CN113216675B - Method for shifting stay bar and cable clamp in cable structure - Google Patents

Method for shifting stay bar and cable clamp in cable structure Download PDF

Info

Publication number
CN113216675B
CN113216675B CN202110314984.0A CN202110314984A CN113216675B CN 113216675 B CN113216675 B CN 113216675B CN 202110314984 A CN202110314984 A CN 202110314984A CN 113216675 B CN113216675 B CN 113216675B
Authority
CN
China
Prior art keywords
cable
power source
displacing
spacer
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110314984.0A
Other languages
Chinese (zh)
Other versions
CN113216675A (en
Inventor
柳明亮
周春娟
董军锋
魏超琪
马瑞
程荣荣
李俊楠
苏东升
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Architecture Science Research Institute Co Ltd
Original Assignee
Shaanxi Architecture Science Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Architecture Science Research Institute Co Ltd filed Critical Shaanxi Architecture Science Research Institute Co Ltd
Priority to CN202110314984.0A priority Critical patent/CN113216675B/en
Publication of CN113216675A publication Critical patent/CN113216675A/en
Application granted granted Critical
Publication of CN113216675B publication Critical patent/CN113216675B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/342Structures covering a large free area, whether open-sided or not, e.g. hangars, halls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/14Suspended roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0281Repairing or restoring roofing or roof covering
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • E04G25/04Shores or struts; Chocks telescopic

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a method for displacing a stay bar and a cable clamp in a cable structure, which comprises the following steps: the method comprises the following steps of firstly, providing a stay bar restoration device, wherein the stay bar restoration device comprises a support tool and a power source, the bottom of the support tool is connected with the power source, and the power source can drive the support tool to move; secondly, abutting the top of the supporting tool against an upper roof structure, and connecting the power source to the steel cable; thirdly, driving the supporting tool to tightly prop against the upper roof structure by using the power source, so that the cable clamp at the bottom of the supporting rod is separated from the cast steel node; and step four, moving the support rod to a design position. The method for shifting the stay bar and the cable clamp in the cable structure is simple and easy to implement, and the used device is simple and easy to assemble and disassemble.

Description

Method for shifting support rod and cable clamp in cable structure
Technical Field
The invention relates to the technical field of structure repair, in particular to a method for displacing a stay bar and a cable clamp in a cable structure.
Background
The large-span spatial structure is one of the important marks of the national building science and technology development level. The research and development of the space structure in all countries in the world are paid great attention, and the space structure is widely applied to a large-span structure by virtue of attractive building shape and good mechanical property. The upper part of the supporting rod used in the technical field of large-span space structures is used for supporting a large-span upper roof structure, the lower part of the supporting rod is fixed on the steel cable through the cable clamp, and the tension of the steel cable provides elasticity for the supporting rod at the cast steel node where the cable clamp is located, so that the supporting rod supports the upper roof structure. Over time, the cable clips at the lower end of the support rods slide relative to the cables, causing the support rods to shift and fail to provide adequate support for the upper roof structure. Therefore, a method for displacing the stay bar and the cable clamp in the cable structure is required to solve the above-mentioned problem of displacement of the stay bar.
Disclosure of Invention
Therefore, the technical problem to be solved by the invention is to provide a method for restoring the position of the support rod, which is simple and easy to operate, short in construction period and small in engineering quantity.
In order to solve the technical problem, the invention provides a method for shifting a stay bar and a cable clamp in a cable structure, which comprises the following steps:
the method comprises the following steps of firstly, providing a stay bar restoration device, wherein the stay bar restoration device comprises a support tool and a power source, the bottom of the support tool is connected with the power source, and the power source can drive the support tool to move;
secondly, abutting the top of the supporting tool against an upper roof structure, and connecting the power source to the steel cable;
driving the supporting tool to tightly push the upper roof structure by using the power source so as to separate the cable clamp at the bottom of the support rod from the cast steel node;
and fourthly, restoring the position of the support rod.
In an embodiment of the invention, the connecting the bottom of the support tool with the power source specifically includes that the bottom of the support tool is detachably connected with the power source.
In one embodiment of the invention, coupling the power source to the wire rope includes coupling the power source device to the wire rope using a bolt.
In one embodiment of the invention, the bolt is a U-bolt, and the radius of the arc part of the U-bolt matches the radius of the steel cable.
In an embodiment of the invention, the second step specifically includes abutting the top of the supporting tool against the upper roof structure, and after the power source is connected to the steel cable, making the supporting tool perpendicular to the steel cable.
In one embodiment of the invention, the support tool comprises a support rod, and the lower end of the support rod is connected with the power source.
In an embodiment of the invention, the supporting tool further comprises a first sealing plate, and the first sealing plate is arranged on the top of the supporting rod.
In an embodiment of the present invention, the supporting tool further includes a second sealing plate, and the second sealing plate is disposed between the supporting rod and the power source.
In one embodiment of the invention, the power source is a jack.
In one embodiment of the present invention, step four specifically includes moving the brace to the design position using a lever block.
Compared with the prior art, the technical scheme of the invention has the following advantages: the shifting method of the stay bar and the cable clamp in the cable structure is simple and easy to implement, and the used device is simple and easy to assemble and disassemble.
Drawings
In order that the present disclosure may be more readily understood, a more particular description of the disclosure will be rendered by reference to specific embodiments thereof which are illustrated in the appended drawings
Fig. 1 is a schematic view showing a strut restoring apparatus according to a preferred embodiment of the present invention;
FIG. 2 is an operational schematic of a strut restoration device in a preferred embodiment of the present invention;
fig. 3 is a schematic view of a power source structure in a preferred embodiment of the present invention.
Wherein: 1. supporting a tool; 2. a power source; 3. a bolt; 4. a support bar; 5. a first sealing plate; 6. lifting lugs; 7. a stay bar; 8. a steel cord; 9. a second sealing plate; 10. and (4) a cable clamp.
Detailed Description
The present invention is further described below in conjunction with the drawings and the embodiments so that those skilled in the art can better understand the present invention and can carry out the present invention, but the embodiments are not to be construed as limiting the present invention.
Referring to fig. 1 and 2, there is shown a method of displacing a stay and a clip in a cable structure in a preferred embodiment of the present invention, in which a stay 7 to be restored is connected at the bottom to a wire rope 8 by a clip 10 and at the top to support an upper roof structure.
The method for restoring the position of the support rod comprises the following steps:
the method comprises the following steps that firstly, a support rod restoration device is provided, the support rod restoration device comprises a support tool 1 and a power source 2, the bottom of the support tool 1 is connected with the power source 2, and the power source 2 can drive the support tool 1 to move;
preferably, the supporting rod that the supporting tool comprises, the bracing piece lower extreme is connected the power supply.
Specifically, be equipped with a pair of lug 6 on the bracing piece 4, lug 6 makes things convenient for hoist and mount bracing piece 4.
Preferably, the support rod 4 is a steel pipe, which can provide sufficient supporting force.
In some embodiments, the supporting tool 1 further comprises a first sealing plate 5, and the first sealing plate 5 is connected to the top of the supporting rod 4. The first sealing plate 5 can increase the contact surface of the supporting rod 4 and the upper roof structure, reduce the pressure of the supporting rod 4 to the upper roof structure and avoid scratching the upper roof structure.
In some embodiments, the supporting tool 1 further includes a second sealing plate 9, and the second sealing plate 9 is connected to the bottom of the supporting rod 4 and disposed between the supporting rod 4 and the power source 2, so that the power source 2 can stably load the supporting tool 1.
Preferably, support 1 bottoms of frock and connect power supply 2, specifically include, support 1 bottoms of frock and can dismantle and connect power supply 2, make things convenient for the dismouting to support frock 1.
Preferably, the power source 2 is a jack, and the jack can stably jack the steel pipe tool 1, so that the steel pipe tool 1 gradually supports the upper roof structure.
Secondly, the top of the supporting tool 1 is abutted against the upper roof structure, and the power source 2 is connected to the steel cable 8;
in some embodiments, as shown in fig. 2, the top of the support tool 1 is preferably positioned against the upper roof structure at the upper end of the stay 7, which is effective to support the upper roof structure.
Preferably, attaching power source 2 to wire rope 8 specifically includes attaching power source 2 to wire rope 8 using bolts 3.
In some embodiments, as shown in fig. 2, there are two bolts 3, and the bolts 3 are disposed at both ends of the base of the power source 2, so that the power source 2 can be stably fixed to the wire rope 8. As shown in fig. 3, the bolt 3 is a U-shaped bolt, and the radius of the arc portion of the U-shaped bolt matches the radius of the steel cable 8 fastened to the U-shaped bolt, so that the tension direction of the steel cable 8 is the same as the force application direction of the power source 2.
The top that will support frock 1 supports upper portion roof structure, after connecting power supply 2 on 8 with the cable wire, makes and supports frock 1 perpendicular to cable wire, makes the tension of cable wire 8, the application of force direction of power supply 2 and supports frock 1 unanimous to the application of force direction of upper portion roof structure, can prop upper portion roof structure steadily.
Thirdly, driving the supporting tool 1 to tightly push the upper roof structure by using the power source 2, so that the cable clamp 10 at the bottom of the support rod 7 is separated from the cast steel node;
moving the support rod 7 to a design position;
in some embodiments, the strut 7 is moved to a position perpendicular to the wire 8, eliminating the tendency for relative sliding between the strut 7 and the wire 8, and the cable clamp 10 is then tightened to secure the strut 7 to the wire 8.
Optionally, the lever block or other loading devices are used for moving the support rod 7 to the design position, and the lever block is simple and easy to operate and high in working efficiency.
Specifically, the lever block is used for drawing the cable clamp 10 at the lower end of the steel pipe to reset the stay bar 7 along the steel cable 8, so that the displacement of the cable clamp 10 at the lower end of the stay bar 7 is shortest, and the construction period is shortened.
It should be understood that the above examples are only for clarity of illustration and are not intended to limit the embodiments. Other variations and modifications will be apparent to persons skilled in the art in light of the above description. This need not be, nor should it be exhaustive of all embodiments. And obvious variations or modifications therefrom are within the scope of the invention.

Claims (10)

1. A method of displacing a stay and a cable clamp in a cable structure, comprising the steps of:
the method comprises the following steps of firstly, providing a stay bar restoration device, wherein the stay bar restoration device comprises a support tool and a power source, the bottom of the support tool is connected with the power source, and the power source can drive the support tool to move;
secondly, abutting the top of the supporting tool against an upper roof structure, and connecting the power source to the steel cable; the method comprises the following steps: connecting a power source to the steel cable by using bolts, wherein the bolts are U-shaped bolts, the radius of the arc part of each U-shaped bolt is matched with that of the steel cable buckled with the U-shaped bolt, and the bolts are arranged at two ends of a power source base;
driving the supporting tool to tightly push the upper roof structure by using the power source so as to separate the cable clamp at the bottom of the support rod from the cast steel node;
and fourthly, restoring the position of the support rod.
2. A method of displacing spacer and cable clamp assemblies in cable constructions as claimed in claim 1, wherein: support the frock bottom and connect the power supply specifically includes, support the frock bottom and can dismantle the connection the power supply.
3. A method of displacing spacer and cable clamp assemblies in cable constructions as claimed in claim 1, wherein: connecting the power source to the wire rope specifically includes connecting the power source to the wire rope using a bolt.
4. A method of displacing a spacer and a cable clamp in a cable structure as claimed in claim 3, characterized in that: the bolt is a U-shaped bolt, and the radius of the arc part of the U-shaped bolt is matched with that of the steel cable.
5. A method of displacing a spacer and a cable clamp in a cable structure as claimed in claim 1, characterized in that: and step two specifically comprises the step of abutting the top of the supporting tool against an upper roof structure, and enabling the supporting tool to be perpendicular to the steel cable after the power source is connected to the steel cable.
6. A method of displacing spacer and cable clamp assemblies in cable constructions as claimed in claim 1, wherein: the supporting tool comprises a supporting rod, and the lower end of the supporting rod is connected with the power source.
7. A method of displacing a spacer and a cable clamp in a cable structure as claimed in claim 6, characterized in that: the supporting tool further comprises a first sealing plate, and the first sealing plate is arranged at the top of the supporting rod.
8. A method of displacing spacer and clip in a cable structure according to claim 6, wherein: the supporting tool further comprises a second sealing plate, and the second sealing plate is arranged between the supporting rod and the power source.
9. A method of displacing spacer and cable clamp assemblies in cable constructions as claimed in claim 1, wherein: the power source is a jack.
10. A method of displacing a spacer and a cable clamp in a cable structure as claimed in claim 1, characterized in that: and step four, specifically, moving the support rod to a design position by using a lever hoist.
CN202110314984.0A 2021-03-24 2021-03-24 Method for shifting stay bar and cable clamp in cable structure Active CN113216675B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110314984.0A CN113216675B (en) 2021-03-24 2021-03-24 Method for shifting stay bar and cable clamp in cable structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110314984.0A CN113216675B (en) 2021-03-24 2021-03-24 Method for shifting stay bar and cable clamp in cable structure

Publications (2)

Publication Number Publication Date
CN113216675A CN113216675A (en) 2021-08-06
CN113216675B true CN113216675B (en) 2023-02-10

Family

ID=77083970

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110314984.0A Active CN113216675B (en) 2021-03-24 2021-03-24 Method for shifting stay bar and cable clamp in cable structure

Country Status (1)

Country Link
CN (1) CN113216675B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102116012A (en) * 2009-12-30 2011-07-06 上海天演建筑物移位工程有限公司 Suspender replacement method for tie bar type overpass bridge
CN102162279A (en) * 2011-02-14 2011-08-24 东南大学 Tensioning joint and device for single hoop cable in cable-rod structure by top support rod
CN202559771U (en) * 2012-05-07 2012-11-28 中铁十局集团建筑工程有限公司 High-altitude rope replacing device of pre-stress beam string structure
CN203113619U (en) * 2013-02-28 2013-08-07 华南理工大学建筑设计研究院 Support rod anti-sliding device provided with beam string structure
CN103243924A (en) * 2013-04-25 2013-08-14 中国华冶科工集团有限公司 Method for improving slippage resistance of cable clamp
CN104234445A (en) * 2014-09-25 2014-12-24 扬州大学 Restoration-security multifunctional bracket of deformed wooden structure building
CN104763162A (en) * 2014-12-29 2015-07-08 中国地质大学(武汉) Counter-jacking repairing scheme for loaded offset concrete filled steel tube column

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102116012A (en) * 2009-12-30 2011-07-06 上海天演建筑物移位工程有限公司 Suspender replacement method for tie bar type overpass bridge
CN102162279A (en) * 2011-02-14 2011-08-24 东南大学 Tensioning joint and device for single hoop cable in cable-rod structure by top support rod
CN202559771U (en) * 2012-05-07 2012-11-28 中铁十局集团建筑工程有限公司 High-altitude rope replacing device of pre-stress beam string structure
CN203113619U (en) * 2013-02-28 2013-08-07 华南理工大学建筑设计研究院 Support rod anti-sliding device provided with beam string structure
CN103243924A (en) * 2013-04-25 2013-08-14 中国华冶科工集团有限公司 Method for improving slippage resistance of cable clamp
CN104234445A (en) * 2014-09-25 2014-12-24 扬州大学 Restoration-security multifunctional bracket of deformed wooden structure building
CN104763162A (en) * 2014-12-29 2015-07-08 中国地质大学(武汉) Counter-jacking repairing scheme for loaded offset concrete filled steel tube column

Also Published As

Publication number Publication date
CN113216675A (en) 2021-08-06

Similar Documents

Publication Publication Date Title
CN113216675B (en) Method for shifting stay bar and cable clamp in cable structure
JP3167203B2 (en) Main column replacement equipment for steel pipe steel tower
JP5056659B2 (en) Utility pole rebuilding tool and utility pole rebuilding method
CN114961219B (en) Climbing device for municipal works inspection shaft
CN110977924A (en) Tunnel gas pipeline installation manipulator
CN112982475B (en) Auxiliary mounting tool for prefabricated foundation of power transmission line
JP5419003B2 (en) Construction method of storage tank jack and floating roof storage tank
CN211078204U (en) Narrow space pipeline hoisting accessory
CN212202081U (en) Tunnel engineering steel bow member fixing device
CN210683047U (en) Loading and unloading vehicle device suitable for large-scale component
CN102817624A (en) Hydraulic pressure supporting frame dismantling device
JPH0213115B2 (en)
JP6954752B2 (en) Tube lifting device
CN219366088U (en) Tunnel construction braced frame model
CN214699541U (en) High-efficient mounting structure of fire control galvanized steel pipe
CN218320399U (en) Petroleum pipeline hoisting crane
CN218879171U (en) Cement culvert pipe hoist device
CN213062023U (en) Foundation pit supporting device
JP2001268758A (en) Replacement method of damaged component of transmission steel tower, and replacement tool
CN205045712U (en) Caterpillar crane of assembled is with keeping off cord rack device
CN211851709U (en) Buffering manipulator for oil drilling platform
CN216272912U (en) A transportation, lifting devices for equipment material construction installation
SU1416647A1 (en) Power transmission line support
CN219058292U (en) Clamp tool for hoisting slope protection stone
CN215673891U (en) Pipeline valve installation device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Liu Mingliang

Inventor after: Zhou Chunjuan

Inventor after: Dong Junfeng

Inventor after: Wei Chaoqi

Inventor after: Ma Rui

Inventor after: Cheng Rongrong

Inventor after: Li Junnan

Inventor after: Su Dongsheng

Inventor before: Liu Mingliang

Inventor before: Gu Sheng

Inventor before: Sun Jinbo

Inventor before: Lin Li

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant