CN202559771U - High-altitude rope replacing device of pre-stress beam string structure - Google Patents

High-altitude rope replacing device of pre-stress beam string structure Download PDF

Info

Publication number
CN202559771U
CN202559771U CN 201220199173 CN201220199173U CN202559771U CN 202559771 U CN202559771 U CN 202559771U CN 201220199173 CN201220199173 CN 201220199173 CN 201220199173 U CN201220199173 U CN 201220199173U CN 202559771 U CN202559771 U CN 202559771U
Authority
CN
China
Prior art keywords
rope
rope replacing
altitude
string structure
beam string
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220199173
Other languages
Chinese (zh)
Inventor
王春生
文璐
闫家波
于建利
高思禄
冉悠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CR10BG CONSTRUCTION ENGINEERING Co Ltd
China Railway No 10 Engineering Group Co Ltd
Original Assignee
CR10BG CONSTRUCTION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CR10BG CONSTRUCTION ENGINEERING Co Ltd filed Critical CR10BG CONSTRUCTION ENGINEERING Co Ltd
Priority to CN 201220199173 priority Critical patent/CN202559771U/en
Application granted granted Critical
Publication of CN202559771U publication Critical patent/CN202559771U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a high-altitude rope replacing device of a pre-stress beam string structure. The high-altitude rope replacing device comprises a plurality of rope replacing rest piers, wherein each rope replacing rest pier is an eight-three-style railway light type military bridge pier; a jack and a double-I-steel support are arranged between the top of each rope replacing rest pier and a beam string structure; a tensile steel wire rope for limiting the deformation of the beam string structure and a large hand hoist are arranged among a plurality of the rope replacing rest piers; the steel wire rope is tensioned through tensioning hoops which are fixed at the two ends of the beam string structure; a middle column deviation-preventing counter weight is arranged in the middle of the steel wire rope; and the distribution of the plurality of rope replacing rest piers is determined by a tension rope force obtained by calculation and actual monitoring. According to the high-altitude rope replacing device disclosed by the utility model, rope replacing can be realized under the condition of keeping an upper load immobile; the construction efficiency is obviously improved, the construction period is shortened and the stopping time of a motor car is reduced to the greatest extent; and meanwhile, an upper structure is kept and the rope replacing cost is reduced to the greater extent.

Description

The rope device is changed in a kind of prestressing force beam string structure high-altitude
Technical field
The utility model relates to a kind of large-span prestressed tension string beam structure high-altitude and changes the rope device, is applicable to the large-span prestressed steel work maintenance works of railway station.
Background technology
Newly-built along with the Large-scale Railway station, the room intercolumniation is increasing, requires its beam span also increasing, and the construction technology that large span H shaped steel plane combining structure is opened the string beam is employed more and more.H shaped steel plane combining structure is opened the construction technology of string beam and is made up of H shaped steel solid web girder, strut and cable wire; The three interconnects, and solid web girder is connected with cable wire through strut, and the anchoring of cable wire endpoint node is fixed on the steel plate through ground tackle; Be supported on the solid web girder through stiffener; The cable wire tightness can be regulated, and through regulating the cable wire tightness, solid web girder is applied prestressing force (as shown in Figure 1).The design life of prestressed cable is 50 years, and not in place because of the maintenance between the operating period according to statistics, the actual life of prestressed cable is on average less than 30 years.Particularly to change the rope technology very immature in the high-altitude for the construction technology that present domestic large span H shaped steel plane combining structure is opened the string beam, the maintenance and the replacing problem of the prestressed cable that therefore needs to be resolved hurrily.
Summary of the invention
The utility model technical problem to be solved is the deficiency to prior art, and a kind of replacing apparatus and method of prestressed cable are provided.
For solving this technical problem; The utility model provides a kind of prestressing force beam string structure high-altitude to change the rope device; Comprise a plurality of rope buttresses that change, the said rope buttress that changes is the military bridge piers of eight or three formula Railway Light, jack is set between a top of changing the rope buttress and a string beam supports with two i iron.
Said a plurality of change be provided with between the rope buttress that restriction opens the distortion of string beam socket wire rope and big hand cucurbit, this wire rope is through being fixed on the tension anchor ear tension at a string beam two ends.
Be provided with the anti-inclined to one side counterweight of center pillar at the middle part of wire rope.
Said a plurality of distribution of changing the rope buttress is confirmed through the stretching rope power of calculating and actual monitoring obtains.
Beneficial effect: the utility model can keep at upper load realizes changing rope under the motionless condition; Significantly improve efficiency of construction, shortened the construction period, reduced motor-car idle time to greatest extent; The reservation of superstructure has simultaneously reduced on largely and has changed Suo Chengben.
Description of drawings
Fig. 1 is the tension string beam structure sketch map;
Fig. 2 be the utility model open at the bottom of the string beam and support and connection sketch map between buttress;
Fig. 3 is that the deformation monitoring point of the utility model is arranged sketch map.
Among the figure: 1 string beam, 2 struts, 3 cable wires, 4 change rope buttress, 5 jack, 6 pairs of i iron.
The specific embodiment
Below in conjunction with accompanying drawing and embodiment the utility model is done specific descriptions.
Shown in Figure 2 be the utility model open at the bottom of the string beam and support and connection sketch map between buttress.
The utility model comprises a plurality of rope buttresses 4 that change, and jack 5 is set between a top of changing rope buttress 4 and a string beam 1 supports with two i iron 6.
For the string beam 1 of opening that prevents to change in the rope process is out of shape; A plurality of change be provided with between the rope buttress 4 that restriction opens 1 distortion of string beam socket wire rope and big hand cucurbit; Said wire rope also is provided with the anti-inclined to one side counterweight of center pillar through being fixed on the tension anchor ear tension at string beam 1 two ends at the middle part of wire rope.
The utility model adopts the military bridge pier of eight or three formula Railway Light as changing rope buttress 4, has improved on largely and has changed rope efficient, has shortened and has changed the rope construction period; The military bridge pier of eight or three formula Railway Light can recycle, and has practiced thrift and has changed Suo Chengben; Simultaneously, because of the intensity of the military bridge pier of eight or three formula Railway Light is high, rigidity is big, reduced to greatest extent when changing rope the adverse effect of existing structure, it is controlled to change the rope work safety.
A plurality of distributions of changing rope buttress 4 combine through analogue simulation analysis and construction monitoring; Under the situation of removal superstructure load not; Under off-design behaviour, carry out string beam 1 high-altitude definite (as shown in Figure 3) of stretching rope power value when changing rope through calculating to obtain with actual monitoring; Wherein analogue simulation calculates the optimization scheme that construction technology can be provided; Construction monitoring can provide accurate construction control target: I shown in Figure 3, II, III, IV, V are five monitoring points, and both can verify each other simultaneously, and this has further guaranteed the q&r of construction.
The utility model can keep under the motionless condition at upper load to be realized changing rope, has significantly improved efficiency of construction, has shortened the construction period, has reduced motor-car idle time to greatest extent, and the reservation of superstructure has simultaneously reduced on largely and changed Suo Chengben.
The above-mentioned embodiment of the utility model just illustrates, and is not only, all in the utility model scope or the change that is equal in the scope of the utility model all surrounded by the utility model.

Claims (2)

1. the rope device is changed in a prestressing force beam string structure high-altitude; Comprise a plurality of rope buttresses (4) that change; It is characterized in that: the said rope buttress (4) that changes is the military bridge piers of eight or three formula Railway Light; Jack (5) and two i iron (6) support are set between a top of changing rope buttress (4) and a string beam (1); Said a plurality of change be provided with between the rope buttress (4) that restriction opens string beam (1) distortion socket wire rope and big hand cucurbit, this wire rope is provided with the anti-inclined to one side counterweight of center pillar through being fixed on the tension anchor ear tension at string beam (a 1) two ends at the middle part of wire rope.
2. the rope device is changed in prestressing force beam string structure according to claim 1 high-altitude, it is characterized in that: said a plurality of distributions of changing rope buttress (4) are confirmed through the stretching rope power value of calculating and actual monitoring obtains.
CN 201220199173 2012-05-07 2012-05-07 High-altitude rope replacing device of pre-stress beam string structure Expired - Fee Related CN202559771U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220199173 CN202559771U (en) 2012-05-07 2012-05-07 High-altitude rope replacing device of pre-stress beam string structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220199173 CN202559771U (en) 2012-05-07 2012-05-07 High-altitude rope replacing device of pre-stress beam string structure

Publications (1)

Publication Number Publication Date
CN202559771U true CN202559771U (en) 2012-11-28

Family

ID=47209438

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220199173 Expired - Fee Related CN202559771U (en) 2012-05-07 2012-05-07 High-altitude rope replacing device of pre-stress beam string structure

Country Status (1)

Country Link
CN (1) CN202559771U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107313604A (en) * 2017-07-12 2017-11-03 天津大学 A kind of drag-line node reinforced for space structure string
CN108824839A (en) * 2018-08-29 2018-11-16 国网江苏省电力有限公司扬州供电分公司 A kind of drag-line ruggedized construction of existing C-type steel purlin
CN113216675A (en) * 2021-03-24 2021-08-06 陕西省建筑科学研究院有限公司 Method for shifting support rod and cable clamp in cable structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107313604A (en) * 2017-07-12 2017-11-03 天津大学 A kind of drag-line node reinforced for space structure string
CN108824839A (en) * 2018-08-29 2018-11-16 国网江苏省电力有限公司扬州供电分公司 A kind of drag-line ruggedized construction of existing C-type steel purlin
CN108824839B (en) * 2018-08-29 2023-11-24 国网江苏省电力有限公司扬州供电分公司 Cable reinforcement structure of existing C-shaped steel purline
CN113216675A (en) * 2021-03-24 2021-08-06 陕西省建筑科学研究院有限公司 Method for shifting support rod and cable clamp in cable structure
CN113216675B (en) * 2021-03-24 2023-02-10 陕西省建筑科学研究院有限公司 Method for shifting stay bar and cable clamp in cable structure

Similar Documents

Publication Publication Date Title
CN103088750B (en) Especial-big span suspension bridge of uniparted hyperboloid space rope net main cable and construction method thereof
CN103669224B (en) Method and steel pipe support for construction of arch tower of inclined arch tower double-cable-plane prestressed concrete cable-stayed bridge
CN102235092B (en) Layered hoisting construction process for suspended steel structure
CN201172597Y (en) Wide span heavy-load cable hoisting machine
CN102041782B (en) Multi-point pushing system of large-span steel truss girders and pushing process thereof
CN102635186A (en) Double-layer spoke type space string-structure steel roof truss and pre-stressed tension method thereof
CN105386411A (en) Multifunctional portal device of suspension bridge pillar top
CN103334378B (en) The few circulation classification stretch-draw construction method of Self-Anchored Concrete Suspension hoist cable
CN202559771U (en) High-altitude rope replacing device of pre-stress beam string structure
CN106541489B (en) Bridge deck prefabricated formwork system
CN102108748B (en) Quadrilateral endless rope chord supporting structure and construction process
CN110205940A (en) 0# block construction bracket and its reverse drawing preloading method
CN105714681B (en) Implementation method of suspension type monorail traffic rigid frame system
CN203296361U (en) Long-span steel structure cross assembling hoisting platform
CN201746779U (en) Prestressed tension jack moving frame
CN103572703A (en) Construction method of outer wrapped concrete obliquely pulling and buckling and ring and section dividing combination method
CN203613467U (en) Steel pipe bracket for construction of arch tower in oblique arch tower double-cable plane pre-stressed concrete cable-stayed bridge
CN114182647A (en) Construction method for lifting and rotating weak arch
CN207775734U (en) A kind of balance regulator of single-cantilever assembly
CN207749417U (en) A kind of concrete king-post internal model stiff skeleton
CN103061514A (en) Long-span steel structure corridor construction method
CN203716044U (en) Low bearing or middle bearing cable arch combined structural bridge
CN111395210B (en) Method for improving bearing capacity of truss girder bridge by using external prestressed tendons
CN205205685U (en) Span wire pier is function portal device at most
CN102877657B (en) Large-span H-shaped plane composite structure beam string upper-air cable replacement construction method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121128

Termination date: 20150507

EXPY Termination of patent right or utility model