CN202868048U CN 201220486970 CN201220486970U CN202868048U CN 202868048 U CN202868048 U CN 202868048U CN 201220486970 CN201220486970 CN 201220486970 CN 201220486970 U CN201220486970 U CN 201220486970U CN 202868048 U CN202868048 U CN 202868048U
Authority
CN
China
Prior art keywords
module
piping lane
pipe
galley
steel structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220486970
Other languages
Chinese (zh)
Inventor
陈朝明
杨晓东
黄恒佐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Morimatsu Jiangsu Heavy Industry Co Ltd
Original Assignee
Morimatsu Jiangsu CNOOC Engineering Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Morimatsu Jiangsu CNOOC Engineering Equipment Co Ltd filed Critical Morimatsu Jiangsu CNOOC Engineering Equipment Co Ltd
Priority to CN 201220486970 priority Critical patent/CN202868048U/en
Application granted granted Critical
Publication of CN202868048U publication Critical patent/CN202868048U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to a drawer type modularization steel structure pipe galley system which comprises a pipe galley module. The pipe galley module is a steel structure module forming an independent frame independently, the pipe galley module is connected with the stand columns of a main structure module and pipe galley hanging columns through a plurality of support components, and therefore the pipe galley module and the frame of the main structure module form a whole. A specific connecting structure is that connecting plates are welded on the connecting portions of the stand columns of the main structure module, the pipe galley hanging columns and the support components, the support components and the connecting plates are connected and fixed through column connecting bolts, and the support components and the pipe galley module are connected and fixed through pipe galley module connecting bolts. The steel structure galley system can be separated from a main steel structure module well, and prefabrication, installation and inspection can be carried out to the steel structure frame of the pipe galley system and the pipelines laid on the pipe galley system parallel to the main steel structure module.

Description

A kind of drawer module steel structure piping lane system
Technical field
The utility model right relates to a kind of steel structure piping lane system, particularly a kind of drawer module steel structure piping lane system.
Background technique
Modularization refers to that at the modern industrial engineering special secondary school equipment, pipeline, the electric meter of whole system device are assembled in composition single delivery unit---module in several steel frames that can transport fractionation by certain technological requirement, after all modules are transported to the erecting bed, lifting, in place and be mounted to the device that can bring into play set process function.
Module can relate to the within battery limit piping lane in installation process, the form of the within battery limit piping lane that uses at present is generally directly and main body during welding for steel structure piping lane support together, and such piping lane support generally can be divided into along with the form of topic module overall formula and single-unit formula.For these two kinds of within battery limit piping lanes, its technology is used to get comparative maturity, and the scope of application is also more extensive.But piping lane self is proposed to have of one's own module all the time, this just causes the piping lane steel structure and the pipeline that lays thereon must design, build and install along with the main structure module; And the pipeline on the piping lane has been concentrated more than 70% of whole device district interior conduit often; Thereby caused the pipe laying on the piping lane to be subject to the impact of space, height and other aspect of main body steel structure module; Caused finally that the pipeline on the piping lane must be high-lift operation in the whole device district in installation process, also be subject to simultaneously the impact of main structural framework, and have influence on pipeline installation rate and progress on the piping lane.
Summary of the invention
The technical problem that the utility model right will solve provides a kind of drawer module steel structure piping lane system, can be independent from main body steel structure module steel structure piping lane system preferably so that the piping lane system no matter be its steel structure frame or lay thereon pipeline all can be parallel to main body steel structure module carry out prefabricated, install and check.
In order to solve the problems of the technologies described above, the technical solution of the utility model is: a kind of drawer module steel structure piping lane system, its innovative point is: comprise the piping lane module, described piping lane module is a steel structure module that has separate frame of one's own, its column and piping lane davit by a plurality of rest members and main structure module couples together, thereby becomes as a whole with the framework of main structure module; Concrete linkage structure is: need to be welded to connect plate with rest member joint at main structure module column and piping lane davit, the rest member is connected and fixed by post connecting bolt and connecting plate, and the rest member is connected and fixed by piping lane module connecting bolt and piping lane module.
Further, described piping lane module interior conduit is connected with the piping lane Outer Tube by one section adjustable straight length.
Advantage of the present utility model:
Can prior to connected a plurality of main structure modules carry out pipeline and structure prefabricated, install and check; Before the pre-assembly unit of main body steel structure module whole, first prefabricated pipeline is installed on the piping lane module; After the pre-assembly unit of steel structure is good, directly carry out the installation of piping lane module;
2. the pipeline that lays on the piping lane module can directly carry out on the ground in installation process, has reduced the pipe laying inconvenience that high-lift operation brings, and has improved the Security of workman in work progress;
3. the not impact in acceptor's construction module space of the pipeline that lays on the piping lane module;
4. the pipeline that lays on the piping lane module has reduced because the frequency of crane tool is frequently used in high-lift operation, has reduced the cost of installation process;
5. the steel structure module on the main body frame can be independent of right under this equally, carries out the structure, pipeline, instrument on it, the installation of electric and HVAC airduct;
6. after piping lane module installation in position is in the main structure module, by adjusting straight length modularization piping lane and piping lane Outer Tube are connected again, the pipe fitting of whole modularization piping lane part is compared with traditional piping lane Installation Modes, has reduced widely workload and the time of workman's high-lift operation;
7. break through the size restrictions of individual module, the piping lane that originally was divided in three or four modules can be assembled a large piping lane on the one hand, can reduce the flange quantity that pipe level connects; On the other hand, after the piping lane modularization, reduce the pipeline linkage interface between each module and the adjacent block, so that each independent structure little module only has the interface of connecting tube with piping lane as far as possible, so just reduced the required precision that owner's project field module is installed; Simultaneously, also can reduce the steel using amount of support of pipelines, save the cost of project.
Description of drawings
Fig. 1 is the utility model drawer module steel structure piping lane System Implementation organigram.
Fig. 2 represents the piping lane module is filled to from the main body module side crane phase diagram of module floor face.
Fig. 3 represent with the piping lane module move on to need installation in position under phase diagram on the floorboard.
Fig. 4 represents piping lane is vertically hung designed elevation, and the phase diagram of the good rest member of piping lane is installed.
Fig. 5 is the utility model drawer module steel structure piping lane system and main structure module connection diagram.
Embodiment
As shown in Figure 5, comprise piping lane module 1, rest member 2, main structure module column 3, post connecting bolt 4, connecting plate 5.
Piping lane module 1 is a steel structure module that has separate frame of one's own, and as shown in Figure 1, this separate frame adopts the channel-section steel welding to consist of.Tubing on the steel structure frame of piping lane module 1, instrument, electric and HVAC airduct etc.Piping lane module 1 interior conduit is connected with the piping lane Outer Tube by one section adjustable straight length.
Piping lane module 1 is arranged in the main structure module, by rest member 2 and main structure module column 3.Concrete linkage structure is: need to be welded to connect with the joint of rest member 2 plate 5 at main structure module column 4 and piping lane module davit, rest member 2 sides are connected and fixed by four post connecting bolts 4 and connecting plate 5, and rest member 2 upper surfaces are connected and fixed by a pair of piping lane module connecting bolt and piping lane module 1.
The concrete steps that the utility model piping lane module 1 is installed in the main structure module are:
Shown in Fig. 2,3,4, piping lane module 1 is carried out prefabricated, check prior to the steel structure module on the main structure module and is installed, and lays with its upper a large amount of pipelines, instrument, electric and HVAC airduct and also can carry out simultaneously prefabricated, installation;
Piping lane module 1 installs on the ground, and this piping lane module 1 usefulness loop wheel machine is hung flooring height with piping lane module 1 floor of living in to it;
Piping lane module 1 from the outside of main structure modular platform 6 along horizontal shift-in under the position that the piping lane module need to be installed to;
Piping lane module 1 is promoted vertically upward above 150 millimeters that need setting height(from bottom), in order to piping lane module rest member 2 is installed;
Connecting plate 5 welding on each piping lane module rest member 2 and main structure module column 3, the piping lane module davit is good by post connecting bolt 4 connects;
Piping lane module 1 is put down, allow it fall on the required piping lane module rest member 2 of piping lane module 1, and aim at the connecting bolt hole, by piping lane module connecting bolt piping lane module 1 and rest member 2 are coupled together.

Claims (2)

1. drawer module steel structure piping lane system, it is characterized in that: comprise the piping lane module, described piping lane module is a steel structure module that has separate frame of one's own, its column and piping lane davit by a plurality of rest members and main structure module couples together, thereby becomes as a whole with the framework of main structure module; Concrete linkage structure is: need to be welded to connect plate with rest member joint at main structure module column and piping lane davit, the rest member is connected and fixed by post connecting bolt and connecting plate, and the rest member is connected and fixed by piping lane module connecting bolt and piping lane module.
2. drawer module steel structure piping lane according to claim 1 system, it is characterized in that: described piping lane module interior conduit is connected with the piping lane Outer Tube by one section adjustable straight length.
CN 201220486970 2012-09-24 2012-09-24 Drawer type modularization steel structure pipe galley system Expired - Fee Related CN202868048U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220486970 CN202868048U (en) 2012-09-24 2012-09-24 Drawer type modularization steel structure pipe galley system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220486970 CN202868048U (en) 2012-09-24 2012-09-24 Drawer type modularization steel structure pipe galley system

Publications (1)

Publication Number Publication Date
CN202868048U true CN202868048U (en) 2013-04-10

Family

ID=48034768

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220486970 Expired - Fee Related CN202868048U (en) 2012-09-24 2012-09-24 Drawer type modularization steel structure pipe galley system

Country Status (1)

Country Link
CN (1) CN202868048U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113404304A (en) * 2021-02-05 2021-09-17 海洋石油工程(青岛)有限公司 Process for building ultra-large FPSO pipe gallery module

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113404304A (en) * 2021-02-05 2021-09-17 海洋石油工程(青岛)有限公司 Process for building ultra-large FPSO pipe gallery module

Similar Documents

Publication Publication Date Title
CN101200959B (en) Multi-point pushing cumulative-gliding construction method for steel roof truss
CN203247859U (en) Alignment device for butt joint perpendicularity of large steel columns
CN103195256B (en) Hanging column type steel structure jig frame construction method
CN105604185B (en) A kind of earthquake-resistant structure support connection structure and attaching method thereof
EP2434188A2 (en) Structural duct bearing system
CN105586833B (en) Stiff skeleton steel reinforcement cage global formation large-scale cast-in-place tall pier and thin wall construction method
CN201417657Y (en) Installation device of indoor transformer
CN202810173U (en) Mounting and construction platform for steel lining bracket and circular crane track girder of nuclear power plant
CN205242885U (en) Lightweight concrete prefabricated staircase connection structure
CN109763835A (en) A kind of shield machine reception steel platform
CN102691412B (en) Prefabricated frame structure connection supporting template with adjustable vertical height
CN204476416U (en) The simple and easy sliding form apparatus of a kind of vertical shaft concrete lining
CN103663302B (en) L-type portal installation frame
CN202868048U (en) Drawer type modularization steel structure pipe galley system
CN206580492U (en) The removable lifting positioning apparatus of piping lane pipeline
CN103628692A (en) Floor beam mounting bracket and use and construction method thereof
CN103174300B (en) Viscous damper installation construction method
CN104499728A (en) Absorbing tower horizontal moving device and construction method thereof
CN206093192U (en) Novel comprehensive pipe support
CN203640313U (en) Floor beam installing support
CN204531180U (en) Control the stiff skeleton of large-scale component reinforcing bar binding precision
CN104209724B (en) A kind of derrick assembles with combination steelframe
CN205330033U (en) Mixed structure prefabricated staircase installs system
CN208155335U (en) Adhesion type measures bracket
CN201810878U (en) Bridge type bracket

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: MORIMATSU (JIANGSU) HEAVY INDUSTRY CO., LTD.

Free format text: FORMER OWNER: SENSONG (JIANGSU) OFFSHORE OIL ENGINEERING EQUIPMENT CO., LTD.

Effective date: 20140306

COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 226500 NANTONG, JIANGSU PROVINCE TO: 226532 NANTONG, JIANGSU PROVINCE

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20140306

Address after: 226532, room 319, building 306, spring garden, Changjiang town (Rugao port area), Nantong, Jiangsu, Rugao

Patentee after: Morimatsu (Jiangsu) Heavy Industry Co., Ltd.

Address before: 226500, room 319, building 306, spring garden, Changjiang town (Rugao port area), Nantong, Jiangsu, Rugao

Patentee before: Morimatsu (Jiangsu) CNOOC Engineering Equipment Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130410

Termination date: 20160924