CN202846443U - Electrified overhauling wrench - Google Patents

Electrified overhauling wrench Download PDF

Info

Publication number
CN202846443U
CN202846443U CN 201220525629 CN201220525629U CN202846443U CN 202846443 U CN202846443 U CN 202846443U CN 201220525629 CN201220525629 CN 201220525629 CN 201220525629 U CN201220525629 U CN 201220525629U CN 202846443 U CN202846443 U CN 202846443U
Authority
CN
China
Prior art keywords
bracket
sleeve
insulating
pull rod
wrench
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220525629
Other languages
Chinese (zh)
Inventor
刘俊强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Cangzhou Power Supply Co of State Grid Hebei Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Cangzhou Power Supply Co of State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Hebei Electric Power Co Ltd, Cangzhou Power Supply Co of State Grid Hebei Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN 201220525629 priority Critical patent/CN202846443U/en
Application granted granted Critical
Publication of CN202846443U publication Critical patent/CN202846443U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Hand Tools For Fitting Together And Separating, Or Other Hand Tools (AREA)

Abstract

本实用新型公开了一种带电检修扳手,包括用于防止螺栓转动的第一绝缘拉杆、第一支架和上套头,以及用于紧固螺栓的第二绝缘拉杆、第二支架和下套头;所述第一绝缘拉杆与第一支架之间、第二绝缘拉杆与第二支架之间均通过焊接固定;所述第二支架与第一支架之间通过第一支架上的套管活动套接;所述第一支架与上套头之间、第二支架与下套头之间均是活动连接。本实用新型的有益效果如下:可以自由调节绝缘杆的长度,实现不同高度电力线路螺栓的检修,检修人员在地面就可进行操作,不用登高,提高检修的安全性和检修效率;在检修工作进行时,可以不用停电,提高供电可靠性,有效维护电力企业的经济利益;整体结构简单,便于拆装和携带。

Figure 201220525629

The utility model discloses a live overhaul wrench, which comprises a first insulating pull rod, a first bracket and an upper sleeve for preventing bolts from rotating, and a second insulating pull rod, a second bracket and a lower sleeve for fastening the bolts; The first insulating rod and the first bracket, the second insulating rod and the second bracket are all fixed by welding; the second bracket and the first bracket are flexibly socketed through the casing on the first bracket; Both the first bracket and the upper sleeve, and the second bracket and the lower sleeve are connected flexibly. The beneficial effects of the utility model are as follows: the length of the insulating rod can be adjusted freely, and the inspection and maintenance of power line bolts of different heights can be realized. When there is no need for power outages, the reliability of power supply can be improved, and the economic interests of power companies can be effectively maintained; the overall structure is simple, and it is easy to disassemble and carry.

Figure 201220525629

Description

带电检修扳手Live maintenance wrench

技术领域 technical field

本实用新型涉及一种带电检修扳手,适用于电力系统检修技术领域。 The utility model relates to a live maintenance wrench, which is suitable for the technical field of power system maintenance.

背景技术 Background technique

目前,国家电力部门的架空线路使用一段时间后,往往需要进行检修,如110-220KV变电站一次设备(开关、CT、PT引线等)的松动,将会导致线路发热,容易引发电路故障,影响人们正常的生产生活。导致一次设备松动的原因主要有:接触面氧化;风力过大引线摇摆;螺栓质量差;线卡质量差。这些故障原因往往发生在夏季用电高峰期,事故一旦发生,需要马上停电检修处理,以一条110KV线路停电2小时为例,每处理一次故障造成的停电损失约为3万KWh。对于电力设备的检修,目前通用的的工具主要有用于紧固螺栓的检修扳手等,现有的检修扳手都是导电材质,需要停电检修;另外现有的检修扳手需要检修人员登高接近电力设备,才能进行检修,效率低,安全可靠性差。因此,迫切需要一种能够带电使用且不用登高的检修扳手。 At present, the overhead lines of the national power department often need to be repaired after being used for a period of time. For example, the looseness of the primary equipment (switches, CTs, PT leads, etc.) normal production and life. The main reasons for the looseness of primary equipment are: oxidation of the contact surface; swinging of lead wires due to excessive wind force; poor quality of bolts; poor quality of line cards. The causes of these failures often occur during the peak power consumption period in summer. Once an accident occurs, it needs to be repaired immediately. Taking a 110KV line outage for 2 hours as an example, the power outage loss caused by each failure is about 30,000 KWh. For the maintenance of electrical equipment, the current general-purpose tools mainly include maintenance wrenches for fastening bolts, etc. The existing maintenance wrenches are made of conductive materials and require power-off maintenance; To carry out maintenance, low efficiency, poor safety and reliability. Therefore, there is an urgent need for an inspection wrench that can be used with electricity and without climbing.

实用新型内容 Utility model content

本实用新型所要解决的技术问题是提供一种可以在地面进行带电操作的带电检修扳手,结构简单,携带方便,提高检修效率。 The technical problem to be solved by the utility model is to provide a live maintenance wrench which can be operated live on the ground, which has a simple structure, is easy to carry, and improves maintenance efficiency.

为解决上述技术问题,本实用新型所采取的技术方案是:一种带电检修扳手,包括用于防止螺栓转动的第一绝缘拉杆、第一支架和上套头,以及用于紧固螺栓的第二绝缘拉杆、第二支架和下套头;所述第一绝缘拉杆与第一支架之间、第二绝缘拉杆与第二支架之间均通过焊接固定;所述第二支架与第一支架之间通过第一支架上的套管活动套接;所述第一支架与上套头之间、第二支架与下套头之间均是活动连接。 In order to solve the above technical problems, the technical solution adopted by the utility model is: a live maintenance wrench, including a first insulating pull rod, a first bracket and an upper sleeve used to prevent the bolt from rotating, and a second bolt used to fasten the bolt. The insulating rod, the second bracket and the lower sleeve; the first insulating rod and the first bracket, the second insulating rod and the second bracket are all fixed by welding; the second bracket and the first bracket are fixed by welding The casing on the first bracket is flexibly socketed; the first bracket and the upper sleeve, and the second bracket and the lower sleeve are all flexibly connected.

所述第一支架与上套头之间通过方接头活动连接,方接头与第一支架焊接,上套头与方接头卡接;所述第二支架与下套头之间通过方接头活动连接,方接头与第二支架焊接,下套头与方接头卡接。 The first bracket and the upper sleeve are movably connected through a square joint, the square joint is welded to the first bracket, and the upper sleeve is clamped with the square joint; the second bracket and the lower sleeve are flexibly connected through a square joint, and the square joint It is welded with the second bracket, and the lower sleeve is clamped with the square joint.

使用本实用新型所述的带电检修扳手进行带电检修的工作过程如下:(1)根据需要紧固或者更换的螺栓型号,选择合适的相应上套头和下套头,并将上套头安装到第一支架上,将下套头安装到第二支架上;(2)检修人员手持第一绝缘拉杆,将上套头靠近待紧固螺栓的上部,并固定不动;(3)检修人员根据螺栓尺寸,调节扳手开口大小,然后操作第二绝缘拉杆使下套头靠近待紧固螺栓的下部;(4)转动第二绝缘拉杆将螺栓进行紧固或拆卸。 The working process of using the live maintenance wrench described in the utility model for live maintenance is as follows: (1) According to the type of bolt to be fastened or replaced, select the appropriate corresponding upper and lower sleeves, and install the upper sleeve to the first bracket (2) The maintenance personnel hold the first insulating pull rod, put the upper sleeve close to the upper part of the bolt to be fastened, and fix it still; (3) The maintenance personnel adjust the wrench according to the size of the bolt The size of the opening, and then operate the second insulating pull rod to make the lower sleeve close to the lower part of the bolt to be fastened; (4) Turn the second insulating pull rod to tighten or disassemble the bolt.

采用上述技术方案所产生的有益效果在于: The beneficial effects produced by adopting the above-mentioned technical scheme are:

(1)将螺栓套头通过支架安装到绝缘杆上,可以自由调节绝缘杆的长度,实现不同高度电力线路螺栓的检修,检修人员在地面就可进行操作,不用登高,提高检修的安全性和检修效率; (1) Install the bolt sleeve on the insulating rod through the bracket, the length of the insulating rod can be adjusted freely, and the maintenance of power line bolts at different heights can be realized. The maintenance personnel can operate on the ground without climbing up, which improves the safety and maintenance of maintenance. efficiency;

(2)由于检修人员是通过绝缘杆进行操作,在检修工作进行时,可以不用停电,提高供电可靠性,有效维护电力企业的经济利益; (2) Since the maintenance personnel operate through insulating rods, there is no need to cut off the power during the maintenance work, which improves the reliability of power supply and effectively maintains the economic interests of power companies;

(3)由于检修扳手各部分是活动连接的,结构简单,便于拆装和携带。 (3) Since the various parts of the maintenance wrench are movably connected, the structure is simple, and it is easy to disassemble and carry.

附图说明 Description of drawings

下面结合附图和具体实施方式对本实用新型作进一步详细的说明。 Below in conjunction with accompanying drawing and specific embodiment, the utility model is described in further detail.

图1是本实用新型的结构示意图; Fig. 1 is a structural representation of the utility model;

其中,1、第一绝缘拉杆,2、第二绝缘拉杆,3、第一支架,4、第二支架,5、上套头,6、下套头。 Wherein, 1, the first insulating pull rod, 2, the second insulating pull rod, 3, the first bracket, 4, the second bracket, 5, the upper pulley, 6, the lower pulley.

具体实施方式 Detailed ways

如图1所示的实施例可知,本实用新型所述的带电检修扳手,包括用于防止螺栓转动的第一绝缘拉杆1、第一支架3和上套头5,以及用于紧固螺栓的第二绝缘拉杆2、第二支架4和下套头6;所述第一绝缘拉杆1与第一支架3之间、第二绝缘拉杆2与第二支架4之间均通过焊接固定;所述第二支架4与第一支架3之间通过第一支架3上的套管活动套接;所述第一支架3与上套头5之间、第二支架4与下套头6之间均是活动连接。 As can be seen from the embodiment shown in Figure 1, the live overhaul wrench described in the utility model includes a first insulating pull rod 1, a first bracket 3 and an upper sleeve 5 for preventing the bolt from rotating, and a first bolt for fastening the bolt. Two insulating rods 2, the second bracket 4 and the lower sleeve 6; between the first insulating rod 1 and the first bracket 3, between the second insulating rod 2 and the second bracket 4 are all fixed by welding; the second The support 4 and the first support 3 are flexibly socketed through the sleeve on the first support 3; between the first support 3 and the upper sleeve 5, and between the second support 4 and the lower sleeve 6 are all movably connected.

上述第一支架3与上套头5之间通过方接头活动连接,方接头与第一支架3焊接,上套头5与方接头卡接;所述第二支架4与下套头6之间通过方接头活动连接,方接头与第二支架4焊接,下套头6与方接头卡接。 The first bracket 3 and the upper sleeve 5 are movably connected through a square joint, the square joint is welded to the first bracket 3, the upper sleeve 5 is clamped with the square joint; the second bracket 4 and the lower sleeve 6 are connected through a square joint Flexible connection, the square joint is welded to the second bracket 4, and the lower sleeve 6 is clamped with the square joint.

使用上述带电检修扳手进行带电检修的工作过程如下: The working process of using the above-mentioned live inspection wrench for live inspection is as follows:

(1)根据需要紧固或者更换的螺栓型号,选择合适的相应上套头5和下套头6,并将上套头5安装到第一支架3上,将下套头6安装到第二支架4上; (1) According to the type of bolts to be fastened or replaced, select the appropriate corresponding upper sleeve head 5 and lower sleeve head 6, and install the upper sleeve head 5 on the first bracket 3, and install the lower sleeve head 6 on the second bracket 4;

(2)检修人员手持第一绝缘拉杆1,将上套头5靠近待紧固螺栓的上部,并固定不动; (2) The maintenance personnel hold the first insulating pull rod 1, put the upper sleeve head 5 close to the upper part of the bolt to be fastened, and fix it still;

(3)检修人员根据螺栓尺寸,调节扳手开口大小,然后操作第二绝缘拉杆2使下套头6靠近待紧固螺栓的下部; (3) The maintenance personnel adjust the size of the opening of the wrench according to the size of the bolt, and then operate the second insulating rod 2 to make the lower sleeve 6 close to the lower part of the bolt to be tightened;

(4)转动第二绝缘拉杆2将螺栓进行紧固或拆卸。  (4) Turn the second insulating rod 2 to fasten or remove the bolts. the

Claims (2)

1.一种带电检修扳手,其特征在于,包括用于防止螺栓转动的第一绝缘拉杆(1)、第一支架(3)和上套头(5),以及用于紧固螺栓的第二绝缘拉杆(2)、第二支架(4)和下套头(6);所述第一绝缘拉杆(1)与第一支架(3)之间、第二绝缘拉杆(2)与第二支架(4)之间均通过焊接固定;所述第二支架(4)与第一支架(3)之间通过第一支架(3)上的套管活动套接;所述第一支架(3)与上套头(5)之间、第二支架(4)与下套头(6)之间均是活动连接。 1. A live repair wrench, characterized in that it includes a first insulating pull rod (1), a first bracket (3) and an upper sleeve (5) for preventing bolt rotation, and a second insulating rod for tightening bolts Pull rod (2), second bracket (4) and lower sleeve (6); between the first insulating pull rod (1) and the first bracket (3), between the second insulating pull rod (2) and the second bracket (4) ) are fixed by welding; the second bracket (4) and the first bracket (3) are flexibly socketed through the sleeve on the first bracket (3); the first bracket (3) and the upper There are flexible connections between the pulleys (5) and between the second support (4) and the lower pulley (6). 2.根据权利要求1所述的带电检修扳手,其特征在于,所述第一支架(3)与上套头(5)之间通过方接头活动连接,方接头与第一支架(3)焊接,上套头(5)与方接头卡接;所述第二支架(4)与下套头(6)之间通过方接头活动连接,方接头与第二支架(4)焊接,下套头(6)与方接头卡接。 2. The live overhaul wrench according to claim 1, characterized in that, the first bracket (3) and the upper sleeve (5) are movably connected by a square joint, and the square joint is welded to the first bracket (3), The upper sleeve (5) is clamped with the square joint; the second bracket (4) and the lower sleeve (6) are movably connected through the square joint, the square joint is welded to the second bracket (4), and the lower sleeve (6) is connected to the The square connector snaps together.
CN 201220525629 2012-10-15 2012-10-15 Electrified overhauling wrench Expired - Fee Related CN202846443U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220525629 CN202846443U (en) 2012-10-15 2012-10-15 Electrified overhauling wrench

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220525629 CN202846443U (en) 2012-10-15 2012-10-15 Electrified overhauling wrench

Publications (1)

Publication Number Publication Date
CN202846443U true CN202846443U (en) 2013-04-03

Family

ID=47977679

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220525629 Expired - Fee Related CN202846443U (en) 2012-10-15 2012-10-15 Electrified overhauling wrench

Country Status (1)

Country Link
CN (1) CN202846443U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105186365A (en) * 2015-09-21 2015-12-23 国网山东荣成市供电公司 Charged suspension clamp fastener
CN106711840A (en) * 2015-11-12 2017-05-24 国网辽宁省电力有限公司本溪供电公司 Combined tool for ground potential processing insulator string and wire clip falling defect
CN108858019A (en) * 2018-07-19 2018-11-23 广东电网有限责任公司 A kind of Electrified fastening screw device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105186365A (en) * 2015-09-21 2015-12-23 国网山东荣成市供电公司 Charged suspension clamp fastener
CN105186365B (en) * 2015-09-21 2017-11-07 国网山东荣成市供电公司 Powered suspension clamp fastener
CN106711840A (en) * 2015-11-12 2017-05-24 国网辽宁省电力有限公司本溪供电公司 Combined tool for ground potential processing insulator string and wire clip falling defect
CN108858019A (en) * 2018-07-19 2018-11-23 广东电网有限责任公司 A kind of Electrified fastening screw device

Similar Documents

Publication Publication Date Title
CN101428412B (en) Special purpose tools for electric fastening bolt
CN202034506U (en) Lead hanging hook of earth wire
CN202846443U (en) Electrified overhauling wrench
CN105818084B (en) Power transmission and transformation line bolt live dismantling device
CN203233099U (en) A live installation bird repellent tool
CN204382187U (en) A kind of contact net inclined cantilever insulator replacement tool
CN205148170U (en) Electrified fastening bolt instrument of transmission line
CN203218756U (en) A special tool for replacing the operating mechanism box of an isolating switch with electricity
WO2012088988A1 (en) Maintenance tool used for double insulator strings of direct current transmission line
CN204947466U (en) Portable live line working line lifter
CN202039764U (en) Insulating ladder for live working of transformer substation combined buses
CN202034330U (en) Bypass fuse
CN110653741A (en) Tool for electrically fastening clamp bolt in overhead electrified remote control of power transmission line
CN203278145U (en) Commutation device for DC excitation enclosed busbar
CN202622631U (en) Grounding wire hardware fitting bolt fastening wrench
CN210957558U (en) Lifting assistor tool for insulated operating rod
CN210704540U (en) A tool for high-altitude live remote control electric tightening of wire clamp bolts for transmission lines
CN204030448U (en) A kind of electrified fastening pin type insulator nut tool
CN202190022U (en) Upright bottle fastening operating rod
CN203813320U (en) Tools for replacing tension insulator strings of 220kV narrow base tower
CN203352055U (en) Electric pole grounding downlead lifting apparatus
CN208093785U (en) A kind of live adds the device of drainage thread
CN202678551U (en) Novel grounding device for personal security wire
CN103247961A (en) V-shaped pull rod fixture for live working of changing large-tension tension insulator
CN106392969B (en) Livewire work rocking arm spanner

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130403