CN203475457U - Composite pile foundation used for soft soil building foundation - Google Patents

Composite pile foundation used for soft soil building foundation Download PDF

Info

Publication number
CN203475457U
CN203475457U CN201320506778.0U CN201320506778U CN203475457U CN 203475457 U CN203475457 U CN 203475457U CN 201320506778 U CN201320506778 U CN 201320506778U CN 203475457 U CN203475457 U CN 203475457U
Authority
CN
China
Prior art keywords
foundation
graphite
reinforced concrete
pile
stake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320506778.0U
Other languages
Chinese (zh)
Inventor
李正全
洪伟
韩少龙
郝彤途
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CITIC Construction Co Ltd
Original Assignee
CITIC Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CITIC Construction Co Ltd filed Critical CITIC Construction Co Ltd
Priority to CN201320506778.0U priority Critical patent/CN203475457U/en
Application granted granted Critical
Publication of CN203475457U publication Critical patent/CN203475457U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to the field of buildings, in particular to a composite pile foundation used for a soft soil building foundation. The composite pile foundation used for the soft soil building foundation comprises an upper-portion foundation body, a bearing layer, reinforced concrete piles and graphite piles. The length of the reinforced concrete piles is equal to the length of the graphite piles, one end of each reinforced concrete pile and one end of each graphite pile are both inserted into the bearing layer, the length by which the end of each reinforced concrete pile is inserted and the length by which the end of each graphite pile is inserted are equal, and the upper-portion foundation body is arranged on the other ends of the reinforced concrete piles and the other ends of the graphite piles. According to the composite pile foundation for the soft soil building foundation, the reinforced concrete piles and the graphite piles are arranged, the length of the reinforced concrete piles is the same as the length of the graphite piles, one end of each reinforced concrete pile and one end of each graphite pile are together inserted into the bearing layer and the upper-portion foundation body is arranged on the other ends of the reinforced concrete piles and the other ends of the graphite piles. Due to the fact that the reinforced concrete piles, the graphite piles and soil below the upper-portion foundation body can together bear the load of a building, the composite pile foundation has good load capacity. Compared with an existing pile foundation, the composite pile foundation used for the soft soil building foundation is reduced in manufacturing cost, and therefore the building cost is lowered.

Description

A kind of for weak soil building foundation composite pile foundation
Technical field
The utility model relates to building field, in particular to a kind of for weak soil building foundation composite pile foundation.
Background technology
At present, the base form that China's building foundation field adopts has three kinds of natural ground, composite foundation and pile foundations.In correlation technique, be directed to Soft Clay, conventionally adopting pile foundation is base form, though adopt the good load of bearing building of this base form energy, pile foundation cost is too high, causes the rising of building costs.Therefore develop and a kind ofly can well bear built-loading, can reduce again the composite pile foundation of building costs, be people's problem demanding prompt solutions.
Utility model content
It is a kind of for weak soil building foundation composite pile foundation, to solve the above problems that the purpose of this utility model is to provide.
In embodiment of the present utility model, provide a kind of for weak soil building foundation composite pile foundation, comprise basis, top, bearing stratum, reinforced concrete pile and graphite stake, reinforced concrete pile and graphite stake equal in length, all insert in bearing stratum one end of one end of reinforced concrete pile and graphite stake, and insertion is equal in length; State on the other end of reinforced concrete pile and the other end of graphite stake and be provided with basis, top.
The utility model above-described embodiment a kind of for weak soil building foundation composite pile foundation, by by the reinforced concrete pile of equal length and graphite stake, and inserts bearing stratum jointly by its one end, its other end be provided with basis, top above.Due to the soil under reinforced concrete pile and graphite stake and basis, top can shared the load of building, therefore composite pile foundation has good weight bearing power.Through a large amount of architectural experiments, prove, be directed to the building foundation of soft clay area, adopt the common composite pile foundation forming of reinforced concrete pile and graphite stake to compare with existing pile foundation, can reduce by 20%~30% pile foundation cost, thereby reduce building costs; And can effectively prevent the sedimentation of building, can be by settlement Control between 1 centimetre~4 centimetres.
Accompanying drawing explanation
Fig. 1 shows a kind of structural representation for weak soil building foundation composite pile foundation that the utility model provides.
The specific embodiment
Below by specific embodiment, also by reference to the accompanying drawings the utility model is described in further detail.
As shown in Figure 1, what the present embodiment provided is a kind of for weak soil building foundation composite pile foundation, comprises basis, top, bearing stratum 6, reinforced concrete pile 4 and graphite stake 5.Reinforced concrete pile 4 is equal in length with graphite stake 5.All insert in bearing stratum 6 one end of one end of reinforced concrete pile 4 and graphite stake 5, and insertion is equal in length.Above the other end of the other end of reinforced concrete pile 4 and graphite stake 5, be provided with basis, top.What the present embodiment provided is a kind of for weak soil building foundation composite pile foundation, by by the reinforced concrete pile of equal length 4 and graphite stake 5, and its one end is inserted to bearing stratum 6 jointly, its other end be provided with basis, top above.Due to the soil under reinforced concrete pile 4 and graphite stake 5 and basis, top can shared building load, therefore composite pile foundation has good weight bearing power.Through a large amount of architectural experiments, prove, be directed to the building foundation of soft clay area, adopt reinforced concrete pile 4 to compare with existing pile foundation with the common composite pile foundation forming of graphite stake 5, can reduce by 20%~30% pile foundation cost, thereby reduce building costs; And can effectively prevent the sedimentation of building, can be by settlement Control between 1 centimetre~4 centimetres.In addition, in the present embodiment, reinforced concrete pile 4 arranges with graphite stake 5 intervals, between two adjacent reinforced concrete piles 4, is provided with a graphite stake 5, and design like this can further can effectively increase the weight bearing power of the composite pile foundation that the present embodiment provides.
As shown in Figure 1, the present embodiment provides a kind ofly can also comprise mattress layer 3 for weak soil building foundation composite pile foundation, mattress layer 3 be arranged on basis, top below, be arranged on reinforced concrete pile 4 and graphite stake 5 above, mattress layer is arranged between top basis and reinforced concrete pile 4 and graphite stake 5.The material of mattress layer 3 can be selected according to the actual needs of building, and its thickness also can need according to actual building to select.In the present embodiment, mattress layer 3 is preferably comprised of rubble and sand, and the thickness of mattress layer 3 is 10 centimetres~25 centimetres.By be provided with mattress layer 3 between reinforced concrete pile 4, graphite stake 5 and basis, top, between the composite pile foundation that can make building and the present embodiment provide, there is good buffering, make this composite pile foundation there is stronger shock resistance.Through seismic resistance calculation, the composite pile foundation seismic resistance calculation that the present embodiment provides reaches 8 degree requirementss for fortification against earthquake.Furthermore, what the present embodiment provided is a kind of for weak soil building foundation composite pile foundation, and basis, top comprises C10 element concrete bed course 2 and raft plate 1, and C10 element concrete bed course 2 is arranged on mattress layer 3, and raft plate 1 is arranged on C10 element concrete bed course 2.Further, in the present embodiment, bearing stratum 6 is boulder bed.Provide in the present embodiment a kind of for weak soil building foundation composite pile foundation is provided, at mattress layer 3, away from a side of C10 element concrete bed course 2, be provided with a slabstone 7, and a stake slabstone 7 is arranged between reinforced concrete pile 4 and graphite stake 5.By being provided with a slabstone 7, can make reinforced concrete pile 4, graphite stake 5 and the basis, top link together closely, further improved the load-carrying ability of the composite pile foundation that the present embodiment provides.
As shown in Figure 1, what the present embodiment provided is a kind of for weak soil building foundation composite pile foundation, first with pile press, graphite stake 5 and reinforced concrete pile 4 is passed to soil layer 8, is pressed into bearing stratum 6.Between graphite stake 5 and reinforced concrete pile 4, a slabstone 7 is set, then graphite stake 5 with reinforced concrete pile 4 above, spread mattress layer 3, finally on mattress layer, spread successively the plain concrete bed course 2 of C10 and raft plate 1.
As shown in Figure 1, what the present embodiment provided is a kind of for weak soil building foundation composite pile foundation, by being provided with reinforced concrete pile 4, graphite stake 5 and mattress layer 3, therefore have higher load-carrying ability, effectively prevent the sedimentation of building, can be by settlement Control between 1 centimetre~4 centimetres; And effectively reduce the cost of traditional pile foundation, lower building costs.In addition, also there is higher shock resistance, through seismic resistance calculation, reach 8 degree requirementss for fortification against earthquake.
The foregoing is only preferred embodiment of the present utility model, be not limited to the utility model, for a person skilled in the art, the utility model can have various modifications and variations.All within spirit of the present utility model and principle, any modification of doing, be equal to replacement, improvement etc., within all should being included in protection domain of the present utility model.

Claims (8)

1. one kind for weak soil building foundation composite pile foundation, it is characterized in that, comprise basis, top, bearing stratum, reinforced concrete pile and graphite stake, described reinforced concrete pile and described graphite stake equal in length, all insert in described bearing stratum one end of one end of described reinforced concrete pile and described graphite stake, and insertion is equal in length; Above the other end of the other end of described reinforced concrete pile and described graphite stake, be provided with basis, top.
2. according to claim 1 a kind ofly it is characterized in that for weak soil building foundation composite pile foundation, described reinforced concrete pile and described graphite stake interval arrange.
3. according to claim 2 a kind ofly it is characterized in that for weak soil building foundation composite pile foundation, also comprise mattress layer, described mattress layer be arranged on basis, described top below, be arranged on described reinforced concrete pile and described graphite stake above.
4. according to claim 3 a kind of for weak soil building foundation composite pile foundation, it is characterized in that, basis, described top comprises C10 element concrete bed course and raft plate, and described C10 element concrete bed course is arranged on described mattress layer, and described raft plate is arranged on described C10 element concrete bed course.
5. according to claim 4 a kind ofly it is characterized in that for weak soil building foundation composite pile foundation, described bearing stratum is boulder bed.
6. according to claim 5 a kind ofly it is characterized in that for weak soil building foundation composite pile foundation, described mattress layer is comprised of rubble and sand.
7. according to claim 6 a kind ofly it is characterized in that for weak soil building foundation composite pile foundation, the thickness of described mattress layer is 10 centimetres~25 centimetres.
8. according to claim 7 a kind of for weak soil building foundation composite pile foundation, it is characterized in that, at described mattress layer, away from a side of described C10 element concrete bed course, be also provided with a slabstone, and described stake slabstone is arranged between described reinforced concrete pile and described graphite stake.
CN201320506778.0U 2013-08-19 2013-08-19 Composite pile foundation used for soft soil building foundation Expired - Lifetime CN203475457U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320506778.0U CN203475457U (en) 2013-08-19 2013-08-19 Composite pile foundation used for soft soil building foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320506778.0U CN203475457U (en) 2013-08-19 2013-08-19 Composite pile foundation used for soft soil building foundation

Publications (1)

Publication Number Publication Date
CN203475457U true CN203475457U (en) 2014-03-12

Family

ID=50223813

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320506778.0U Expired - Lifetime CN203475457U (en) 2013-08-19 2013-08-19 Composite pile foundation used for soft soil building foundation

Country Status (1)

Country Link
CN (1) CN203475457U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103912005A (en) * 2014-04-14 2014-07-09 五邑大学 Foundation structure
CN104153383A (en) * 2014-08-08 2014-11-19 中建五局土木工程有限公司 Marine facies soft soil foundation structure and processing method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103912005A (en) * 2014-04-14 2014-07-09 五邑大学 Foundation structure
CN104153383A (en) * 2014-08-08 2014-11-19 中建五局土木工程有限公司 Marine facies soft soil foundation structure and processing method thereof
CN104153383B (en) * 2014-08-08 2016-06-08 中建五局土木工程有限公司 A kind of marine soft soil foundation structure and treatment process thereof

Similar Documents

Publication Publication Date Title
CN202543966U (en) Pile-supported cantilever retaining wall
CN202466620U (en) Reinforced concrete buttress retaining wall
CN203755341U (en) Geogrid retaining wall
CN202117068U (en) Micropile plate-type composite foundation
CN204000897U (en) A kind of for the multipurpose anti-slide pile structure system on sliding mass
CN203846450U (en) Riverway retaining wall
CN202227368U (en) Underground groove structured anti-floating structure
CN103993580B (en) A kind of river course barricade
CN102797265A (en) Protective structure for bedding slope bridge piers and abutments
CN203475457U (en) Composite pile foundation used for soft soil building foundation
CN204000914U (en) A kind of composite foundation base
CN203977409U (en) A kind of prefabricated assembled concrete pile foundation
CN202830994U (en) Protective structure for bedding slope bridge abutments
CN202124863U (en) Screw anchor excavated composite foundation
CN203891020U (en) Bundled type slurry pocket grouting anchor rod
CN203977433U (en) Soft Deep Foundation Pit engineering composite supporting construction
CN201517210U (en) Concrete wedge-shaped post with ribs
CN203947469U (en) Two carrying helical burr ram for building
CN203603162U (en) Construction elevator load basic system based on foundation pit edge
CN203080540U (en) Iron tower foundation of power transmission line
CN2905904Y (en) Stereo reinforced earth
CN204356794U (en) Adjustable building pile foundation differential settlement device
CN202416304U (en) Special-shaped concrete tubular pile
CN204238222U (en) Foundation pit structure
CN206308823U (en) Rubber granule energy-eliminating shock-insulating structure is filled out outside rammed earth agriculture room constructional column

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20140312