CN203583514U - Pre-buried structure of ultra-deep foundation bolt - Google Patents

Pre-buried structure of ultra-deep foundation bolt Download PDF

Info

Publication number
CN203583514U
CN203583514U CN201320707020.3U CN201320707020U CN203583514U CN 203583514 U CN203583514 U CN 203583514U CN 201320707020 U CN201320707020 U CN 201320707020U CN 203583514 U CN203583514 U CN 203583514U
Authority
CN
China
Prior art keywords
sleeve
foundation bolt
buried structure
steel plate
stone bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320707020.3U
Other languages
Chinese (zh)
Inventor
李永华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN201320707020.3U priority Critical patent/CN203583514U/en
Application granted granted Critical
Publication of CN203583514U publication Critical patent/CN203583514U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a pre-buried structure of an ultra-deep foundation bolt. The pre-buried structure comprises a sleeve with an upward opening, wherein the sleeve is composed of five steel plates; anchor plates are respectively arranged on the outer side faces of the sleeve; the foundation bolt is vertically arranged in the center of the sleeve; the sleeve is filled with a shrinkage-free grouting material; a reinforcing steel plate is arranged at the top of the sleeve; the foundation bolt penetrates through the reinforcing steel plate. As the technical scheme is adopted, the pre-buried structure is simple in structure and convenient to construct; the anchor plates are respectively welded on the four outer side faces of the sleeve consisting of the five steel plates, so that the anchoring effect of the sleeve in concrete foundation can be greatly increased, and the defect that the junction surfaces of the steel plates and concrete are small in coefficient of friction resistance. Moreover, the pre-buried structure is constructed together with equipment foundation, and does not need to be taken out, so that the pre-buried quality of the ultra-deep foundation bolt can be ensured, the operating requirement of the foundation bolt is reliably ensured, and the manpower and time cost that templates need to be taken out in the prior art are reduced.

Description

A kind of pre-buried structure of super dark stone bolt
Technical field
The utility model relates to a kind of pre-buried structure, is specifically related to a kind of pre-buried structure of super dark stone bolt.
Background technology
In industrial construction, according to all needing to configure various production equipments in a lot of workshops of technique instructions for use, these equipment are fixed by stone bolt and equipment Foundations.According to the operating condition of distinct device, stone bolt will bear pressure, uplift force, and the horizontal direction component producing in the time of sometimes also will bearing equipment operation, so the quality of the reserved quality of stone bolt directly affects top equipment operation.The pre-buried structure of equipment anchor bolt routine has two kinds: the one, and employing plank is template, forms a square box, before equipment Foundations concrete construction, imbeds, and during concrete final set, is extracted again.Its shortcoming is that the preformed hole degree of depth is difficult to ensure card, and wooden model surrounding concrete density is bad, and particularly in super dark preformed hole, wooden model is difficult to extract completely, affects bolt and installs.The 2nd, employing steel pipe is template, when the final set of equipment Foundations concrete, is extracted.Its shortcoming is after punching block is extracted, and concrete hole wall is very smooth, and the hole wall coefficient of friction resistance diminishes, and affects the anchorage effect of stone bolt.
Summary of the invention
The technical problem that the utility model solves is: a kind of simple in structure, easy construction is provided, can not only strengthens and the coefficient of friction resistance of concrete joint surface, and do not need the pre-buried structure of the super dark stone bolt that takes out template, to overcome the deficiencies in the prior art.
The utility model is to form like this: it comprises the sleeve 1 that consists of upward opening shape five block plates, at the lateral surface of sleeve 1, be respectively equipped with anchor slab 2, center at sleeve 1 is vertically provided with stone bolt 3, in sleeve 1, be filled with contraction-free grouting concrete 4, at sleeve 1 top, be provided with reinforcement steel plate 5, stone bolt 3 is through reinforcement steel plate 5.
In the pre-buried structure of above-mentioned super dark stone bolt, described stone bolt 3 is welded to connect with the contact position of reinforcement steel plate 5, and reinforcement steel plate 5 is welded to connect with sleeve 1 contact position.
Owing to having adopted technique scheme, compared with prior art, the utility model is simple in structure, easy construction, by welding anchor slab on four sides in the sleeve outside of five block plate compositions respectively, can significantly increase the anchoring effect of sleeve in concrete foundation, make up the shortcoming that steel plate and the concrete joint surface coefficient of friction resistance are little.In addition, the utility model is to construct together with equipment Foundations, does not need to take out, and can guarantee the pre-buried quality of super dark stone bolt, Reliable guarantee the instructions for use of stone bolt, saved the manpower and the time cost that in prior art, need to take out template simultaneously.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Being labeled as of accompanying drawing: 1-sleeve, 2-anchor slab, 3-stone bolt, 4-contraction-free grouting concrete, 5-reinforcement steel plate, 6-equipment Foundations.
The specific embodiment:
Embodiment of the present utility model: as shown in Figure 1, with five block plate welding, form the sleeve 1 of upward opening shape, at the lateral surface of sleeve 1 anchor slab 2 that is welded respectively, by Steel bar rack, sleeve 1 is fixed in equipment Foundations 6, stone bolt 3 is vertically installed at center at sleeve 1, in sleeve 1, pour into contraction-free grouting concrete 4, at reinforcement steel plate 5 of sleeve 1 welded top, and stone bolt 3 is passed to reinforcement steel plate 5.For further foot bolt 3 firmly, improve installation quality, stone bolt 3 and the contact position of reinforcement steel plate 5 can be welded to connect, and reinforcement steel plate 5 and sleeve 1 contact position are welded to connect.
Embodiment of the present utility model is not limited to above-described embodiment, and the various variations of making under the prerequisite that does not depart from utility model aim all belong to the protection domain of utility model.

Claims (2)

1. the pre-buried structure of a super dark stone bolt, it is characterized in that: it comprises the sleeve (1) that consists of upward opening shape five block plates, at the lateral surface of sleeve (1), be respectively equipped with anchor slab (2), at the center of sleeve (1), be vertically provided with stone bolt (3), in sleeve (1), be filled with contraction-free grouting concrete (4), at sleeve (1) top, be provided with reinforcement steel plate (5), stone bolt (3) is through reinforcement steel plate (5).
2. the pre-buried structure of super dark stone bolt according to claim 1, is characterized in that: described stone bolt (3) is welded to connect with the contact position of reinforcement steel plate (5), and reinforcement steel plate (5) is welded to connect with sleeve (1) contact position.
CN201320707020.3U 2013-11-11 2013-11-11 Pre-buried structure of ultra-deep foundation bolt Expired - Lifetime CN203583514U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320707020.3U CN203583514U (en) 2013-11-11 2013-11-11 Pre-buried structure of ultra-deep foundation bolt

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320707020.3U CN203583514U (en) 2013-11-11 2013-11-11 Pre-buried structure of ultra-deep foundation bolt

Publications (1)

Publication Number Publication Date
CN203583514U true CN203583514U (en) 2014-05-07

Family

ID=50581457

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320707020.3U Expired - Lifetime CN203583514U (en) 2013-11-11 2013-11-11 Pre-buried structure of ultra-deep foundation bolt

Country Status (1)

Country Link
CN (1) CN203583514U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105672345A (en) * 2016-02-02 2016-06-15 中国船舶重工集团公司第七一二研究所青岛研究所 Installation method and device for embedded bolt holes of large generator cast iron platform foundation
CN107780666A (en) * 2017-12-04 2018-03-09 三洋电梯(珠海)有限公司 A kind of rapid construction device and method of exterior wall elevator hoistways built-in fitting
CN110359480A (en) * 2019-07-17 2019-10-22 湖南长高高压开关集团股份公司 A kind of disconnecting switch embedded foundation bracket

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105672345A (en) * 2016-02-02 2016-06-15 中国船舶重工集团公司第七一二研究所青岛研究所 Installation method and device for embedded bolt holes of large generator cast iron platform foundation
CN107780666A (en) * 2017-12-04 2018-03-09 三洋电梯(珠海)有限公司 A kind of rapid construction device and method of exterior wall elevator hoistways built-in fitting
CN110359480A (en) * 2019-07-17 2019-10-22 湖南长高高压开关集团股份公司 A kind of disconnecting switch embedded foundation bracket

Similar Documents

Publication Publication Date Title
CN203247600U (en) Equipment foundation bolt preformed hole die
CN203583514U (en) Pre-buried structure of ultra-deep foundation bolt
CN203701387U (en) Floor slab structure with embedded heat preservation cavities
CN204898672U (en) Discard device of pulling out of pile foundation
CN103452328B (en) Post brutal bracing means and method is subtracted for reinforced concrete member
CN201581394U (en) Large pile toe grout-injection precast pile
CN109024973B (en) Connecting structure for prefabricated shear wall and construction method thereof
CN204919829U (en) Steel plate concrete shear force wall and basic connection structure and basic built -in fitting structure
CN204826639U (en) Rag bolt preformed hole mould
CN203998719U (en) A kind of high-building construction tower crane adheres to uses shaped steel anchor structure
CN104265005B (en) The back ruggedized construction that a kind of steel plate combines with reinforcing bar
CN204023791U (en) Embedding anchor bolts device
CN103243913B (en) The method for blocking of fabricated shear wall architectural lower floor junction grout blanket
CN202055259U (en) Foundation bolt preformed hole structure for equipment
CN204626732U (en) A kind of precast reinforced concrete construction superposed beam antipriming
CN203755682U (en) Secondary pouring form board constructing structure for small opening of concrete structure floor slab
CN207794321U (en) Monoblock type fills walling steel tie bar embedded part
CN204491953U (en) Floor slab structure between architecture pipe
CN203856192U (en) Bottom plate haunching template structure
CN203960813U (en) Anchorage part for earth work membrane
CN204311446U (en) A kind of fully prestressed concrete solid square pile end plate
CN203430027U (en) Adjustable large steel formwork
CN205857792U (en) Shear wall concrete replacement bottom provisions for grouting
CN206752790U (en) A kind of part combination beam with tie-rod
CN204940821U (en) One can be had enough to meet the need and utilize Finalized rebar operating desk

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20140507

CX01 Expiry of patent term