CN203998699U - Voltage transformer attaching/detaching apparatus - Google Patents

Voltage transformer attaching/detaching apparatus Download PDF

Info

Publication number
CN203998699U
CN203998699U CN201420389686.3U CN201420389686U CN203998699U CN 203998699 U CN203998699 U CN 203998699U CN 201420389686 U CN201420389686 U CN 201420389686U CN 203998699 U CN203998699 U CN 203998699U
Authority
CN
China
Prior art keywords
column
poles
pole
transformer
electric
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420389686.3U
Other languages
Chinese (zh)
Inventor
付克勤
周伟
万书亭
韩东
黄鸿
李群
贾洪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
North China Electric Power University
Binshan Power Supply Co of State Grid Chongqing Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
North China Electric Power University
Binshan Power Supply Co of State Grid Chongqing Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, North China Electric Power University, Binshan Power Supply Co of State Grid Chongqing Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201420389686.3U priority Critical patent/CN203998699U/en
Application granted granted Critical
Publication of CN203998699U publication Critical patent/CN203998699U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Housings And Mounting Of Transformers (AREA)

Abstract

本实用新型公开了一种变压器拆装装置,包括第一、第二支撑杆,其分别设置在对应的电杆侧,第一、第二支撑杆下部均通过固定杆与对应的电杆的下部连接;横梁设置在二电杆之间且端头分别置于第一、第二支撑杆的上端端头处;立柱设置在二根电杆的前侧,立柱上设置攀爬结构,立柱与位于左侧的电杆通过固定杆连接,立柱与位于右侧的电杆通过固定杆连接;承重梁前端布置于立柱的顶端,后端布置于横梁上,承重梁上设置滑动台,滑动台上设置手拉葫芦;手摇定滑轮布置在立柱底部,并通过钢丝与所述滑动台连接。本实用新型操作简单,方便实用,占地面积小,微调结构和支架的使用方便调整元件安装位置。

The utility model discloses a disassembly and assembly device for a transformer, which comprises first and second support rods, which are respectively arranged on the sides of the corresponding electric poles. connection; the beam is set between the two poles and the ends are respectively placed at the upper ends of the first and second support poles; the uprights are set on the front side of the two poles, and a climbing structure is set on the uprights, and the uprights are connected to the The electric pole on the left is connected by a fixed pole, and the column is connected to the electric pole on the right by a fixed pole; the front end of the load-bearing beam is arranged on the top of the column, and the rear end is arranged on the beam. Hand chain hoist; the fixed pulley is arranged at the bottom of the column and connected with the sliding table through a steel wire. The utility model is simple in operation, convenient and practical, and occupies a small area. The use of the fine-tuning structure and the bracket is convenient to adjust the installation position of the components.

Description

变压器拆装装置Transformer disassembly device

技术领域 technical field

本实用新型涉及一种变压器拆装装置。 The utility model relates to a dismounting device for a transformer.

背景技术 Background technique

目前电力局安装更换变压器时普遍采用的方法有两种:第一种是使用吊车等大型起重机械,第二种是采用搭斜台人工起落的办法。因吊车体积庞大,安装更换过程中占地面积较大,在街道、公路较窄的情况下严重阻碍交通,给出行车辆造成极大不便。此外,在山区等路况差的地区,因安装环境等限制,大型起重机械无法进入的情况下只能采用人力起落的办法,这种办法容易引起事故,造成人员伤害和财产损失,不确定因素较大。 At present, there are two methods commonly used by power bureaus to install and replace transformers: the first is to use large hoisting machinery such as cranes, and the second is to use an inclined platform for manual lifting. Due to the large size of the crane, the installation and replacement process occupies a large area, which seriously hinders traffic in the case of narrow streets and roads, causing great inconvenience to vehicles. In addition, in areas with poor road conditions such as mountainous areas, due to the limitations of the installation environment and other restrictions, the method of manpower lifting and landing can only be used when large lifting machinery cannot enter. This method is likely to cause accidents, cause personal injury and property loss, and uncertain factors larger.

公开号为CN 102951560的专利中公开了一种电力系统中吊装用起重机,但其同样存在诸多不足,例如:在吊装过程中电杆稳定性不足,易造成安全隐患,拉杆在安装过程中需要根据其他结构随时调整,安装过程繁琐。 The patent with the publication number CN 102951560 discloses a hoisting crane in the power system, but it also has many shortcomings, for example: the pole is not stable enough during the hoisting process, which may easily cause potential safety hazards. Other structures are adjusted at any time, and the installation process is cumbersome.

实用新型内容 Utility model content

本实用新型的目的就是为了解决上述问题,提供一种适合在狭窄空间内起落变压器的变压器拆装装置。 The purpose of the utility model is to solve the above-mentioned problems, and provide a transformer dismounting device suitable for lifting and lowering the transformer in a narrow space.

为了实现上述目的,本实用新型采用如下技术方案:一种变压器拆装装置,用于在两电杆间拆装变压器,包括: In order to achieve the above purpose, the utility model adopts the following technical solution: a transformer dismounting device for disassembling a transformer between two electric poles, including:

第一、第二支撑杆,其分别设置在对应的电杆侧,用于支撑电杆,所述的第一、第二支撑杆下部均通过固定杆与对应的电杆的下部连接; The first and second support rods are respectively arranged on the sides of the corresponding electric poles for supporting the electric poles, and the lower parts of the first and second support rods are connected to the lower parts of the corresponding electric poles through fixed rods;

横梁,其设置在二根电杆之间,且端头分别置于第一、第二支撑杆的上端端头处; A crossbeam, which is arranged between two electric poles, and the ends are respectively placed at the upper ends of the first and second support poles;

立柱,其设置在二根电杆的前侧,所述立柱上设置攀爬结构,所述立柱与位于左侧的电杆通过固定杆连接,所述立柱与位于右侧的电杆通过固定杆连接; An upright column, which is arranged on the front side of the two electric poles, and a climbing structure is arranged on the upright column, and the upright column is connected with the electric pole on the left side through a fixed rod, and the upright column is connected with the electric pole on the right side through a fixed rod connect;

承重梁,其前端布置于所述立柱的顶端,后端布置于所述横梁上,所述承重梁上设置滑动台,所述滑动台上设置手拉葫芦; A load-bearing beam, the front end of which is arranged on the top of the column, and the rear end is arranged on the crossbeam, a sliding platform is arranged on the bearing beam, and a chain block is arranged on the sliding platform;

手摇定滑轮,其布置在所述立柱底部,并通过钢丝与所述滑动台连接,用于控制滑动台在承重梁上前后移动。 The fixed hand pulley is arranged at the bottom of the column and is connected with the sliding table through a steel wire, and is used to control the sliding table to move forward and backward on the load-bearing beam.

进一步:所述立柱顶部左右侧均设置L型支架,所述立柱底部左右侧均设置L型支架,所述第一、第二支撑杆底部一侧均设置L型支架,所述固定杆一端设置用于与电杆连接的带式捆绑器,另一端下部等间距设置若干竖杆,两相邻的竖杆间形成可挂于支架上的钩挂结构。 Further: L-shaped brackets are set on the left and right sides of the top of the column, L-shaped brackets are set on the left and right sides of the bottom of the column, L-shaped brackets are set on the bottom side of the first and second support rods, and one end of the fixed rod is set The belt-type tie-down device used to connect with the electric pole, the lower part of the other end is provided with a plurality of vertical rods at equal intervals, and a hook structure that can be hung on the bracket is formed between two adjacent vertical rods.

进一步:所述横梁下方设置桁架结构。 Further: a truss structure is set under the beam.

进一步:所述的第一、第二支撑杆底部均设置垫板。 Further: the bottoms of the first and second support rods are provided with backing plates.

进一步:所述第一、第二支撑杆顶部均设置连接结构,所述连接结构前部具有可嵌入电杆的凹部,后部具有可供横梁搭接的平台。 Further: the tops of the first and second support rods are provided with a connection structure, the front part of the connection structure has a concave part that can be embedded in the pole, and the rear part has a platform for cross beams to overlap.

与现有技术相比,本实用新型具有如下有益效果:本实用新型设计合理,操作简单,方便实用,尤其是挂钩式微调结构和支架的使用不仅可以方便的调整元件安装位置,而且省去了螺栓连接等工作,省时省力,具有安装拆卸更加简单快捷、使用也方便、占地小的特点,解决了在有限空间内或其他条件限制无法使用大型起重机械安装变压器困难的问题,具有较好的推广应用价值。 Compared with the prior art, the utility model has the following beneficial effects: the utility model is reasonable in design, simple in operation, convenient and practical, especially the use of the hook-type fine-tuning structure and the bracket can not only adjust the installation position of the components conveniently, but also save the Bolt connection and other work save time and effort. It has the characteristics of simpler and faster installation and disassembly, convenient use, and small footprint. It solves the problem that it is difficult to install transformers with large lifting machinery in limited space or other conditions. Good promotion and application value.

附图说明 Description of drawings

图1为实施例中变压器拆装装置结构示意图。 Fig. 1 is a schematic diagram of the structure of the transformer dismounting device in the embodiment.

图2为实施例中承重梁与滑动台结构示意图。 Fig. 2 is a structural schematic diagram of the load-bearing beam and the sliding table in the embodiment.

图3为实施例中立柱结构示意图。 Fig. 3 is a schematic diagram of the column structure in the embodiment.

图4为实施例中固定杆端头的微调结构示意图。 Fig. 4 is a schematic diagram of the fine-tuning structure of the end of the fixed rod in the embodiment.

具体实施方式 Detailed ways

为了使本实用新型实现的技术手段、创作特征、达成目的与功效易于明白了解,下面结合具体图示,进一步阐述本实用新型。 In order to make the technical means, creative features, goals and effects achieved by the utility model easy to understand, the utility model will be further elaborated below in conjunction with specific illustrations.

本申请所涉及的变压器拆装装置为一种可以起落变压器的简单机械,适合在因街道狭窄、环境限制等导致大型起重机械无法进入的环境中使用。为了便于表述,实施例中的前方以图中箭头方向为参照。 The transformer dismounting device involved in this application is a simple machine that can lift and lower transformers, and is suitable for use in environments where large lifting machines cannot enter due to narrow streets and environmental restrictions. For the convenience of expression, the front in the embodiment is referred to the direction of the arrow in the figure.

参见图1到4,一种变压器拆装装置,用于在两电杆(第一、第二电杆11、12)间拆装变压器,包括第一支撑杆21、第二支撑杆22、横梁4、立柱6、承重梁5以及手摇定滑轮61。 Referring to Figures 1 to 4, a transformer disassembly and assembly device is used to disassemble and assemble a transformer between two electric poles (first and second electric poles 11, 12), including a first support pole 21, a second support pole 22, a beam 4, column 6, load-bearing beam 5 and hand fixed pulley 61.

第一、第二支撑杆21、22分别设置在对应的电杆侧(即分别与第一电杆11、第二电杆12对应),用于支撑电杆,所述的第一、第二支撑杆21、22下部均通过固定杆3(方钢)与对应的电杆的下部连接。 The first and second support poles 21 and 22 are respectively arranged on the corresponding electric pole sides (that is, corresponding to the first electric pole 11 and the second electric pole 12 respectively) for supporting the electric poles. The first and second The lower parts of the support rods 21 and 22 are connected to the lower parts of the corresponding electric poles through the fixed rod 3 (square steel).

横梁4设置在二根电杆之间,且端头分别置于第一、第二支撑杆的上端端头处。具体而言,所述第一、第二支撑杆21、22顶部均设置连接结构,所述连接结构前部具有可嵌入电杆的凹部,后部具有可供横梁搭接的平台。 The crossbeam 4 is arranged between two electric poles, and the ends are respectively placed at the upper ends of the first and second support poles. Specifically, the tops of the first and second support rods 21 and 22 are provided with connection structures, the front part of the connection structure has a concave part that can be embedded in the electric pole, and the rear part has a platform for cross beams to overlap.

第一、第二支撑杆21、22上端固定有横梁4,这样能够使横梁在工作中承受的力转移到支撑杆上,提高了结构的工作强度范围。另外,支撑结构还能避免横梁直接固定在电线杆上带来的不稳定性,而且安装过程也更加省力快捷。 The upper ends of the first and second support rods 21, 22 are fixed with crossbeams 4, so that the force borne by the crossbeams during work can be transferred to the support rods, thereby improving the working strength range of the structure. In addition, the support structure can also avoid the instability caused by the direct fixing of the beam on the utility pole, and the installation process is more labor-saving and quicker.

立柱6设置在二根电杆的前侧,所述立柱6上设置攀爬结构,所述立柱6与位于左侧的电杆(第二电杆12)通过固定杆连接,所述立柱6与位于右侧的电杆(第一电杆11)通过固定杆连接。 The upright 6 is arranged on the front side of the two electric poles, and a climbing structure is arranged on the upright 6, and the upright 6 is connected with the electric pole (the second electric pole 12) on the left side through a fixed rod, and the upright 6 is connected with the The electric pole on the right side (the first electric pole 11) is connected by a fixed pole.

承重梁5前端布置于所述立柱6的顶端,后端布置于所述横梁4上,所述承重梁5上设置滑动台51,所述滑动台51上设置手拉葫芦。 The front end of the load-bearing beam 5 is arranged on the top of the column 6 , and the rear end is arranged on the crossbeam 4 , a sliding platform 51 is arranged on the bearing beam 5 , and a chain block is arranged on the sliding platform 51 .

手摇定滑轮61布置在所述立柱6底部,并通过钢丝与所述滑动台51连接,用于控制滑动台在承重梁上前后移动。 The fixed hand pulley 61 is arranged at the bottom of the column 6, and is connected with the sliding table 51 through a steel wire, and is used to control the sliding table to move forward and backward on the load-bearing beam.

立柱6顶部左右侧均设置L型支架62,立柱6底部左右侧均设置L型支架62,第一、第二支撑杆21、22底部一侧均设置L型支架62,固定杆一端设置用于与电杆连接的带式捆绑器,另一端下部等间距设置若干竖杆31,两相邻的竖杆31间形成可挂于支架62上的钩挂结构。挂钩式微调结构能够快速调节立柱及第一、第二支撑杆与电杆之间的安装位置。 The left and right sides of the top of the column 6 are all provided with an L-shaped support 62, the left and right sides of the bottom of the column 6 are all provided with an L-shaped support 62, and one side of the bottom of the first and second support rods 21 and 22 is provided with an L-shaped support 62, and one end of the fixed rod is provided for The belt type binding device that is connected with electric pole, the lower part of the other end is equidistantly provided with several vertical rods 31, forms the hook structure that can be hung on the support 62 between two adjacent vertical rods 31. The hook-type fine-tuning structure can quickly adjust the installation position between the column, the first and second support rods and the electric pole.

横梁4下方设置桁架结构,用来提高横梁的抗弯强度。第一、第二支撑杆底部均设置垫板。 A truss structure is arranged under the beam 4 to improve the bending strength of the beam. Backing plates are provided at the bottom of the first and second support rods.

实施例中,固定杆为方钢,用于防止立柱和第一、第二支撑杆左右晃动从而保持其稳定性。立柱和第一、第二支撑杆为圆管钢材,立柱沿纵向均匀分布两排爬梯(攀爬结构),方便工作人员上下攀爬。立柱的下端设有手摇定滑轮,它通过钢丝绳来移动承重梁上的滑动台。承重梁搭在立柱和横梁上,横梁为一根槽钢,承重梁为方钢,一端与立柱通过螺栓固定连接,另一端搭在横梁的定位槽上。滑动台可以在承重梁上来回移动最终将变压器放到合适的位置,承重梁两端带有滑轮用来减少钢丝绳的摩擦。 In the embodiment, the fixing rod is a square steel, which is used to prevent the upright column and the first and second support rods from shaking left and right so as to maintain their stability. The column and the first and second support rods are made of round pipe steel, and the column is evenly distributed along the longitudinal direction with two rows of ladders (climbing structure), which is convenient for the staff to climb up and down. The lower end of the column is provided with a fixed hand pulley, which moves the sliding table on the load-bearing beam through a wire rope. The load-bearing beam is built on the column and the beam, the beam is a channel steel, the load-bearing beam is a square steel, one end is fixedly connected with the column by bolts, and the other end is placed on the positioning groove of the beam. The sliding table can move back and forth on the load-bearing beam to finally put the transformer in a suitable position. There are pulleys at both ends of the load-bearing beam to reduce the friction of the wire rope.

本实用新型设计合理,操作简单,方便实用,尤其是挂钩式微调结构和支架的使用不仅可以方便的调整元件安装位置,而且省去了螺栓连接等工作,省时省力,具有安装拆卸更加简单快捷、使用也方便、占地小的特点,解决了在有限空间内或其他条件限制无法使用大型起重机械安装变压器困难的问题,具有较好的推广应用价值。 The utility model is reasonable in design, simple in operation, convenient and practical, especially the use of the hook-type fine-tuning structure and the bracket can not only adjust the installation position of the components conveniently, but also save work such as bolt connection, save time and effort, and have simpler and faster installation and disassembly. , Easy to use, small footprint, solves the problem that it is difficult to use large lifting machinery to install transformers in limited space or other conditions, and has good promotion and application value.

变压器拆装装置工作过程如下:手拉葫芦吊在滑动台下即可安装更换变压器,安装时先用手拉葫芦将变压器从支座7升至合适的位置,转动脚梯下端焊接的手摇定滑轮,通过钢丝绳移动滑动台将变压器移动到立柱和支座之间,调节手拉葫芦将变压器降下即可完成安装过程,更换变压器重复上述操作即可。 The working process of the transformer dismounting device is as follows: the transformer can be installed and replaced by hanging the chain hoist under the sliding table. The pulley moves the sliding table through the wire rope to move the transformer between the column and the support, adjust the chain hoist to lower the transformer to complete the installation process, and replace the transformer and repeat the above operations.

以上所述仅为本实用新型的优选实施方式,本实用新型的保护范围并不仅限于上述实施方式,凡是属于本实用新型原理的技术方案均属于本实用新型的保护范围。对于本领域的技术人员而言,在不脱离本实用新型的原理的前提下进行的若干改进,这些改进也应视为本实用新型的保护范围。 The above descriptions are only preferred implementations of the present utility model, and the scope of protection of the present utility model is not limited to the above-mentioned implementations. All technical solutions belonging to the principle of the utility model belong to the protection scope of the utility model. For those skilled in the art, some improvements made on the premise of not departing from the principle of the utility model, these improvements should also be regarded as the protection scope of the utility model.

Claims (5)

1.一种变压器拆装装置,用于在两电杆间拆装变压器,其特征在于,包括: 1. A transformer dismounting device, used for disassembling a transformer between two electric poles, is characterized in that, comprising: 第一、第二支撑杆,其分别设置在对应的电杆侧,用于支撑电杆,所述的第一、第二支撑杆下部均通过固定杆与对应的电杆的下部连接; The first and second support rods are respectively arranged on the sides of the corresponding electric poles for supporting the electric poles, and the lower parts of the first and second support rods are connected to the lower parts of the corresponding electric poles through fixed rods; 横梁,其设置在二根电杆之间,且端头分别置于第一、第二支撑杆的上端端头处; A crossbeam, which is arranged between two electric poles, and the ends are respectively placed at the upper ends of the first and second support poles; 立柱,其设置在二根电杆的前侧,所述立柱上设置攀爬结构,所述立柱与位于左侧的电杆通过固定杆连接,所述立柱与位于右侧的电杆通过固定杆连接; An upright column, which is arranged on the front side of the two electric poles, and a climbing structure is arranged on the upright column, and the upright column is connected with the electric pole on the left side through a fixed rod, and the upright column is connected with the electric pole on the right side through a fixed rod connect; 承重梁,其前端布置于所述立柱的顶端,后端布置于所述横梁上,所述承重梁上设置滑动台,所述滑动台上设置手拉葫芦; A load-bearing beam, the front end of which is arranged on the top of the column, and the rear end is arranged on the crossbeam, a sliding platform is arranged on the bearing beam, and a chain block is arranged on the sliding platform; 手摇定滑轮,其布置在所述立柱底部,并通过钢丝与所述滑动台连接,用于控制滑动台在承重梁上前后移动。 The fixed hand pulley is arranged at the bottom of the column and is connected with the sliding table through a steel wire, and is used to control the sliding table to move forward and backward on the load-bearing beam. 2.根据权利要求1所述的变压器拆装装置,其特征在于:所述立柱顶部左右侧均设置L型支架,所述立柱底部左右侧均设置L型支架,所述第一、第二支撑杆底部一侧均设置L型支架,所述固定杆一端设置用于与电杆连接的带式捆绑器,另一端下部等间距设置若干竖杆,两相邻的竖杆间形成可挂于支架上的钩挂结构。 2. The transformer dismounting device according to claim 1, characterized in that: L-shaped brackets are arranged on the left and right sides of the top of the column, L-shaped brackets are installed on the left and right sides of the bottom of the column, and the first and second supports L-shaped brackets are arranged on one side of the bottom of the pole, and one end of the fixed pole is provided with a belt tie for connecting with the electric pole, and a number of vertical poles are arranged at equal intervals at the lower part of the other end, and a bracket can be hung between two adjacent vertical poles. on the hook structure. 3.根据权利要求1所述的变压器拆装装置,其特征在于:所述横梁下方设置桁架结构。 3. The transformer dismounting device according to claim 1, characterized in that: a truss structure is arranged under the beam. 4.根据权利要求1所述的变压器拆装装置,其特征在于:所述的第一、第二支撑杆底部均设置垫板。 4. The transformer dismounting device according to claim 1, characterized in that: the bottoms of the first and second support rods are provided with backing plates. 5.根据权利要求1所述的变压器拆装装置,其特征在于:所述第一、第二支撑杆顶部均设置连接结构,所述连接结构前部具有可嵌入电杆的凹部,后部具有可供横梁搭接的平台。 5. The transformer dismounting device according to claim 1, characterized in that: the tops of the first and second support rods are provided with connection structures, the front part of the connection structure has a concave part that can be embedded in the pole, and the rear part has a A platform for beam lapping.
CN201420389686.3U 2014-07-15 2014-07-15 Voltage transformer attaching/detaching apparatus Expired - Fee Related CN203998699U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420389686.3U CN203998699U (en) 2014-07-15 2014-07-15 Voltage transformer attaching/detaching apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420389686.3U CN203998699U (en) 2014-07-15 2014-07-15 Voltage transformer attaching/detaching apparatus

Publications (1)

Publication Number Publication Date
CN203998699U true CN203998699U (en) 2014-12-10

Family

ID=52038730

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420389686.3U Expired - Fee Related CN203998699U (en) 2014-07-15 2014-07-15 Voltage transformer attaching/detaching apparatus

Country Status (1)

Country Link
CN (1) CN203998699U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105023711A (en) * 2015-07-21 2015-11-04 江苏宝亨新电气有限公司 Transformer fastening device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105023711A (en) * 2015-07-21 2015-11-04 江苏宝亨新电气有限公司 Transformer fastening device

Similar Documents

Publication Publication Date Title
CN202186848U (en) Universal movable maintenance gantry crane
CN202785364U (en) Movable dual-door-type mast hoisting device
CN207748760U (en) A kind of bridge crane of hoisting large-size drainpipe
CN105621280A (en) Device and method for mounting and dismounting crane boom
CN204661163U (en) A kind of Multifunction transformer sleeve pipe lifting support
CN203128099U (en) Slipping type pipeline lifting device
CN202017337U (en) Efficient elevator mechanism adhered to electric lifting scaffold
CN207108405U (en) Portable light-duty jacking apparatus
CN203998699U (en) Voltage transformer attaching/detaching apparatus
CN204549923U (en) The mobile mast-up of a kind of chemical equipment overhaul
CN216807824U (en) Pipeline mobile device for hydraulic engineering
CN204324743U (en) A kind of transfer crane being applicable to the long shape article of handling
CN103896153A (en) Zig-zag derrick for replacing disconnecting link
CN204198306U (en) A kind of device for purlin lifting in building operation
CN209260563U (en) A kind of Bailey beam truss entirety transverse sliding device for cast-in-situ continuous beam
CN203755153U (en) Simply supported plate bridge bottom plate maintenance construction moving operation platform
CN203402829U (en) Frame of lifting machine for portable transformer
CN203333224U (en) Steel structural beam upward lifting tool
CN201857225U (en) Hoisting device for bridge crane frame
CN206841277U (en) Lifting and delivery head base device for electric pole conveying
CN105672910A (en) Oil tube traction lifting auxiliary machine
CN203269425U (en) Movable lifting equipment
CN203794469U (en) Inversed-v-shaped holding pole for replacing disconnecting link
CN219929468U (en) Hoisting tool used in narrow space
CN203707659U (en) Rapid installation suspender for distribution grid cross arms

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141210

Termination date: 20210715

CF01 Termination of patent right due to non-payment of annual fee