CN203312731U - Transformer station flexible bus sag-adjusting device - Google Patents

Transformer station flexible bus sag-adjusting device Download PDF

Info

Publication number
CN203312731U
CN203312731U CN2013203139089U CN201320313908U CN203312731U CN 203312731 U CN203312731 U CN 203312731U CN 2013203139089 U CN2013203139089 U CN 2013203139089U CN 201320313908 U CN201320313908 U CN 201320313908U CN 203312731 U CN203312731 U CN 203312731U
Authority
CN
China
Prior art keywords
sag
adjusting device
insulator
transformer station
flexible bus
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2013203139089U
Other languages
Chinese (zh)
Inventor
刘春雨
刘明辉
李丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Cangzhou Power Supply Co of State Grid Hebei Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Cangzhou Power Supply Co of State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Hebei Electric Power Co Ltd, Cangzhou Power Supply Co of State Grid Hebei Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN2013203139089U priority Critical patent/CN203312731U/en
Application granted granted Critical
Publication of CN203312731U publication Critical patent/CN203312731U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Insulators (AREA)

Abstract

The utility model discloses a transformer station flexible bus sag-adjusting device, and relates to the technical field of transformer station distribution lines. The sag-adjusting device comprises a composite silica gel insulator, a porcelain insulator and a strain clamp. The other ends of the insulators are provided with stroke adjusting bolts capable of being connected with a tower. The sag-adjusting device has a simple structure, is convenient and reliable, and can timely, rapidly and safely adjust the sag of a flexible bus. By employing the sag-adjusting device, standards accord with requirements are met, replacing times are decreased, labor, time and materials are saved, work intensity for erection and daily maintenance is reduced, line faults are reduced, power supply reliability is improved, and economy losses of countries and enterprises are reduced.

Description

The transformer station flexible bus sag adjusting device
Technical field
The utility model relates to transformer station flexible bus and distribution line technical field.
Background technology
In the voltage power distribution equipments at different levels of transformer and distribution station, engine, transformer are called to bus with the wire that various electrical equipment is connected.Bus is divided into hard bus and soft bus by structure, and hard bus is mainly used in indoor, and soft bus is mainly used in being connected between transmission line and transformer, is mainly used in outdoorly, is the outdoor aerial aluminium stranded conductor, flexible.In transformer station's line construction process, the sag of adjusting soft bus is to set up, safeguard the indispensable routine work of distribution line, the factors such as the distance between the size of sag and transmission line and transformer, line voltage distribution, weather are relevant, the excessive or too small safe operation that all can affect circuit of sag.When sag is excessive, can not guarantee the safe distance of soft bus to ground, especially during summer high temperature, soft bus can extend because of heat expansion, and sag is larger, during strong wind, also may cause short circuit accident, when sag was too small, the stress that soft bus bears was excessive, when temperature is too low in the winter time, soft bus shrinks, and likely causes the broken string accident.
In the transformer station flexible bus erection process, traditional construction method is: first use soft bus one end insulator to fix in bus steelframe structure one side, the other end is fixed in the other end insulation of bus steelframe structure after adjusting sag, adjust sag and adopt the method for marking, this method usually needs unwrapping wire, stringing several times to adjust sag, working strength is large, and is difficult to the sag adjustment of bus to satisfactory standard; And in day-to-day operation, soft bus there will be the inconsistent situation of sag, if processed not in time, will cause transformer station or line fault, therefore in the regular maintenance process, need to process in time the inconsistent soft bus of sag, and owing to fixing at soft bus two ends, can not adjust, to the inconsistent soft bus of sag occurred, can only change, change and need to have a power failure, cause the operating time long, working strength is large, the waste material.
The utility model content
Technical problem to be solved in the utility model is to provide a kind of simple in structure, convenient and reliable transformer station flexible bus sag adjusting device, can adjust in time, fast, safely the sag of soft bus, reach satisfactory standard, reduced the replacing number of times, laborsaving, save time, economize material.
For solving the problems of the technologies described above, technical solution adopted in the utility model is: a kind of transformer station flexible bus sag adjusting device, comprise insulator and the strain clamp of being located at insulator one end, the other end of described insulator is provided with the stroke adjustment bolt that can be connected with pylon.
Be preferably, described strain clamp is connected with insulator by simply connected bowl head.
Be preferably, described insulator is insulator string.
Be preferably, described stroke adjustment bolt is U bolt, is connected with this insulator by the connecting ring of being located at insulator one end.
Be preferably, described stroke adjustment bolt is provided with connector, and this connector is connected with the stroke adjustment bolt by through hole provided thereon.
The beneficial effect that adopts technique scheme to produce is: the utility model is simple in structure, convenient and reliable, can adjust in time, fast, safely the sag of soft bus, reach satisfactory standard, reduced the replacing number of times, laborsaving, save time, economize material, reduce the working strength of setting up with regular maintenance, reduce line fault, reduce the economic loss of country and enterprise.The utility model is not only applicable to the adjusting of transformer station flexible bus sag, is applicable to the adjusting of little span circuit (being less than 50m) sag yet.
The accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
In figure: the 1-strain clamp; 2-simply connected bowl head; The 3-insulator; The 4-connecting ring; 5-stroke adjustment bolt; The 6-connector; The 7-nut.
Embodiment
Below in conjunction with the drawings and specific embodiments, the utility model is described in further detail.
As shown in Figure 1, the transformer station flexible bus sag adjusting device, comprise insulator 3 and the strain clamp 1 of being located at insulator 3 one ends, and the other end of described insulation 3 is provided with the stroke adjustment bolt 5 that can be connected with pylon; Described strain clamp 1 is connected with insulator 3 by simply connected bowl 2; Described insulator 3 is preferably as insulator string; Described stroke adjustment bolt 5 is preferably U bolt, is connected with this insulator 3 by the connecting ring 4 of being located at insulator 3 one ends; Described stroke adjustment bolt 5 is provided with connector 6, and this connector 6 is connected with stroke adjustment bolt 5 by through hole provided thereon.
Strain clamp 1 is for being fixed on wire on insulator string and bearing the gold utensil of wire tension, select strain clamp 1, can selecting according to actual needs different models, easy to use; Adopt being connected of strain clamp 1 and insulator 3 simply connected bowl 2, simply connected bowl 2 connection functions, used mounting or dismounting convenient, and can guarantee certain safe distance; Insulator 3 is selected insulator string, the number of the insulator on insulator string can be selected according to the gradation for surface pollution of electric pressure, insulator material, infield, therefore the utility model can be selected suitable insulator string according to concrete actual conditions, one end of insulator string, with connecting ring 4, facilitates penetrating of U bolt; Stroke adjustment bolt 5 is used for regulating the size of soft bus sag, its length can be selected according to actual conditions, preferably use U bolt, be equivalent to regulate with two bolts fixing, by the nut 7 on U bolt, regulate the sag of soft bus after required standard, and the two ends of U bolt are fixed to pylon, strengthened stable and fail safe; On U bolt, being provided with connector 6, is in order with pylon, to be fixedly connected with.
In concrete line construction process, an end that the utility model is provided with to strain clamp 1 is connected with soft bus, connector 6 on U bolt is fixedly linked with pylon, connector 6 can directly be welded on pylon, also two through holes can be set on connector 6, adopt bolt that connector 6 and pylon are fixed together, the two ends of U bolt are all with nut 7, can regulate the sag of soft bus, reach and meet the requirements, because power system security has a big risk, in the specific implementation, for guaranteeing power system security, at the two ends of U bolt, all adopt double nut 7 fixing, adopt again split pin locking nut 7.In the operating repairs process, when the sag of soft bus is undesirable, also can pass through adjusting nut 7 in the situation that do not cut off the power supply, make the sag of soft bus reach requirement.
The utility model is simple in structure, convenient and reliable, can adjust in time, fast, safely the sag of soft bus, reach satisfactory standard, reduced the replacing number of times, laborsaving, save time, economize material, reduce the working strength of setting up with regular maintenance, reduce line fault, reduce the economic loss of country and enterprise, be particularly suitable for the adjusting of transformer station flexible bus, little span circuit (being less than 50 meters) sag.

Claims (5)

1. transformer station flexible bus sag adjusting device is characterized in that: comprise insulator (3) and be located at the strain clamp (1) of insulator (3) one ends, the other end of described insulator (3) is provided with the stroke adjustment bolt (5) that can be connected with pylon.
2. transformer station flexible bus sag adjusting device according to claim 1 is characterized in that: described strain clamp (1) is connected with insulator (3) by simply connected bowl head (2).
3. transformer station flexible bus sag adjusting device according to claim 1, it is characterized in that: described insulator (3) is insulator string.
4. transformer station flexible bus sag adjusting device according to claim 1, it is characterized in that: described stroke adjustment bolt (5) is U bolt, is connected with this insulator (3) by the connecting ring (4) of being located at insulator (3) one ends.
5. according to the described transformer station flexible bus sag adjusting device of claim 1 or 4, it is characterized in that: described stroke adjustment bolt (5) is provided with connector (6), and this connector (6) is connected with stroke adjustment bolt (5) by through hole provided thereon.
CN2013203139089U 2013-06-03 2013-06-03 Transformer station flexible bus sag-adjusting device Expired - Fee Related CN203312731U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013203139089U CN203312731U (en) 2013-06-03 2013-06-03 Transformer station flexible bus sag-adjusting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013203139089U CN203312731U (en) 2013-06-03 2013-06-03 Transformer station flexible bus sag-adjusting device

Publications (1)

Publication Number Publication Date
CN203312731U true CN203312731U (en) 2013-11-27

Family

ID=49618906

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013203139089U Expired - Fee Related CN203312731U (en) 2013-06-03 2013-06-03 Transformer station flexible bus sag-adjusting device

Country Status (1)

Country Link
CN (1) CN203312731U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105633886A (en) * 2016-02-18 2016-06-01 成都佳美嘉科技有限公司 Strain clamp for power transmission

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105633886A (en) * 2016-02-18 2016-06-01 成都佳美嘉科技有限公司 Strain clamp for power transmission

Similar Documents

Publication Publication Date Title
CN105514877A (en) Cross arm clamp for insulator replacement of steel pipe pole of common-tower double-circuit lines
CN203352052U (en) Live-line fastening tool for bolt of strain clamp of power transmission line
CN203800477U (en) Clamping tool used for electriferous replacement of first insulator of power transmission line tension single chain at wire side
CN201146346Y (en) Portable insulation maintenance gap bridge
CN203312731U (en) Transformer station flexible bus sag-adjusting device
CN206575086U (en) Insulate turnbuckle plate pulling device
CN203260986U (en) Special framework for arrester and online monitoring instrument on 10kV bus bridge
CN206775000U (en) Wire lifts insulating support
CN202846443U (en) Electrified overhauling wrench
CN202633869U (en) Wind deviation prevention structure of phase drainage wire in 110 kV line YJ-shaped iron tower
CN102222553A (en) Trough-type connecting hardware fitting of sectional-type composite isolator
CN204732236U (en) 10kV lightning-protection ice used for transmission line needle type composite insulator
CN204441800U (en) A kind of 500kV compact line V-type replacing insulator string jig
CN204205413U (en) A kind of link rod of Electrified fastening screw
CN210956301U (en) Insulator string suspension device for salt density test
CN107425466A (en) Wire lifts insulating support and its application method
CN203813320U (en) Tool for live exchange of 220 kV narrow base tower strain insulator string
CN209692315U (en) A kind of walking mechanism of automatic de-icing device
CN202650795U (en) Split type rectifier transformer for DC-based deicing
CN202260345U (en) Power transmission line AC ice melting device adopting capacitor reactive compensation
CN201549854U (en) Inter-conductor insulation supporting device
CN202308903U (en) Insulating supporting holding pole used in cathead suspension tower live line work maintenance
CN205159921U (en) A insulating pole of embracing that is used for changing with electricity with many times transmission line strain insulator string in tower
CN215120054U (en) Ice melting device for power line
CN2168914Y (en) Insulated glass fibre reinforced plastic crossbar

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Patentee after: State Grid Corporation of China

Patentee after: Cangzhou Power Supply Branch Company, State Grid Hebei Electric Power Company

Patentee after: State Grid Hebei Electric Power Company

Address before: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Patentee before: State Grid Corporation of China

Patentee before: Cangzhou Power Supply Co.,Ltd.

Patentee before: Hebei Electric Power Corporation

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20131127

Termination date: 20180603