- Publication number
- CN202733170U CN202733170U CN 201220415364 CN201220415364U CN202733170U CN 202733170 U CN202733170 U CN 202733170U CN 201220415364 CN201220415364 CN 201220415364 CN 201220415364 U CN201220415364 U CN 201220415364U CN 202733170 U CN202733170 U CN 202733170U
- Authority
- CN
- China
- Prior art keywords
- fixedly connected
- mounting
- supporting steel
- steel plate
- crossbeam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Sewage (AREA)
Abstract
The utility model discloses a pipeline mounting machine which comprises a frame which is formed by assembling a cross beam and supporting tripods respectively positioned on lower portions at two ends of the cross beam. The cross beam is provided with a movable pulley device, the lower portion of the movable device is fixedly connected with a main chain block, and small chain blocks are fixedly connected onto the supporting tripods. The pipeline mounting machine can be assembled on the spot according to needs and is convenient for transport, flexible and light, inconvenience in use of a crane for coordinative mounting is omitted, and mounting of reinforced concrete drainage pipes can be directly realized at the bottom of a trench. Mounting of the drainage pipes is low in lifting height, clear in operation sight, small in manual leading chain action amplitude and convenient in interface mounting of the drainage pipe, so that safety coefficient of project construction is improved, construction period is greatly shortened, cost of crane machine team is saved, and huge convenience is brought for mounting construction of the reinforced concrete drainage pipes. The pipeline mounting machine can be used for mounting other large-sized pipelines and is suitable for popularization and application.
Description
Technical field
The utility model relates to a kind of pipeline fitting machine, relates in particular to a kind of installation heavy caliber (pipeline fitting machine of concrete reinforced pipe of 0.8m~2.0m).
Background technique
Along with the continuous quickening of urbanization process, the town road that need to build is also more and more.In the prior art, town road drainage works when construction since the reinforced concrete sewer pipe that lays from great, the installation difficulty is large, labor intensity is high, machinery and manpower consumption amount are large, has brought very large inconvenience for the engineering construction process.During engineering construction, generally all adopt crane to cooperate and install, not only the construction period is long, the mechanical one-shift expense is high, and poor safety performance.
In the past, concrete drain tile was installed and is all relied on omnidistance cooperation of motorised crane to install, and secondary to lift waste pipe along pipe trench to bottom of trench, and operating distance was far away, and the hoistman sight line is unintelligible, can only blindly look operation or rely on signal command operation, poor stability.
The model utility content
The purpose of this utility model be to provide a kind of conveniently moving, simple to operate, Safety performance is strong, can effectively shorten the pipeline fitting machine of construction period.
For achieving the above object, the technological scheme taked of the utility model is:
A kind of pipeline fitting machine, comprise support body, described support body is assembled by crossbeam and the support triangle frame that lays respectively at bottom, crossbeam two ends, and described crossbeam is provided with the mobile pulley device, the bottom of described shifter is fixedly connected with main jack, is fixedly connected with little jack on the described support triangle frame.
Described mobile pulley device comprises two block plates that are oppositely arranged, and the top of two block plates is fixedly connected with the top steel plate, is provided with two groups of pulleys between the two block plate tops, is provided with coupling shaft between the two block plate bottoms.
Described support triangle frame comprises the second supporting steel plate, and the bottom of described the second supporting steel plate is fixedly connected with two supporting steel pipes, is provided with the first stiffening rib and the second stiffening rib between the described supporting steel pipe, and the bottom of described supporting steel pipe is respectively equipped with the sliding roller in bottom.
The lower position at described crossbeam two ends is fixedly connected with respectively the first supporting steel plate, and described the first supporting steel plate is fixedly connected with the second supporting steel plate.
The end, two ends, the left and right sides of described crossbeam is respectively equipped with the sidepiece pulley, and an end of described little jack is fixedly connected with the second stiffening rib, and the other end is fixedly connected with the top steel plate of shifter 2 by wire rope, sidepiece pulley.
Be provided with the 3rd stiffening rib between described the first stiffening rib and the crossbeam.
The pipeline fitting machine that the utility model provides can carry out Assembling as required, convenient transportation, and lithe has saved crane and has cooperated the inconvenience of installing, and can directly carry out at bottom of trench the installation of reinforced concrete sewer pipe.And sling height is low, the operation sight line is clear when fixing a drainpipe, manually guide chain movement range interface little, drainage pipe is easy for installation, improved the safety coefficient of engineering construction, greatly shortened the construction period, saved the crane One-Shift Costs, for the installation of reinforced concrete sewer pipe brings great convenience.This pipeline fitting machine can also be installed other large-scale pipelines, is suitable for applying.
Description of drawings
Fig. 1 is structural representation of the present utility model.
Among the figure, 1-crossbeam, 2-mobile pulley device, 3-the first supporting steel plate, 4-the second supporting steel plate, the 5-supporting steel pipe, 6-the first stiffening rib, 7-the second stiffening rib, 8-the 3rd stiffening rib, the sliding roller in 9-bottom, 10-sidepiece pulley, the little jack of 11-, 12-wire rope, 13-master's jack, 14-top steel plate.
Embodiment
Below in conjunction with specific embodiment and accompanying drawing thereof, the utility model is described in further detail, but mode of execution of the present utility model is not limited to this.
As shown in Figure 1, the pipeline fitting machine that the utility model provides comprises support body, and support body is by 20 of a 3m length
#I-steel master load bearing cross beam 1 assembles with the support triangle frame that lays respectively at bottom, crossbeam 1 two ends.Mobile pulley device 2 is installed on the crossbeam 1, mobile pulley device 2 comprises two block plates that are oppositely arranged, the welded top of two block plates has top steel plate 14, be connected with two groups of pulleys with bolt between the two block plate tops, connect with coupling shaft between the two block plate bottoms, mobile pulley device 2 can carry out the slip of position, the left and right sides along crossbeam 1.The bottom of shifter 2 is connected with 8 tons of main jacks 13 with bolt.
The support triangle frame comprises the second supporting steel plate 4, the bottom of the second supporting steel plate 4 is welded with two φ, 80 supporting steel pipes 5, be welded with the first stiffening rib 6 and the second stiffening rib 7 between two supporting steel pipes 5, the first stiffening rib 6 and the second stiffening rib 7 are steel pipe, and their effect is in order to strengthen the enabling capabilities of support triangle frame.The bottom of four supporting steel pipes 5 is welded with respectively the sliding roller 9 in bottom.
Being connected with the 3rd stiffening rib 8, the three stiffening ribs 8 with bolt between the first stiffening rib 6 and the crossbeam 1 is 10
#Channel-section steel.The lower position at crossbeam 1 two ends welds respectively the first supporting steel plate 3 of one 350 * 250 * 20, the hole that 4 φ 20 are bored respectively at the 40mm place, four angular distance limits of the second supporting steel plate 4 of the first supporting steel plate 3 and support triangle frame, connect with φ 18 high-strength bolts, thereby can carry out at the scene the assembling of this pipeline fitting machine.
Be welded with respectively an end of 10,3 tons of little jacks 11 of sidepiece pulley and 7 colligations of the second stiffening rib in the end, two ends, the left and right sides of crossbeam 1 together, the other end is fixedly connected with the top steel plate 14 of shifter 2 by wire rope 12, wire rope above the sidepiece pulley 10.Sidepiece pulley 10 can prevent the wearing and tearing of wire rope 12, reduces resistance, and then by straining or loosening the 3 tons little jacks 11 in both sides, control drainage pipe move left and right is to accurate location.
According to the difference of the waste pipe caliber of installing, can adjust flexibly the strong point on the crossbeam 1 of being positioned at of the length of I-steel crossbeam 1 and the 3rd stiffening rib 8.When the waste pipe of pipe laying caliber≤1.2m, it is 16 of 3.0m that crossbeam 1 adopts length
#I-steel, the 3rd stiffening rib 8 adopts short diagonal brace.When the pipe laying caliber was the waste pipe of 1.2m~2.0m, it was 20 I-steel of 3.5m that crossbeam 1 adopts length, and the 3rd stiffening rib 8 lengthens, and changes the strong point, adopts long diagonal brace.
Process at the construction and installation waste pipe is as follows:
1, from tube mill ship concrete pipe directly with crane from disposable lower pipe on the transport vehicle to pipe duct the bottom;
2, according to the width of pipe duct bottom, place respectively 16 of a 6m length in the both sides of drainage pipe
#Channel-section steel is as track, and track is between the waste pipe of the waste pipe that has been in place and pre-installation, and the sliding roller 9 in bottom can roll along groove steel rail is sliding, and artificial the promotion is transported to drainage pipe the position of pre-installation waste pipe.
3, tie up waste pipe with wire rope, utilize the leading chain 12 of 8t of pipeline fitting machine that waste pipe is sling apart from ground 20cm place, or reach the setting height(from bottom) place.The installation of waste pipe, the control of upper-lower position are by the lifting of 8 tons of main jacks 13 of this load-bearing and loosen to carry out, make waste pipe be mounted to accurate location.
4, utilize the little guide chain of 3t to adjust position, the left and right sides and the axis coinciding that fixes a drainpipe, promote the pipeline fitting machine and make waste pipe move to mounted mouth of pipe 3cm place.
5, adjust the pre-installation waste pipe about and upper-lower position, waste pipe is in place, promote the sliding roller in bottom of pipeline fitting machine, make drain interface tight, reach final mounting point.
6, install concrete pad, fix waste pipe, unclamp leading chain 12 and be bundled in wire rope on the waste pipe.Then the movement pipeline fitting machine is installed next joint waste pipe by said procedure, the like, until install all waste pipes.
Whole installation process has been saved crane and has been cooperated the operation of installing, and directly installed by the pipeline fitting machine at bottom of trench, and bottom of trench construction lifting position is low, distance is little, and Safety performance improves greatly.
In as installed, on-the-spot need to 5 operators the construction.During the hoisting steel reinforced concrete drainage pipe, two human wire rope are firm with the waste pipe colligation, and other three people move this pipeline fitting machine to the position of pre-installation reinforced concrete sewer pipe.Utilize main jack lifting waste pipe extremely apart from ground 20cm place, then a people holds waste pipe, all the other four-players are at the corner location of this pipeline fitting machine support triangle frame, utilize the sliding roller in support triangle frame bottom, promote this pipeline fitting machine and waste pipe and together move to the interface position place, adjust the interface gaps of waste pipe, package the water proof rubber circle.Again utilize main jack and wire rope pulling waste pipe, make the mouth of pipe seam of waste pipe tight, then line is proofreaied and correct, strict control center line and absolute altitude, upstream install from the downstream, and with center line and the elevation of center collimation method or sideline method control drainage pipe, reach code requirement.
Above-described only is preferred embodiment of the present utility model, does not limit to the utility model.Should be understood that for the person of ordinary skill of the art, under technology enlightenment provided by the utility model, can also make other equivalent modifications and improvement, all can realize the purpose of this utility model, all should be considered as protection domain of the present utility model.
Claims (6)
1. pipeline fitting machine, it is characterized in that, comprise support body, described support body is assembled by crossbeam (1) and the support triangle frame that lays respectively at crossbeam (1) bottom, two ends, described crossbeam (1) is provided with mobile pulley device (2), the bottom of described shifter (2) is fixedly connected with main jack (13), is fixedly connected with little jack (11) on the described support triangle frame.
2. a kind of pipeline fitting machine according to claim 1, it is characterized in that, described mobile pulley device (2) comprises two block plates that are oppositely arranged, the top of two block plates is fixedly connected with top steel plate (14), be provided with two groups of pulleys between the two block plate tops, be provided with coupling shaft between the two block plate bottoms.
3. a kind of pipeline fitting machine according to claim 1, it is characterized in that, described support triangle frame comprises the second supporting steel plate (4), the bottom of described the second supporting steel plate (4) is fixedly connected with two supporting steel pipes (5), be provided with the first stiffening rib (6) and the second stiffening rib (7) between the described supporting steel pipe (5), the bottom of described supporting steel pipe (5) is respectively equipped with the sliding roller (9) in bottom.
4. a kind of pipeline fitting machine according to claim 1 is characterized in that, the lower position at described crossbeam (1) two ends is fixedly connected with respectively the first supporting steel plate (3), and described the first supporting steel plate (3) is fixedly connected with the second supporting steel plate (4).
5. a kind of pipeline fitting machine according to claim 1, it is characterized in that, the end, two ends, the left and right sides of described crossbeam (1) is respectively equipped with sidepiece pulley (10), one end of described little jack (11) is fixedly connected with the second stiffening rib (7), and the other end is fixedly connected with the top steel plate (14) of shifter (2) by wire rope (12), sidepiece pulley (10).
6. a kind of pipeline fitting machine according to claim 3 is characterized in that, is provided with the 3rd stiffening rib (8) between described the first stiffening rib (6) and the crossbeam (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220415364 CN202733170U (en) | 2012-08-21 | 2012-08-21 | Pipeline mounting machine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220415364 CN202733170U (en) | 2012-08-21 | 2012-08-21 | Pipeline mounting machine |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202733170U true CN202733170U (en) | 2013-02-13 |
Family
ID=47658869
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201220415364 Expired - Fee Related CN202733170U (en) | 2012-08-21 | 2012-08-21 | Pipeline mounting machine |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202733170U (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104627849A (en) * | 2015-02-03 | 2015-05-20 | 中建五局工业设备安装有限公司 | Hoisting equipment and hoisting method for hoisting inner courtyard pipeline |
CN104831941A (en) * | 2015-04-27 | 2015-08-12 | 湖北精工工业建筑系统有限公司 | Steel structure product construction trolley and construction method |
CN105110197A (en) * | 2015-07-30 | 2015-12-02 | 交通运输部天津水运工程科学研究所 | Overhead travelling crane for mounting laboratory artificial armor block |
CN106826081A (en) * | 2017-01-22 | 2017-06-13 | 中国十七冶集团有限公司 | A kind of major diameter corrugated pipe pipeline counterpart installation method |
CN107419793A (en) * | 2017-05-27 | 2017-12-01 | 南昌诺义弘科技有限公司 | A kind of burial equipment of subsoil drain |
CN110040620A (en) * | 2019-04-23 | 2019-07-23 | 上海外高桥造船有限公司 | A kind of bracket and its application method |
CN111042163A (en) * | 2019-12-31 | 2020-04-21 | 上海祥曙科技发展中心 | Large-diameter polyethylene plastic pipeline installation structure and construction method |
CN111795205A (en) * | 2020-07-22 | 2020-10-20 | 武汉市年华管业有限公司 | Concrete pipeline joint strengthening treatment method |
CN112320611A (en) * | 2020-11-30 | 2021-02-05 | 中建一局集团建设发展有限公司 | Overweight assembled prefabricated staircase hoisting device and construction method |
CN112856038A (en) * | 2019-11-27 | 2021-05-28 | 中国石油天然气集团有限公司 | Pipeline assembly device |
-
2012
- 2012-08-21 CN CN 201220415364 patent/CN202733170U/en not_active Expired - Fee Related
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104627849A (en) * | 2015-02-03 | 2015-05-20 | 中建五局工业设备安装有限公司 | Hoisting equipment and hoisting method for hoisting inner courtyard pipeline |
CN104831941A (en) * | 2015-04-27 | 2015-08-12 | 湖北精工工业建筑系统有限公司 | Steel structure product construction trolley and construction method |
CN105110197A (en) * | 2015-07-30 | 2015-12-02 | 交通运输部天津水运工程科学研究所 | Overhead travelling crane for mounting laboratory artificial armor block |
CN106826081A (en) * | 2017-01-22 | 2017-06-13 | 中国十七冶集团有限公司 | A kind of major diameter corrugated pipe pipeline counterpart installation method |
CN106826081B (en) * | 2017-01-22 | 2019-02-26 | 中国十七冶集团有限公司 | A kind of major diameter corrugated pipe pipeline counterpart installation method |
CN107419793A (en) * | 2017-05-27 | 2017-12-01 | 南昌诺义弘科技有限公司 | A kind of burial equipment of subsoil drain |
CN110040620A (en) * | 2019-04-23 | 2019-07-23 | 上海外高桥造船有限公司 | A kind of bracket and its application method |
CN110040620B (en) * | 2019-04-23 | 2020-12-22 | 上海外高桥造船有限公司 | Bracket and using method thereof |
CN112856038A (en) * | 2019-11-27 | 2021-05-28 | 中国石油天然气集团有限公司 | Pipeline assembly device |
CN111042163A (en) * | 2019-12-31 | 2020-04-21 | 上海祥曙科技发展中心 | Large-diameter polyethylene plastic pipeline installation structure and construction method |
CN111795205A (en) * | 2020-07-22 | 2020-10-20 | 武汉市年华管业有限公司 | Concrete pipeline joint strengthening treatment method |
CN111795205B (en) * | 2020-07-22 | 2022-04-12 | 武汉市年华管业有限公司 | Concrete pipeline joint strengthening treatment method |
CN112320611A (en) * | 2020-11-30 | 2021-02-05 | 中建一局集团建设发展有限公司 | Overweight assembled prefabricated staircase hoisting device and construction method |
CN112320611B (en) * | 2020-11-30 | 2023-07-25 | 中建一局集团建设发展有限公司 | Overweight assembled prefabricated stair hoisting device and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202733170U (en) | Pipeline mounting machine | |
CN102061927B (en) | Tunnel waterproof material laying equipment and method | |
CN203334730U (en) | Split mounting type steel-structure movable workshop in construction site | |
CN103821087B (en) | Prefabricated bridge Steel Space pipe concrete truss combination beams and construction method | |
CN201884037U (en) | Tunnel waterproof material layering device | |
CN209144864U (en) | Underground pipe gallery tube coupling assembly equipment | |
CN109987546B (en) | Self-propelled pipeline transportation installation vehicle in corridor and construction method thereof | |
CN103726421A (en) | Height and span adjustable track paver for metro construction | |
CN215908537U (en) | Water supply and drainage pipeline optimizes laying device | |
CN103123016A (en) | Construction method for laying gas pipelines along bridge | |
CN107476334B (en) | Prefabricated pipe joint assembling equipment and construction method thereof | |
CN204691326U (en) | Multifunctional mobile component processing plant | |
CN202560321U (en) | Shield split starting pipeline synchronous moving device | |
CN208563380U (en) | A kind of self-propelled pipe gallery plate device | |
CN203684019U (en) | Height and span adjustable track laying machine for subway construction | |
CN209601099U (en) | Buried pipeline transloading equipment | |
CN215249228U (en) | Simple large-scale pipeline installation adjusting device | |
CN208345620U (en) | Light grade penstock mounting operation platform | |
CN215862027U (en) | Large-diameter concrete pipeline (PCCP) laying and installing machine | |
CN215215042U (en) | Inner pipe-penetrating pushing moving mechanism | |
CN215763629U (en) | Large-diameter drainage pipeline sliding traction mounting system | |
CN205934962U (en) | A system of sliding for underground pipe gallery cast -in -situ construction | |
CN212292494U (en) | Portal frame | |
CN204941564U (en) | Subway tunnel narrow spacing leaves the right or normal track row gate-type lining cutting bench frame apparatus | |
CN211645930U (en) | Tunnel inverted arch construction trestle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130213 Termination date: 20170821 |