037U (en) Clamping device for replacing multifunctional suspended insulator string cross-arm side armour clamp
CN204992369U (en) Fixed frame that overhauls of GW4 type isolator
CN204927955U (en) A support for laying ground wires and optical cables on overhead transmission lines
CN203998699U (en) Voltage transformer attaching/detaching apparatus
CN203895804U (en) Multifunctional overhaul platform for isolating switch
CN203707659U (en) Rapid installation suspender for distribution grid cross arms

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20131218

Termination date: 20180520

CF01 Termination of patent right due to non-payment of annual fee