CN207794321U
CN207794321U CN201721917909.9U CN201721917909U CN207794321U CN 207794321 U CN207794321 U CN 207794321U CN 201721917909 U CN201721917909 U CN 201721917909U CN 207794321 U CN207794321 U CN 207794321U
Authority
CN
China
Prior art keywords
iron plate
bar
reinforcing bar
buried iron
walling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721917909.9U
Other languages
Chinese (zh)
Inventor
于国帅
巩建伟
孙杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG WANXIN CONSTRUCTION CO Ltd
Original Assignee
SHANDONG WANXIN CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG WANXIN CONSTRUCTION CO Ltd filed Critical SHANDONG WANXIN CONSTRUCTION CO Ltd
Priority to CN201721917909.9U priority Critical patent/CN207794321U/en
Application granted granted Critical
Publication of CN207794321U publication Critical patent/CN207794321U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model is mainly used in technical field of buildings, more particularly to a kind of monoblock type fills walling steel tie bar embedded part, including longitudinally arranged connection reinforcing bar and pre-buried iron plate, every two connections reinforcing bar is one group, genesis analysis has pre-buried iron plate on the same side of one group of connection reinforcing bar, anchor bar is respectively set in the corner location of pre-buried iron plate, and anchor bar is located at the same side of pre-buried iron plate with reinforcing bar is connect.The mold is directly anchored to before template installation on main body reinforcing bar, after the completion of concreting entirety is formed with agent structure, tension rib is directly subsequently welded on embedded iron on piece, avoids the later stage from being punched on concrete structure, tendon-planted craft flow, shortens steel tie bar for masonry installation period.

Description

Monoblock type fills walling steel tie bar embedded part
Technical field
The utility model is related to a kind of monoblock types to fill walling steel tie bar embedded part, be mainly used in Building technology neck Domain.
Background technology
In construction, for the globality for ensureing concrete structure with filling walling, generally use tension rib will mix Xtah Crude Clay structure becomes an entirety with masonry structure drawknot, and common practices is by the way of pre-buried bar planting, by concrete and masonry Structure carries out drawknot, carries out chemically-planted steel bar after the completion of concrete structure construction, chemically-planted steel bar is on concrete column or shear wall Drilling is then injected into high-strength anchoring adhesive, then reinforcing bar rotation is filled in hole, and after anchoring adhesive consolidation, reinforcing bar connects with concrete structure It is integrated, but there are some drawbacks in this method actual mechanical process:
1) easily stopped by reinforcing bar in shear wall in boring procedure, depth of pore forming deficiency or position is caused deviation occur.
2) take artificial drilling, drilling depth that cannot be effectively ensured.
3) anchoring adhesive quality has differences, and bearing capacity is anchored after the completion of bar planting and is difficult to be guaranteed.
4) after the completion of bar planting, it is necessary to adopt an effective measure and ensure that reinforcing bar is not disturbed, once sending out before anchoring adhesive does not consolidate Raw disturbance, can destroy bar planting effect.
The above drawback makes bar planting construction be easy to that mass defect occurs, and may be that engineering structure is stayed safely if dealing with improperly Lower hidden danger.
Utility model content
The technical problems to be solved in the utility model is:Offer one kind is simple in structure, easy for construction, operation is fast, Neng Goubao Card bar planting positions and dimensions are accurate, ensure to anchor the monoblock type filling walling steel tie bar embedded part that bearing capacity reaches requirement.
Monoblock type described in the utility model fills walling steel tie bar embedded part, including longitudinally arranged connection reinforcing bar with Pre-buried iron plate, every two connections reinforcing bar is one group, and genesis analysis has pre-buried iron plate, embedded iron on the same side of one group of connection reinforcing bar Anchor bar is respectively set in the corner location of piece, and anchor bar is located at the same side of pre-buried iron plate with reinforcing bar is connect.
Described the distance between the two adjacent pre-buried iron plates up and down are 500 millimeters.
The pre-buried iron plate is set as rectangle, and four anchor bars, four anchor bars are arranged in every piece of embedded iron on piece It is respectively welded on four angle points for being fixed on pre-buried iron plate.
The utility model has the beneficial effects that:
1) anchor bar is directly anchored on main body reinforcing bar by the mold before template installation, after the completion of concreting with Agent structure forms entirety, and tension rib is directly subsequently welded on embedded iron on piece, the later stage is avoided to be punched on concrete structure, Tendon-planted craft flow shortens steel tie bar for masonry installation period.
2) since tension rib is using being welded on anchor plate, compared with traditional tendon-planted craft, tension rib is effectively increased Anchoring bearing capacity.
3) due to not using traditional bar planting, avoid that the hole depth that is easy tod produce when bar planting is insufficient, position is improper, anchoring carrying The defects of power is insufficient and easily disturbs, effectively enhances the drawknot globality of secondary masonry structure and agent structure.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the left view structural representation of Fig. 1.
In figure:1, pre-buried iron plate;2, anchor bar;3, reinforcing bar is connected.
Specific implementation mode
The utility model is described further below in conjunction with the accompanying drawings:
As shown in Fig. 1~Fig. 2, monoblock type described in the utility model fills walling steel tie bar embedded part, including longitudinal direction The connection reinforcing bar 3 and pre-buried iron plate 1 of arrangement, every two connections reinforcing bar 3 is one group, longitudinal on the same side of one group of connection reinforcing bar 3 Pre-buried iron plate 1 is distributed with, anchor bar 2 is respectively set in the corner location of pre-buried iron plate 1, and anchor bar 2 is located at reinforcing bar 3 is connect The same side of pre-buried iron plate 1.The distance between upper and lower two adjacent pre-buried iron plates 1 are 500 millimeters.Pre-buried iron plate 1 is set as square Shape, four anchor bars 2 are arranged on every piece of pre-buried iron plate 1, and four anchor bars 2 are separately fixed at four angles of pre-buried iron plate 1 Point on.
Connection reinforcing bar 3 is elongated longitudinal reinforcement, connects reinforcing bar 3 and every piece of 1 firm welding of pre-buried iron plate, pre-buried iron plate 1 Center spacing is generally the height of two skins filling wall building block, is preset as 500mm, and weld in four angle points of every piece of pre-buried iron plate 1 It connects anchor bar 2, when construction, outwardly by 1 smooth surface of integral built-in iron plate, will be welded on every piece of pre-buried iron plate 1 after determining good position Four 2 banding fixeds of anchor bar on shear force wall reinforcing steel bar, ensure the smooth surface of pre-buried iron plate 1 with it is flat on the inside of shear wall formwork Together, pre-buried iron plate 1 is exposed at concrete outer surface after having poured concrete.
In use, the laitance on 1 surface of pre-buried iron plate is cleaned out, then tension rib is welded on pre-buried iron plate 1.

Claims (3)

1. a kind of monoblock type fills walling steel tie bar embedded part, it is characterised in that:Including longitudinally arranged connection reinforcing bar (3) and Pre-buried iron plate (1), every two connection reinforcing bar (3) is one group, and genesis analysis has embedded iron on the same side of one group of connection reinforcing bar (3) Anchor bar (2) is respectively set in the corner location of piece (1), pre-buried iron plate (1), and anchor bar (2) is located in advance with reinforcing bar (3) is connect Bury the same side of iron plate (1).
2. monoblock type according to claim 1 fills walling steel tie bar embedded part, it is characterised in that:Upper and lower two is adjacent The distance between pre-buried iron plate (1) is 500 millimeters.
3. monoblock type according to claim 1 fills walling steel tie bar embedded part, it is characterised in that:Pre-buried iron plate (1) It is set as rectangle, four anchor bars (2) are set on every piece of pre-buried iron plate (1), four anchor bars (2) are respectively welded and are fixed on On four angle points of pre-buried iron plate (1).
CN201721917909.9U 2017-12-27 2017-12-27 Monoblock type fills walling steel tie bar embedded part Expired - Fee Related CN207794321U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721917909.9U CN207794321U (en) 2017-12-27 2017-12-27 Monoblock type fills walling steel tie bar embedded part

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721917909.9U CN207794321U (en) 2017-12-27 2017-12-27 Monoblock type fills walling steel tie bar embedded part

Publications (1)

Publication Number Publication Date
CN207794321U true CN207794321U (en) 2018-08-31

Family

ID=63277111

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721917909.9U Expired - Fee Related CN207794321U (en) 2017-12-27 2017-12-27 Monoblock type fills walling steel tie bar embedded part

Country Status (1)

Country Link
CN (1) CN207794321U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111119396A (en) * 2020-01-08 2020-05-08 浙江丰众建筑材料科技股份有限公司 Autoclaved aerated concrete brick with preset tie bar grooves and processing method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111119396A (en) * 2020-01-08 2020-05-08 浙江丰众建筑材料科技股份有限公司 Autoclaved aerated concrete brick with preset tie bar grooves and processing method thereof

Similar Documents

Publication Publication Date Title
CN104895092B (en) The method that a kind of interim lattice column of inner support is used as permanent structure post
CN103410332B (en) A kind of concrete hollow block reinforcement wall construction technology
CN106168054B (en) Connecting structure and its construction method with dry shaped connecting piece precast shear wall plate
CN108086343B (en) Cantilever type single-side wall body mixed reinforcement and replacement structure and construction method thereof
CN209145035U (en) The node structure blocked when for being in the milk at assembled architecture shear wall installation seam
CN206189647U (en) Novel infilled wall brickwork drawknot muscle structure
CN107083804B (en) A kind of wall structure column joint bar construction method
CN103498425A (en) Full-dismounting combination type multifunctional bracket supporting structure and construction method thereof
CN107503450A (en) A kind of cast-in-place hollow armored concrete filling wall and its construction technology
CN104295003A (en) Structural column construction method
CN109322319A (en) The bindiny mechanism of concrete precast pile and pile foundation support table
CN103061357B (en) Connection joint between basement base plate and underground diaphragm wall
CN206408515U (en) Precast pier section assembling structure
CN107355008B (en) Prefabricated connection structure and method for newly added concrete filled steel tubular column and existing structure
CN206616827U (en) One kind box filled piece of built-in line of building
CN202731936U (en) Tunnel inverted arch end mold
CN114809029A (en) High cutting slope anchor rod frame beam coupling construction method
CN207794321U (en) Monoblock type fills walling steel tie bar embedded part
CN106337530B (en) A kind of construction of frame beam seams stifled construction method
CN202247938U (en) Wedge-shaped foundation bolt preformed hole core formwork device
CN105003088B (en) The construction method of embedded part is leaked in a kind of Construction of Steel Structure
CN104675138B (en) A kind of slab balcony reinforcement means for sound insulation and noise reducing transformation
CN207092299U (en) A kind of cast-in-place hollow armored concrete filling wall
CN110318463A (en) A kind of connection structure and construction method of prefabricated post and beam based on phosphorus magnesium material
CN206233405U (en) The attachment structure of shear wall and after-pouring concrete frame beam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180831