CN209601099U CN201920096874.XU CN201920096874U CN209601099U CN 209601099 U CN209601099 U CN 209601099U CN 201920096874 U CN201920096874 U CN 201920096874U CN 209601099 U CN209601099 U CN 209601099U
Authority
CN
China
Prior art keywords
vertical
bar
guide rail
horizontal
movable stand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920096874.XU
Other languages
Chinese (zh)
Inventor
高洪顺
李龙锦
焦志伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Tongchengda Water Construction Co Ltd
Original Assignee
Beijing Tongchengda Water Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Tongchengda Water Construction Co Ltd filed Critical Beijing Tongchengda Water Construction Co Ltd
Priority to CN201920096874.XU priority Critical patent/CN209601099U/en
Application granted granted Critical
Publication of CN209601099U publication Critical patent/CN209601099U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of buried pipeline transloading equipments, belong to buried pipeline installation apparatus field, its key points of the technical solution are that including two guide rails for being fixed on pipe trench bottom surface and being parallel to each other, the movable stand moved along rail length direction is compressed on guide rail, there are four movable stand settings, and movable stand is symmetrically disposed on two-by-two on two guide rails;The rolling mechanism for driving movable stand mobile in guide rail surface is provided on movable stand;The end connection of symmetrically arranged two liftings cucurbit on two guide rails;It is removably connected with cross bar between two movable stands in rail length direction, is removably connected with vertical pole between two movable stands being symmetrically disposed on two guide rails.The lifting precision of existing equipment lower, inconvenient for use problem when the utility model solves buried pipeline installation.

Description

Buried pipeline transloading equipment
Technical field
The utility model relates to buried pipelines to install apparatus field, in particular to a kind of buried pipeline transloading equipment.
Background technique
Transport vehicle of the buried pipeline as water, oil, gas, one of critical facility of ground surface works.In municipal works, water conservancy In engineering, construction and metallurgical industry Pipe installing, it is frequently run onto the construction operation of buried pipeline.Existing pipe trench pipeline is applied Work mode is usually to be lifted duct segments to pipe trench using large-scale crane, then by pipeline assembly welding, preservative treatment, this is applied Work mode is constructed, and flexible, lifting is quick.
Authorization Notice No. is that the Chinese utility model patent of CN207192614U discloses a kind of pipe trench pipeline transfer carriage, is wrapped At least two door type frames are included, door type frame includes pedestal, column, hoisting beam and jack, and pedestal is set to the two sides of door type frame, column It is set on pedestal, hoisting beam is erected on above two heel posts, is had crossbeam sliding rail on hoisting beam, is provided with down on crossbeam sliding rail Chain;Door type frame is reserved at least between a wing base and pipe trench across being arranged in above pipe trench and each door type frame is axially aligned There is the spacing for placing pipeline.
The lifting stability that above scheme is used for the inaccessiable spatially band of big machinery is strong, precision is high, capable of hoisting Long pipeline is filled, is conducive to pipeline on ground and carries out assembled welding and preservative treatment, but when pipe trench depth is larger, above scheme Middle jack is too long, and lifting precision is lower, inconvenient for use.
Utility model content
The purpose of this utility model is to provide a kind of buried pipeline transloading equipments, have and carry out deeper pipe trench inner connection tube Between the advantages of accurately installing.
The above-mentioned technical purpose of the utility model has the technical scheme that a kind of buried pipeline transhipment Equipment has been compressed on the guide rail and has been moved along rail length direction including two guide rail for being fixed on pipe trench bottom surface and being parallel to each other Dynamic movable stand, there are four the movable stand settings, and the movable stand is symmetrically disposed on two-by-two on two guide rails;The movable stand On be provided with the rolling mechanism for driving movable stand mobile in guide rail surface;
The movable stand includes vertical bar, and the vertical bar is fixedly connected with brace far from one end of guide rail, is consolidated on the brace Equipped with the bottom bar fixed with vertical bar, the bottom bar is slided along rail length direction;Fixed link, institute are respectively fixed on the vertical bar Fixed link is stated between symmetrically arranged two vertical bars on two guide rails, lifting cucurbit is fixed in the fixed link;
The end connection of symmetrically arranged two liftings cucurbit on two guide rails;
It is removably connected with cross bar between two movable stands in the rail length direction, is symmetrically disposed on two institutes It states and is removably connected with vertical pole between two on guide rail movable stands.
By using above-mentioned technical proposal, by guide rail laying and pipe trench bottom surface, by two liftings symmetrically arranged on guide rail Chain sling end connection on cucurbit, chain sling is sheathed on the outside of the connecting tube for needing to carry in pipe trench, then starting lifting cucurbit, Chain sling on lifting cucurbit slings connecting tube, and rolling mechanism drives movable stand mobile in guide rail surface, until movable stand drives Connecting tube is moved to Hoisting Position, and the chain sling lifted on cucurbit is put down, and realizes the installation between connecting tube;Cross bar and vertical pole with Movable stand is detachably connected, and the cross bar and vertical pole of different length is easy to use, to adapt to the company of a variety of different-diameters and length Adapter tube, and be readily transported after cross bar, vertical pole and movable stand disassembly.
The utility model is further arranged to: the cross bar includes detachable with two vertical bars in rail length direction respectively The horizontal outer bar and horizontal interior bar of connection, the horizontal outer bar and horizontal interior bar are respectively U-lag steel, and the horizontal interior bar is backwards to one end of vertical bar Being embedded in horizontal outer bar contradicts the lateral surface of horizontal interior bar and the medial surface of horizontal outer bar, is equipped in the horizontal interior bar of insertion in the horizontal outer bar Horizontal connection bolt, spiral is connected with horizontal attaching nut on the horizontal connection bolt.
By using above-mentioned technical proposal, horizontal attaching nut is rotated from horizontal connection bolt after removing, by horizontal connection spiral shell Bolt is removed from horizontal outer bar and horizontal interior bar, mobile horizontal interior bar, and horizontal interior bar adjusts in horizontal outer bar and cross along horizontal outer rod outer surface sliding Horizontal attaching nut rotation is set to horizontal connection bolt by the horizontal horizontal outer bar of connection screw bolt passes and horizontal interior bar by the relative position of bar On horizontal outer bar and horizontal interior bar compressed into connection.
The utility model is further arranged to: the vertical pole includes being detachably connected with two vertical bars in rail length direction Vertical outer bar and vertical interior bar, the vertical outer bar and vertical interior bar are respectively U-lag steel, the vertical interior bar backwards to vertical bar one end be embedded in Vertical outer bar contradicts the lateral surface of vertical interior bar and the medial surface of vertical outer bar, is equipped in the vertical outer bar vertical in the vertical interior bar of insertion Bolt is connected, spiral is connected with vertical attaching nut on the vertical connection bolt.
By using above-mentioned technical proposal, vertical attaching nut is rotated from vertical connection bolt after removing, by vertical connection spiral shell Bolt is removed from vertical outer bar and vertical interior bar, mobile vertical interior bar, indulges interior bar in indulge outer rod outer surface sliding, adjusting vertical outer bar and indulging Vertical connection screw bolt passes are then indulged outer bar and vertical interior bar by the relative position of bar, and vertical attaching nut rotation is set to vertical connection Vertical outer bar and vertical interior bar are compressed into connection on bolt.
The utility model is further arranged to: being connected separately on two vertical bars being symmetrically disposed on two guide rails The axis of transmission shaft, two transmission shafts is identical, and connecting rod, two connecting rods are removably connected on the transmission shaft Between be fixed with push rod.
By using above-mentioned technical proposal, when movable stand is moved near Pipe installing position, by connecting rod and transmission After axis connection, push rod is pushed, push rod drives movable stand to move along guide rail surface, the accurate position for adjusting movable stand upper connector, Convenient for the installation between connecting tube.
The utility model is further arranged to: the rolling mechanism includes being set to bottom bar along rail length direction both ends Idler wheel, lateral surface and the guide rail surface of the idler wheel compress, and the driving motor being fixed on movable stand is connected on the idler wheel.
By using above-mentioned technical proposal, driving motor drives idler wheel rotation, and idler wheel is mobile in guide rail surface, to drive Movable stand is moved along guide rail surface, realizes connecting tube in the movement in pipe trench.
The utility model is further arranged to: the idler wheel is ladder wheel, and the idler wheel includes the support pressed on guide rail Column and the limited post being fixed on support column, the surface of the limited post towards support column contacts at two opposite tables of guide rail Face.
By using above-mentioned technical proposal, movement that the idler wheel between two guide rails can make movable stand more stable.
The utility model is further arranged to: the guide rail is I-steel.
By using above-mentioned technical proposal, I-steel structure is more stable, and making guide rail, the service life is longer.
The utility model is further arranged to: being removably connected with reinforcing rod between the adjacent vertical pole and vertical bar.
By using above-mentioned technical proposal, reinforcing rod can improve the structural strength connected between movable stand, improve movable stand Safety in utilization prolong its service life simultaneously.
In conclusion the utility model has the following beneficial effects:
1, guide rail laying and pipe trench bottom surface are hung symmetrically arranged two on guide rail by using above-mentioned technical proposal The chain sling end connection on cucurbit is filled, chain sling is sheathed on the outside of the connecting tube for needing to carry in pipe trench, then starting lifting calabash Reed, the chain sling lifted on cucurbit sling connecting tube, and rolling mechanism drives movable stand mobile in guide rail surface, until movable stand band Dynamic connecting tube is moved to Hoisting Position, and the chain sling lifted on cucurbit is put down, and realizes the installation between connecting tube;Cross bar and vertical pole It is detachably connected with movable stand, is easy to use the cross bar and vertical pole of different length, to adapt to a variety of different-diameters and length Connecting tube, and be readily transported after cross bar, vertical pole and movable stand disassembly;
2, when movable stand is moved near Pipe installing position, after connecting rod and transmission axis connection, push rod is pushed, is pushed away Bar drives movable stand to move along guide rail surface, the accurate position for adjusting movable stand upper connector, convenient for the installation between connecting tube;
3, the idler wheel is ladder wheel, and the idler wheel includes the support column pressed on guide rail and the limit that is fixed on support column Position column, the surface of the limited post towards support column contacts at two opposite surfaces of guide rail.
Detailed description of the invention
Fig. 1 is the using state structure diagram of embodiment;
Fig. 2 is the overall structure diagram of embodiment;
Fig. 3 is the structural schematic diagram of rolling mechanism in embodiment.
In figure, 1, guide rail;2, movable stand;21, vertical bar;22, brace;23, bottom bar;24, fixed link;25, reinforcing rod;3, it hangs Fill cucurbit;4, cross bar;41, horizontal outer bar;42, horizontal interior bar;5, vertical pole;51, outer bar is indulged;52, interior bar is indulged;6, adjustment mechanism;61, it passes Moving axis;62, connecting rod;63, push rod;7, rolling mechanism;71, idler wheel;72, driving motor;8, connecting tube;9, pipe trench.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.The wherein identical attached drawing of identical components Label indicates.
Embodiment 1
A kind of buried pipeline transloading equipment, as shown in Figure 1, including making to be bolted to 9 bottom surface of pipe trench and being parallel to each other Two guide rails 1, two guide rails 1 are located in the same horizontal plane, and guide rail 1 is to use track made of I-steel.It is supported on guide rail 1 It is pressed with the movable stand 2 moved along 1 length direction of guide rail, altogether there are four settings, movable stand 2 is symmetrical arranged movable stand 2 two-by-two respectively In on two guide rails 1.
As shown in Fig. 2, movable stand 2 includes the vertical bar 21 for the I-steel support that length is arranged along the vertical direction, vertical bar 21 One end far from guide rail 1 is fixedly connected with brace 22, and the angle between the center line and horizontal plane of brace 22 is 30 degree, brace 22 On be welded with vertical bar 21 weld bottom bar 23, bottom bar 23 in level along 1 length direction of guide rail be arranged.
As shown in Figures 2 and 3, the rolling mechanism 7 for driving movable stand 2 mobile in 1 surface of guide rail is provided on movable stand 2; Rolling mechanism 7 includes the driving motor 72 being connected on vertical bar 21 using screw, uses shaft coupling on the output end of driving motor 72 Device is connected with the axis of rolling, rolls the bearing that outer shaft sleeve is equipped on insertion vertical bar 21, and axis of rolling outer sheath is equipped with idler wheel 71, idler wheel 71 For ladder wheel, idler wheel 71 includes side and 1 upper surface of the guide rail support column compressed and the limited post being wholely set with support column, limit Column is coaxial with support column and the diameter of limited post is greater than support column, and the surface of limited post towards support column contacts at two guide rails, 1 phase Pair surface.
It is removably connected with cross bar 4 as shown in Fig. 2, being located between two movable stands 2 of 1 length direction of guide rail, cross bar 4 wraps The horizontal outer bar 41 and horizontal interior bar 42 being fixed on respectively using screw on two vertical bars 21 on same guide rail 1 are included, horizontal outer bar 41 is U Shape channel steel, horizontal interior bar 42 are outer surface and the U-lag steel that horizontal 42 inner surface of interior bar contradicts, the horizontal one end of interior bar 42 far from vertical bar 21 It is sheathed on horizontal 41 inside of outer bar, the horizontal connection bolt across horizontal interior bar 42, spiral on horizontal connection bolt are equipped in horizontal outer bar 41 Being connected with the horizontal attaching nut compressed with horizontal 42 inner surface of interior bar, horizontal connection bolt and horizontal attaching nut will be on same guide rail 1 Horizontal outer bar 41 and horizontal interior bar 42 connect.
As shown in Fig. 2, being removably connected with vertical pole 5 between two movable stands 2 being symmetrically disposed on two guide rails 1.It is vertical Bar 5 includes being fixed on vertical outer bar 51 and vertical interior bar 52 on two vertical bars 21 on same guide rail 1 using screw respectively, indulges outer bar 51 be U-lag steel, indulges the U-lag steel that interior bar 52 is outer surface and vertical 52 inner surface of interior bar contradicts, and indulges interior bar 52 far from vertical bar 21 One end be sheathed on 51 inside of vertical outer bar, the vertical connection bolt across vertical interior bar 52 is equipped in vertical outer bar 51, indulges connection bolt Upper spiral is connected with the vertical attaching nut compressed with vertical 52 inner surface of interior bar, indulges connection bolt and vertical attaching nut for same guide rail Vertical outer bar 51 and vertical interior bar 52 on 1 connect.
As shown in Fig. 2, having fixed link 24 using screw respectively on vertical bar 21, fixed link 24 is to be connected using screw and nut I-steel on vertical pole 5, fixed link 24 are located on two guide rails 1 between symmetrically arranged two vertical bars 21, fixed link 24 It is upper to be connected with lifting cucurbit 3 using screw;The chain sling end for two lifting cucurbits 3 being symmetrically disposed on two guide rails 1 uses Wirerope connection.It is lifted with connecting tube 8 respectively along two chain slings at 4 length direction both ends of cross bar, chain sling is located at outside connecting tube 8 Side side and along the both ends of 8 axis direction of connecting tube.
As shown in Fig. 2, being respectively welded transmission shaft 61, cross bar 4 on two vertical bars 21 being symmetrically disposed on two guide rails 1 The axis of two transmission shafts 61 at both ends is identical, and connecting rod 62 is arranged on transmission shaft 61, and outer spiral shell is arranged in 61 lateral surface of transmission shaft Line, spiral is connected with the nut contradicted with 62 side of connecting rod on transmission shaft 61, between two drive rods and far from vertical bar 21 One end has been bolted push rod 63.
As shown in Fig. 2, connecting rod 62 is connect with transmission shaft 61 when movable stand 2 is moved near Pipe installing position Afterwards, push rod 63 is pushed, push rod 63 drives movable stand 2 to move along 1 surface of guide rail, the accurate position for adjusting 2 upper connector 8 of movable stand It sets, convenient for the installation between connecting tube 8.
A kind of buried pipeline transloading equipment, the course of work are as follows:
Guide rail 1 is laid with on 9 bottom surface of pipe trench, movable stand 2 is moved in pipe trench 9, two cross bars 4 and vertical pole 5 respectively with Movable stand 2 connects, and the chain sling end for then lifting two be symmetrically disposed on guide rail 1 on cucurbit 3 connects, and chain sling is arranged In 8 outside of connecting tube for needing to carry in pipe trench 9, starting lifting cucurbit 3, the chain sling lifted on cucurbit 3 slings connecting tube 8, Rolling mechanism 7 drives movable stand 2 mobile in 1 surface of guide rail, until movable stand 2 drives connecting tube 8 to be moved to Hoisting Position, uses Adjustment mechanism 6 manually carries out appropriate adjustment to the position of 2 upper connector 8 of movable stand, and the chain sling lifted on cucurbit 3 is put down, real Installation between existing connecting tube 8.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability Field technique personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but As long as all by the protection of Patent Law in the scope of the claims of the utility model.

Claims (8)

1. a kind of buried pipeline transloading equipment, it is characterised in that: including being fixed on pipe trench (9) bottom surface and be parallel to each other two lead Rail (1), the movable stand (2) mobile along guide rail (1) length direction is compressed on the guide rail (1), and the movable stand (2) is provided with Four, the movable stand (2) is symmetrically disposed on two-by-two on two guide rails (1);Drive movable stand is provided on the movable stand (2) (2) rolling mechanism (7) mobile in guide rail (1) surface;
The movable stand (2) includes vertical bar (21), and the vertical bar (21) is fixedly connected with brace far from the one end of guide rail (1) (22), the bottom bar (23) fixed with vertical bar (21) is installed on the brace (22), the bottom bar (23) is along guide rail (1) length side To sliding;It is respectively fixed with fixed link (24) on the vertical bar (21), the fixed link (24) is located at symmetrical on two guide rails (1) Between two vertical bars (21) being arranged, lifting cucurbit (3) is fixed on the fixed link (24);
The end connection of two upper symmetrically arranged two liftings cucurbit (3) of guide rail (1);
Cross bar (4) are removably connected between two movable stands (2) of the guide rail (1) length direction, are symmetrically disposed on Vertical pole (5) are removably connected between two movable stands (2) on two guide rails (1).
2. buried pipeline transloading equipment according to claim 1, it is characterised in that: the cross bar (4) include respectively with lead The horizontal outer bar (41) and horizontal interior bar (42) that two vertical bars (21) of rail (1) length direction are detachably connected, the horizontal outer bar (41) It is respectively U-lag steel with horizontal interior bar (42), the horizontal interior bar (42), which is embedded in horizontal outer bar (41) backwards to the one end of vertical bar (21), makes cross The lateral surface of interior bar (42) and the medial surface of horizontal outer bar (41) contradict, and the horizontal interior bar (42) of insertion is equipped on the horizontal outer bar (41) On horizontal connection bolt, spiral is connected with horizontal attaching nut on the horizontal connection bolt.
3. buried pipeline transloading equipment according to claim 1, it is characterised in that: the vertical pole (5) includes and guide rail (1) The vertical outer bar (51) and vertical interior bar (52) that two vertical bars (21) of length direction are detachably connected, the vertical outer bar (51) and it is vertical in Bar (52) is respectively U-lag steel, and the vertical interior bar (52), which is embedded in vertical outer bar (51) backwards to the one end of vertical bar (21), makes vertical interior bar (52) medial surface of lateral surface and vertical outer bar (51) contradicts, and is equipped on insertion vertical interior bar (52) on the vertical outer bar (51) Vertical to connect bolt, spiral is connected with vertical attaching nut on the vertical connection bolt.
4. buried pipeline transloading equipment according to claim 1, it is characterised in that: be symmetrically disposed on two guide rails (1) it is connected separately with transmission shaft (61) on two vertical bars (21) on, the axis of two transmission shafts (61) is identical, the biography It is removably connected on moving axis (61) connecting rod (62), is fixed with push rod (63) between two connecting rods (62).
5. buried pipeline transloading equipment according to claim 1, it is characterised in that: the rolling mechanism (7) includes setting In bottom bar (23) along the idler wheel (71) at guide rail (1) length direction both ends, lateral surface and guide rail (1) surface of the idler wheel (71) are supported It presses, is connected with the driving motor (72) being fixed on movable stand (2) on the idler wheel (71).
6. buried pipeline transloading equipment according to claim 5, it is characterised in that: the idler wheel (71) is ladder wheel, described Idler wheel (71) includes the support column pressed on guide rail (1) and the limited post being fixed on support column, the limited post direction branch The surface of dagger contacts at two opposite surfaces of guide rail (1).
7. buried pipeline transloading equipment according to claim 1, it is characterised in that: the guide rail (1) is I-steel.
8. buried pipeline transloading equipment according to claim 1, it is characterised in that: the adjacent vertical pole (5) and vertical bar (21) reinforcing rod (25) are removably connected between.
CN201920096874.XU 2019-01-21 2019-01-21 Buried pipeline transloading equipment Expired - Fee Related CN209601099U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920096874.XU CN209601099U (en) 2019-01-21 2019-01-21 Buried pipeline transloading equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920096874.XU CN209601099U (en) 2019-01-21 2019-01-21 Buried pipeline transloading equipment

Publications (1)

Publication Number Publication Date
CN209601099U true CN209601099U (en) 2019-11-08

Family

ID=68401462

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920096874.XU Expired - Fee Related CN209601099U (en) 2019-01-21 2019-01-21 Buried pipeline transloading equipment

Country Status (1)

Country Link
CN (1) CN209601099U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112964070A (en) * 2021-02-01 2021-06-15 中国科学院包头稀土研发中心 Movable trolley capable of running on basis of H steel rail and automatic rare earth electrolysis feeding device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112964070A (en) * 2021-02-01 2021-06-15 中国科学院包头稀土研发中心 Movable trolley capable of running on basis of H steel rail and automatic rare earth electrolysis feeding device

Similar Documents

Publication Publication Date Title
CN109210274B (en) Pipe jacking pipeline butt joint device and method
CN202733170U (en) Pipeline mounting machine
CN103726421B (en) Height and span adjustable track paver for metro construction
CN210074624U (en) Cable laying device that stability is high
CN112025733B (en) Underwater inspection robot suitable for power pipe gallery
CN209601099U (en) Buried pipeline transloading equipment
CN210768824U (en) From track laying running gear and tunnel lining platform truck
CN209380189U (en) Large-diameter pipeline pairing device in a kind of restricted clearance
CN112303332A (en) Pipe work apparatus and method for pipe gallery
CN213776576U (en) Device for assisting in pipeline connection
CN205838507U (en) A kind of power engineering crowbar
CN209954054U (en) Auxiliary transfer device for steel pipe welding machine tool
CN116835033A (en) Quick packing apparatus of building site basement steel pipe
CN216807824U (en) Pipeline mobile device for hydraulic engineering
CN209602000U (en) Buried pipeline installs crane
CN214568556U (en) Multi-pipeline transportation device in narrow space
CN212420287U (en) Welding tool for standard knot of crane
CN115234706A (en) Pipeline laying equipment for pipeline reconstruction construction and method thereof
CN203568803U (en) Device used for lifting hinging shaft of hydraulic support top beam
CN208401421U (en) A kind of line securement device
CN209602038U (en) Hanging device for pipe trench transport pipeline
CN106743260B (en) Pressure steel pipe hole transportation device and method for hole climbing transportation by using same
CN108069340B (en) Replace the method and specific purpose tool of large-scale bridge type grab bucket ship unloader cart speed reducer
CN214653267U (en) Underwater concrete pouring guide pipe lifting frame convenient to move
CN216372087U (en) Fixed support equipment for pipeline installation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191108

Termination date: 20220121