CN203393740U - Integral reinforced concrete foundation structure for assembling drainage pipelines - Google Patents

Integral reinforced concrete foundation structure for assembling drainage pipelines Download PDF

Info

Publication number
CN203393740U
CN203393740U CN201320476364.8U CN201320476364U CN203393740U CN 203393740 U CN203393740 U CN 203393740U CN 201320476364 U CN201320476364 U CN 201320476364U CN 203393740 U CN203393740 U CN 203393740U
Authority
CN
China
Prior art keywords
plate
prefabricated foundation
foundation
plates
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320476364.8U
Other languages
Chinese (zh)
Inventor
万学良
张磊
王贤萍
黄屹
吴穹
解明利
张海昱
吴加伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yangtze River Delta Jiaxing Urban And Rural Construction Design Group Co ltd
Original Assignee
JIAXING PLANNING & RESEARCH INSTITUTE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIAXING PLANNING & RESEARCH INSTITUTE Co Ltd filed Critical JIAXING PLANNING & RESEARCH INSTITUTE Co Ltd
Priority to CN201320476364.8U priority Critical patent/CN203393740U/en
Application granted granted Critical
Publication of CN203393740U publication Critical patent/CN203393740U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses an integral reinforced concrete foundation structure for assembling drainage pipelines. The integral reinforced concrete foundation structure comprises prefabricated foundation plates, connecting plates and pipe sleepers; the prefabricated foundation plates are groove-shaped plates, comprise bottom plates and groove walls integrally connected with the bottom plates and are sequentially spliced with one another to form a foundation structure, the connecting plates are arranged among the adjacent prefabricated foundation plates and are cushioned under the prefabricated foundation plates, and the pipe sleepers are arranged on the bottom plates of the prefabricated foundation plates. The integral reinforced concrete foundation structure has the advantages of simple structure, convenience in construction, good integrity, high strength, social benefit, environmental benefit and economical benefit and short construction period.

Description

Drainage pipe assembled integral reinforced concrete foundation structure
Technical field
The utility model relates to drainage works field, especially a kind of drainage pipe assembled integral reinforced concrete foundation structure.
Background technology
Along with development and the attention to environmental protection of urban construction, the laying of various municipal pipelines is also more and more.According to the material of pipeline, purposes, buried depth degree and geological condition, generally all can adopt cast-in-place basis.But because cast-in-place foundation construction is complicated, long in time limit, when running into the bad situation of soil property, quality cannot guarantee.
Utility model content
The purpose of this utility model is to provide a kind of drainage pipe assembled integral reinforced concrete foundation structure, easy for installation, intensity is high, and the duration is short.
What the utility model solved is that cast-in-place foundation construction is complicated, long in time limit, the problem that quality cannot guarantee when running into the bad situation of soil property.
The technical scheme that the utility model solves its technical problem employing is: the utility model comprises prefabricated foundation plate, junction plate and pipe pillow; Prefabricated foundation plate is groove type plate, comprises base plate and the cell wall connecting as one, and prefabricated foundation plate is spliced into foundation structure in order, and junction plate is located between contiguous prefabricated foundation slab and is padded on the below of prefabricated foundation plate, and pipe pillow is located at the base plate top of prefabricated foundation plate.
The beneficial effects of the utility model are: prefabricated foundation plate of the present utility model is designed to trench structure, have greatly alleviated the weight of prefabricated foundation plate, are conducive to lifting.Pipe pillow can be used for adjusting the absolute altitude of pipeline.Use the utility model easy construction, good integrity, intensity is high, and the duration is short, has higher social benefit, environmental benefit and economic benefit.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Fig. 2 is the schematic diagram of the utility model junction plate and seam.
Fig. 3 is Fig. 2 A-A generalized section.
The specific embodiment
Below in conjunction with drawings and Examples, the utility model is described in further detail.
As shown in Figure 1, Figure 2 and Figure 3, the utility model comprises prefabricated foundation plate 1, junction plate 4 and pipe pillow 2; Prefabricated foundation plate 1 is groove type plate, comprises base plate 1-3 and the cell wall 1-2 connecting as one, and prefabricated foundation plate 1 is spliced into foundation structure in order.Junction plate 4 is located between contiguous prefabricated foundation slab 1 and is padded on the below of prefabricated foundation plate 1, and pipe pillow 2 is located at the base plate 1-3 top of prefabricated foundation plate 1.
Prefabricated foundation plate 1 avris is provided with connecting reinforcement 1-4, and seam 5 is left in contiguous prefabricated foundation slab stitching portion, and the connecting reinforcement 1-4 of contiguous prefabricated foundation slab is at seam crossing by steel connector 6 or welding manner or connect by overlapping mode, and seam crossing tamps concrete.Pipe pillow 2 is located at the base plate 1-3 upside central authorities of prefabricated foundation plate 1.Pipe pillow 2 is for adjusting pipeline absolute altitude.
The remaining space installing in the groove of prefabricated foundation plate 1 after drainage pipe tamps with concrete 3.
Ordered arrangement and concrete watering at prefabricated foundation plate 1, junction plate 4 and pipe pillow 2 pour down, and have formed drainage pipe assembled integral reinforced concrete foundation structure of the present utility model.

Claims (3)

1. a drainage pipe assembled integral reinforced concrete foundation structure, comprises prefabricated foundation plate, junction plate and pipe pillow; It is characterized in that prefabricated foundation plate is groove type plate, comprise base plate and the cell wall connecting as one, prefabricated foundation plate is spliced into foundation structure in order, and junction plate is located between contiguous prefabricated foundation slab and is padded on the below of prefabricated foundation plate, and pipe pillow is located at the base plate top of prefabricated foundation plate.
2. drainage pipe assembled integral reinforced concrete foundation structure according to claim 1, it is characterized in that prefabricated foundation edges of boards side is provided with connecting reinforcement, seam is left in contiguous prefabricated foundation slab stitching portion, the connecting reinforcement of contiguous prefabricated foundation slab is at seam crossing by steel connector or welding manner or connect by overlapping mode, and seam crossing tamps concrete.
3. drainage pipe assembled integral reinforced concrete foundation structure according to claim 1, is characterized in that managing the base plate upside central authorities that pillow is located at prefabricated foundation plate.
CN201320476364.8U 2013-08-06 2013-08-06 Integral reinforced concrete foundation structure for assembling drainage pipelines Expired - Lifetime CN203393740U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320476364.8U CN203393740U (en) 2013-08-06 2013-08-06 Integral reinforced concrete foundation structure for assembling drainage pipelines

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320476364.8U CN203393740U (en) 2013-08-06 2013-08-06 Integral reinforced concrete foundation structure for assembling drainage pipelines

Publications (1)

Publication Number Publication Date
CN203393740U true CN203393740U (en) 2014-01-15

Family

ID=49905282

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320476364.8U Expired - Lifetime CN203393740U (en) 2013-08-06 2013-08-06 Integral reinforced concrete foundation structure for assembling drainage pipelines

Country Status (1)

Country Link
CN (1) CN203393740U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105239660A (en) * 2015-11-09 2016-01-13 中建八局第四建设有限公司 Diversion trench and diversion trench construction method
CN106759384A (en) * 2016-12-24 2017-05-31 中铁十八局集团有限公司 A kind of method that use prefabricated pipeline base plate does Brace in Deep Footing Groove
CN109356353A (en) * 2018-11-28 2019-02-19 金螳螂精装科技(苏州)有限公司 A kind of ground layer mounting structure of subsided rest room
CN115075287A (en) * 2022-06-17 2022-09-20 江苏顺为绿色建筑科学研究院有限公司 Disassembly-free prefabricated pipeline foundation and construction method thereof
CN115075287B (en) * 2022-06-17 2024-06-04 江苏顺为绿色建筑科学研究院有限公司 Disassembly-free prefabricated pipeline foundation and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105239660A (en) * 2015-11-09 2016-01-13 中建八局第四建设有限公司 Diversion trench and diversion trench construction method
CN106759384A (en) * 2016-12-24 2017-05-31 中铁十八局集团有限公司 A kind of method that use prefabricated pipeline base plate does Brace in Deep Footing Groove
CN109356353A (en) * 2018-11-28 2019-02-19 金螳螂精装科技(苏州)有限公司 A kind of ground layer mounting structure of subsided rest room
CN115075287A (en) * 2022-06-17 2022-09-20 江苏顺为绿色建筑科学研究院有限公司 Disassembly-free prefabricated pipeline foundation and construction method thereof
CN115075287B (en) * 2022-06-17 2024-06-04 江苏顺为绿色建筑科学研究院有限公司 Disassembly-free prefabricated pipeline foundation and construction method thereof

Similar Documents

Publication Publication Date Title
CN203440994U (en) Corrugated web I-section steel and concrete composite flat beam
CN205604290U (en) Frame energy dissipation formula of turning up utility tunnel structure
CN203393740U (en) Integral reinforced concrete foundation structure for assembling drainage pipelines
CN204002833U (en) The embed-type passage of many circular arcs arched corrugated steel plate
CN202247719U (en) Corresponding corrugated pre-stressed anti-sedimentation culvert pipe for bridge
CN203238621U (en) Grouting pile provided with double layers of tensile bars
CN206035045U (en) Prefabricated assembled underground granary of endocyst plastics
CN202622994U (en) Steel pedestal structure for pouring precast beam
CN204551172U (en) A kind of prefabricated road surface of assembled steel reinforced concrete hollow
CN202830672U (en) Buttress type U-shaped groove structure
CN207017169U (en) A kind of high-filled subgrade culvert off-loading structure
CN202989942U (en) Wall foundation structure for soft soil or high backfill soil area
CN202117049U (en) Latch type steel pipe pile
CN205604289U (en) Can resist single storehouse underground pipe gallery of large deformation
CN205276317U (en) Utility tunnel's steel construction
CN203429885U (en) Circular-hole web box-shaped steel reinforced concrete composite flat beam
CN204023348U (en) Fast-type backroad hard surface
CN203346857U (en) Prefabricated part for trapezoid channel lining
CN203440990U (en) Toothed web box-type steel and concrete composite flat beam
CN202598918U (en) Buried heat storage container
CN103206221B (en) Large span heavy load thrust arch formula open-cut tunnel structure
CN203475457U (en) Composite pile foundation used for soft soil building foundation
CN203394539U (en) Thrust arch-type open tunnel structure with large span and heavy load
CN202031041U (en) Oblique-crossing precast assembled reinforced concrete culvert
CN205276329U (en) Prefabricated girth joint structure of assembling tunnel

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 314505 No.318, Zhonghuan South Road, Jiaxing City, Zhejiang Province

Patentee after: Yangtze River Delta (Jiaxing) Urban and Rural Construction Design Group Co.,Ltd.

Address before: 314505 No.318, Zhonghuan South Road, Jiaxing City, Zhejiang Province

Patentee before: JIAXING PLANNING & RESEARCH INSTITUTE Co.,Ltd.

CP01 Change in the name or title of a patent holder
CX01 Expiry of patent term

Granted publication date: 20140115

CX01 Expiry of patent term