CN206616827U - One kind box filled piece of built-in line of building - Google Patents
One kind box filled piece of built-in line of building Download PDFInfo
- Publication number
- CN206616827U CN206616827U CN201720314353.8U CN201720314353U CN206616827U CN 206616827 U CN206616827 U CN 206616827U CN 201720314353 U CN201720314353 U CN 201720314353U CN 206616827 U CN206616827 U CN 206616827U
- Authority
- CN
- China
- Prior art keywords
- line
- built
- box
- sealing strip
- building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000007789 sealing Methods 0.000 claims abstract description 13
- 239000013536 elastomeric material Substances 0.000 claims abstract description 3
- 239000000463 material Substances 0.000 claims abstract description 3
- 238000003780 insertion Methods 0.000 claims description 3
- 230000037431 insertion Effects 0.000 claims description 3
- 239000002002 slurry Substances 0.000 claims description 2
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 abstract description 8
- 229910052742 iron Inorganic materials 0.000 abstract description 4
- 239000002023 wood Substances 0.000 abstract description 3
- 238000006073 displacement reaction Methods 0.000 abstract description 2
- 238000010586 diagram Methods 0.000 description 3
- 230000003014 reinforcing effect Effects 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 239000002390 adhesive tape Substances 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000005034 decoration Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000000945 filler Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model is a kind of box filled piece of built-in line of building, it by:Filling block anchors into section(1), screw hole(2), sealing strip(3), groove(4), groove sealing strip(5)Constitute, its material is elastomeric material.It can not only replace wood chip to fill line box, and can precisely fix line box, prevent displacement, iron nail is left in structure roof while avoiding.
Description
Technical field
The utility model is related to a kind of box filled piece of built-in line of building, it is adaptable to pre-buried line box is filled out in concrete structure
Fill and fixation is installed.
Background technology
In building electric engineering, as building structure main body construction needs to carry out burying work beforehand to electric wire box.At present, lead to
Before normal way is concreting, filling timber crumb adhesive tape snarls sealing in line box.The pre-buried peace of concrete shear force wall, post line box
Dress is after conduit and line box are connected, respectively to wear a bar dowel of φ 6 by line box upper and lower side, and be welded in cage bar.Then
Line box box mouth and the distance of metope are adjusted, finally fixed position is tied with steel wire.In concrete floor line box it is pre-buried installation be
Template sets up, after the completion of, after conduit is connected with line box, specify fixed position, iron hammered into the preformed hole on the side of line box four
Nail is connected with plank sheathing.In concreting process of vibrating, reinforcing bar unstability can cause line box to be moved in shear wall, post
Position, it is embedding too deep.In floor after pre-buried line box form removable, top plate can expose iron nail, influence structure roof decorations and sight
Feel quality, while placing filler wood chip in line box, later stage cleaning is cumbersome.
The content of the invention
Technical problem to be solved in the utility model is exactly to be to provide a kind of box filled piece of built-in line of building, and it is not only
Wood chip can be replaced to fill line box, and can precisely fix line box, prevented displacement, iron is left in structure roof while avoiding
Nail.
In order to solve above-mentioned existing technical problem, the utility model uses following scheme:The pre-buried line box of one kind building is filled out
Fill block by:Filling block anchors into section(1), screw hole(2), sealing strip(3), groove(4), groove sealing strip(5)Constitute, its material
For elastomeric material, wherein filling block anchors into section(1)Cup type is designed as convenience of insertion line box, lower mouth is small suitable for reading big, bottom size
For 69 × 69mm, size suitable for reading is 71 × 71mm, and thickness is 13mm, to prevent box filled piece of slurries during concrete is poured of built-in line
Penetrate into line box, filling block is non-to anchor into the sealing strip that section is designed as turning up(3)With groove sealing strip(5), size of turning up is 2mm,
Thickness is 2mm, designs 5 screw holes(2)A diameter of 6mm, depth is 15mm, and filling block is designed as groove at pre-buried line box neck
(4)Size is 8 × 15 × 13mm, groove sealing strip(5)Thickness is 2mm, and size is 2 × 17mm.
Beneficial effect:
A kind of box filled piece of built-in line of building that the utility model is provided using above-mentioned technical proposal, convenient, filling of constructing
Effect is good, line box fixation accurate and repeatable utilization.
Brief description of the drawings
Fig. 1 is a kind of building box filled piece of plan of built-in line;
Fig. 2 is a kind of building box filled piece of elevation of built-in line;
Fig. 3 is that a kind of box filled piece of built-in line of building is fixed on template(7)Upper schematic diagram;
Fig. 4 is pre-buried line box(8)It is fixed on a kind of upper schematic diagram of box filled piece of building built-in line;
Fig. 5 is concrete(11)After the completion of pouring, template(7)Schematic diagram is removed with one kind building pre-embedded block.
Embodiment
Such as Fig. 1, a kind of box filled piece of built-in line of building is made according to floor map;
Such as Fig. 2, a kind of box filled piece of built-in line of building is made according to elevation;
Such as Fig. 3, pre-buried line box is drawn in template(8)Position, in this position respectively by 5 screws(6)Through screw hole
(2)It is fixed on template(7)On;
Such as Fig. 4, reinforcing bar(9)Colligation and pre-buried line box(8)With penetration pipe(10)After the completion of connection, pre-buried line box(8)Insertion
Filling block anchors into section(1)On, utilize pre-buried line box(8)Section is anchored into filling block(1)Bond stress, fixed pre-buried line box;
Such as Fig. 5, concrete(11)After the completion of pouring, intensity meets form removal requirement can form removal(7), because one kind is built
Build box filled piece of built-in line and be fixed on template(7)On, filling block is anchored into section therewith(1)From pre-buried line box(8)In take out of, it is pre-buried
Line box(8)It is precisely pre-buried to complete.
Claims (1)
1. one kind box filled piece of built-in line of building by:Filling block anchors into section(1), screw hole(2), sealing strip(3), groove(4)、
Groove sealing strip(5)Constitute, its material is elastomeric material, wherein filling block anchors into section(1)Cup is designed as convenience of insertion line box
Type, lower mouth is small suitable for reading big, and bottom size is 69 × 69mm, and size suitable for reading is 71 × 71mm, and thickness is 13mm, to prevent built-in line
Box filled piece during concrete is poured slurries penetrate into line box in, filling block is non-to anchor into the sealing strip that section is designed as turning up(3)And groove
Sealing strip(5), size of turning up is 2mm, and thickness is 2mm, designs 5 screw holes(2)A diameter of 6mm, depth is 15mm, built-in line
Filling block is designed as groove at box neck(4)Size is 8 × 15 × 13mm, groove sealing strip(5)Thickness is 2mm, size is 2 ×
17mm。
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720314353.8U CN206616827U (en) | 2017-03-29 | 2017-03-29 | One kind box filled piece of built-in line of building |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720314353.8U CN206616827U (en) | 2017-03-29 | 2017-03-29 | One kind box filled piece of built-in line of building |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN206616827U true CN206616827U (en) | 2017-11-07 |
Family
ID=60234515
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201720314353.8U Expired - Fee Related CN206616827U (en) | 2017-03-29 | 2017-03-29 | One kind box filled piece of built-in line of building |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN206616827U (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107968369A (en) * | 2017-12-19 | 2018-04-27 | 上海宝钢工程咨询有限公司 | A kind of pre-buried wire box of construction |
| CN108590203A (en) * | 2018-04-29 | 2018-09-28 | 陕西建工第三建设集团有限公司 | It is a kind of using the pre-buried electric box of rubber adapter or the construction method of electrical box |
| CN111441581A (en) * | 2020-04-30 | 2020-07-24 | 北京天润建设有限公司 | Template structure and construction method thereof |
| CN113541068A (en) * | 2021-07-19 | 2021-10-22 | 中国建筑第八工程局有限公司 | Concealed wiring box and mounting method thereof |
-
2017
- 2017-03-29 CN CN201720314353.8U patent/CN206616827U/en not_active Expired - Fee Related
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107968369A (en) * | 2017-12-19 | 2018-04-27 | 上海宝钢工程咨询有限公司 | A kind of pre-buried wire box of construction |
| CN108590203A (en) * | 2018-04-29 | 2018-09-28 | 陕西建工第三建设集团有限公司 | It is a kind of using the pre-buried electric box of rubber adapter or the construction method of electrical box |
| CN111441581A (en) * | 2020-04-30 | 2020-07-24 | 北京天润建设有限公司 | Template structure and construction method thereof |
| CN113541068A (en) * | 2021-07-19 | 2021-10-22 | 中国建筑第八工程局有限公司 | Concealed wiring box and mounting method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN206616827U (en) | One kind box filled piece of built-in line of building | |
| CN108374489A (en) | A prefabricated concrete column foot joint structure and its construction method | |
| CN105113797A (en) | Pouring device and method for constructional columns connected with ring beam | |
| CN202023366U (en) | Tie bar structure applicable to cast-in-situ concrete columns | |
| CN203247600U (en) | Equipment foundation bolt preformed hole die | |
| CN107338911A (en) | Precast shear wall steel bar connecting joints | |
| CN205735482U (en) | A kind of structure of fixing built-in fitting | |
| CN106639305A (en) | Constructional column steel template capable of being lifted in slipping mode and construction method thereof | |
| CN107447980A (en) | A kind of building plastic formwork and its installation method for substituting brick fetal membrane | |
| CN202925561U (en) | Bearing platform template structure | |
| CN104762926B (en) | Embedded groove type aqueduct water-stop structure and construction method thereof | |
| CN208777557U (en) | Exposed inversion reinforcing bar grout sleeve precast concrete column | |
| CN209114658U (en) | A kind of precast concrete partition plate structure for staircase | |
| CN209429263U (en) | A kind of prefabricated column connected node fixing templates | |
| CN205954675U (en) | Prefabricated pipeline concrete buttress | |
| CN208235562U (en) | A kind of static pressure pile structure for Collapsible Loess Stabilized | |
| CN203583514U (en) | Pre-buried structure of ultra-deep foundation bolt | |
| CN207092299U (en) | A kind of cast-in-place hollow armored concrete filling wall | |
| CN107237436B (en) | A kind of method of temporarily fixing when cavity floor is constructed | |
| CN203412124U (en) | Dry-hanging external wall insulation board serving as detaching-free building template | |
| CN202766970U (en) | Cast-in-place outer vertical face seamless seal anchor structure | |
| CN207794321U (en) | Monoblock type fills walling steel tie bar embedded part | |
| CN207794322U (en) | A kind of built-in fitting | |
| CN109881817A (en) | A kind of precast concrete shear wall horizontal joint box out overlapped forming hole method | |
| CN214462517U (en) | Lower opening seam plugging structure of aluminum alloy inner wall template |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171107 Termination date: 20180329 |