CN202544394U - Early-dismounting template system - Google Patents

Early-dismounting template system Download PDF

Info

Publication number
CN202544394U
CN202544394U CN2012201886641U CN201220188664U CN202544394U CN 202544394 U CN202544394 U CN 202544394U CN 2012201886641 U CN2012201886641 U CN 2012201886641U CN 201220188664 U CN201220188664 U CN 201220188664U CN 202544394 U CN202544394 U CN 202544394U
Authority
CN
China
Prior art keywords
nut
support
vertical rod
early
channel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012201886641U
Other languages
Chinese (zh)
Inventor
孙兴香
苏源
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANTONG HAIZHOU CONSTRUCTION GROUP CO Ltd
Original Assignee
NANTONG HAIZHOU CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANTONG HAIZHOU CONSTRUCTION GROUP CO Ltd filed Critical NANTONG HAIZHOU CONSTRUCTION GROUP CO Ltd
Priority to CN2012201886641U priority Critical patent/CN202544394U/en
Application granted granted Critical
Publication of CN202544394U publication Critical patent/CN202544394U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model relates to an early-dismounting template system, which comprises a vertical rod support frame and a transverse rod support frame, wherein the vertical rod support frame comprises a regulating support frame and a vertical rod, the transverse rod support frame is arranged at the regulating support frame, and the regulating support frame is movably arranged at the vertical rod. The regulating support frame of the early-dismounting template system is movably arranged at the vertical rod, the vertical rod support frame and the transverse rod support frame are regulated through moving the regulating support frame, and the construction is convenient.

Description

Early-dismantling formwork system
Technical field
The utility model relates to the concrete blinding system of using in a kind of building operations, especially slab form early removing system.
Background technology
At present, the earlier disassembly system of formworks that building field adopted mainly by the bowl fastening type scaffold, early tear column cap, adjustable frames, girder, secondary beam and template open and set up and form.The bowl fastening type scaffold comprises multiple members such as vertical rod, cross bar, brace.Rod end need be installed and early tear column cap open, and the bottom needs the install adjustment base, and the adjusting of bearing height needs through regulating base and early tearing column cap open and carry out, and construction is inconvenient.
The utility model content
In view of above content, be necessary to provide a kind of early-dismantling formwork system of convenient construction.
According to an aspect of the utility model, the early-dismantling formwork system that provides comprises vertical rod support and over brace, and the vertical rod support comprises regulates support and vertical rod, and over brace is installed on adjusting bracket adjustment support and is installed on vertical rod movably.
In certain embodiments, regulate support and comprise that screw rod and adjustable positions are installed on first nut of screw rod wholely, screw rod comprises first end and the first end second opposed end, and vertical rod is provided with accepting hole, and second end of screw rod penetrates accepting hole, and first nut is replaced vertical rod.
In certain embodiments; Regulate support and comprise that also adjustable positions is installed on second nut of screw rod wholely and is sheathed on the channel-section steel support of screw rod; First nut and second nut are positioned at a side of channel-section steel support, and the channel-section steel support is replaced second nut, and over brace is fixed in the channel-section steel support.
In certain embodiments, regulate support and also comprise the carriage that is used to be provided with first flitch, the channel-section steel support is between second nut and carriage.
In certain embodiments, carriage comprises and is fixed in screw rod first end with steel plate that first flitch is set and the fixture that is used for fixing first flitch.
In certain embodiments, fixture is an iron nail, and steel plate is provided with through hole, and fixture passes through hole and is fixed in first flitch.
In certain embodiments, first nut comprises the body of butt vertical rod and is positioned at the handle of body both sides.
In certain embodiments, second nut comprises the body of replacing the channel-section steel support and is positioned at the handle of body both sides.
The adjusting support of the utility model early-dismantling formwork system is installed on vertical rod movably, adjusts vertical rod support and over brace, convenient construction through moving the adjusting support.
Description of drawings
Fig. 1 is the construction view of the utility model early-dismantling formwork system one embodiment;
Fig. 2 regulates the holder part sketch map among Fig. 1.
The specific embodiment
Below in conjunction with accompanying drawing and specific embodiment the utility model is done further to describe in detail explanation.
Please with reference to Fig. 1 and Fig. 2, the utility model early-dismantling formwork system one embodiment comprises a plurality of vertical rod supports 20 and a plurality of over brace 100 (only showing the assembly relation between a vertical rod support 20 and two over braces 100 among Fig. 1).
Vertical rod support 20 comprises regulates support 30 and vertical rod 40.Regulate that support 30 comprises screw rod 32, is fixed in the carriage 34 of screw rod 32, channel-section steel support 36, the adjustable ground that is sheathed on screw rod 32 is installed on first nut 37 of screw rod 32 and second nut 38 that adjustable ground is installed on screw rod 32.Screw rod 32 comprises first end 320 and and first end, 320 second opposed end 322.Carriage 34 comprises steel plate 340 and the fixture 342 that is fixed in screw rod 32 first ends 320.Steel plate 340 is provided with through hole 344 and wears for fixture 342.Channel-section steel support 36 is provided with the through hole 360 that supplies screw rod 32 to wear.First nut 37 and second nut 38 are positioned at the side of channel-section steel support 36 away from carriage 34, and second nut 38 is near channel-section steel support 36.First nut 37 comprises body 370 and is arranged at the handle 372 of body 370 both sides.Second nut 38 comprises body 380 and is arranged at the handle 382 of body 380 both sides.Handle 372 and 382 is convenient to when construction, regulate first nut 37 and second nut 38.The internal diameter of through hole 360 is less than the external diameter of the body 380 of second nut 38, and when vertical rod support 20 vertical placements, channel-section steel support 36 is replaced the body 380 of second nut 38, so that channel-section steel support 36 is fixing.Vertical rod 40 is cylindric, is provided with accepting hole 42 along axis direction.Second end 322 of screw rod 32 penetrates in the accepting hole 42 of vertical rod 40, so that screw rod 32 is contained in the accepting hole 42 of vertical rod 40, the body 370 butt vertical rods 40 of first nut 37 are installed on vertical rod 40 so that regulate support 30.Make that through adjusting first nut 37 regulating support 30 is contained in vertical rod 40 movably.In this embodiment, fixture 342 is an iron nail.
Over brace 100 is made up of cross bar and main joist.The both sides of over brace 100 are fixed in the channel-section steel support 36, so that over brace 100 is arranged at vertical rod support 20.
When construction, the steel plate 340 of regulating support 30 is provided with first flitch 200, and fixture 342 passes through hole 344 and is fixed in first flitch 200, regulates support 40 so that first flitch 200 is fixed in.Regulate first nut 37; Screw rod 32 is moved in vertical rod 40, when the upper surface of first flitch 200 is concordant with the absolute altitude of the bottom of the floor of being built 300, stop to adjust first nut 37; The body 370 butt vertical rods 40 of first nut 37 are regulated support 30 and are installed on vertical rod 40.Over brace 100 is fixed in the channel-section steel support 36 of vertical rod support 20, makes over brace 100 be arranged at vertical rod support 20.Second flitch 400 is set, then placement of multiple layers plate 500 on second flitch 400 on the over brace 100.Regulate second nut 38; The body 380 of second nut 38 drives channel-section steel support 36 and moves, and moves thereby make channel-section steel support 36 drive over brace 100, when the upper surface of composite board 500 is concordant with the upper surface of first flitch 100; Stop to regulate second nut 38; The body 380 of channel-section steel support 36 butts second nut 38, channel-section steel support 36 is fixing, thereby makes over brace 100 be fixed in vertical rod support 20.This moment, the early-dismantling formwork system installation finished.After floor 300 is built, regulate first nut 37 and second nut 38, screw rod 32 is moved down, make channel-section steel support 36 drive over braces 100 simultaneously and move down, dismantle then first flitch 200, second flitch 400 and composite board 500.
First nut 37 and second nut 38 of the utility model early-dismantling formwork system through regulating vertical rod support 20 reaches construction requirement, convenient construction to regulate the height of vertical rod support 20 and over brace 100.

Claims (8)

1. early-dismantling formwork system; It is characterized in that; Comprise vertical rod support (20) and over brace (100); Said vertical rod support (20) comprises regulates support (30) and vertical rod (40), and said over brace (100) is installed on said adjusting support (30), and said adjusting support (30) is installed on vertical rod (40) movably.
2. early-dismantling formwork system according to claim 1; It is characterized in that; Said adjusting support (30) comprises that screw rod (32) and adjustable positions are installed on first nut (37) of said screw rod (32) wholely, and said screw rod (32) comprises first end (320) and said first end (320) second opposed end (322), and said vertical rod (40) is provided with accepting hole (42); Second end of said screw rod (32) penetrates said accepting hole (42), and said first nut (37) is replaced said vertical rod (40).
3. early-dismantling formwork system according to claim 2; It is characterized in that; Said adjusting support (30) comprises that also adjustable positions is installed on second nut (38) of said screw rod (32) wholely and is sheathed on the channel-section steel support (36) of said screw rod (32); Said first nut (37) and said second nut (38) are positioned at a side of said channel-section steel support (36), and said channel-section steel support (36) is replaced said second nut (38), and said over brace (100) is fixed in said channel-section steel support (36).
4. early-dismantling formwork system according to claim 3 is characterized in that, said adjusting support (30) also comprises the carriage (34) that is used to be provided with first flitch (200), and said channel-section steel support (36) is positioned between said second nut (38) and the said carriage (34).
5. early-dismantling formwork system according to claim 4; It is characterized in that said carriage (34) comprises and is fixed in said screw rod (32) first ends (320) with steel plate (340) that said first flitch (200) is set and the fixture (342) that is used for fixing said first flitch (200).
6. early-dismantling formwork system according to claim 5 is characterized in that, said fixture (342) is an iron nail, and said steel plate (340) is provided with through hole (344), and said fixture (342) passes through hole (344) and is fixed in said first flitch (100).
7. early-dismantling formwork system according to claim 2 is characterized in that, said first nut (37) comprises the body (370) of the said vertical rod of butt (40) and is positioned at the handle (372) of said body (370) both sides.
8. early-dismantling formwork system according to claim 3 is characterized in that, said second nut (38) comprises the body (380) of replacing said channel-section steel support (36) and is positioned at the handle (382) of said body (380) both sides.
CN2012201886641U 2012-04-27 2012-04-27 Early-dismounting template system Expired - Fee Related CN202544394U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012201886641U CN202544394U (en) 2012-04-27 2012-04-27 Early-dismounting template system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012201886641U CN202544394U (en) 2012-04-27 2012-04-27 Early-dismounting template system

Publications (1)

Publication Number Publication Date
CN202544394U true CN202544394U (en) 2012-11-21

Family

ID=47165046

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012201886641U Expired - Fee Related CN202544394U (en) 2012-04-27 2012-04-27 Early-dismounting template system

Country Status (1)

Country Link
CN (1) CN202544394U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102628319A (en) * 2012-04-27 2012-08-08 南通海洲建设集团有限公司 Early-dismantling formwork system
CN103485541A (en) * 2013-10-11 2014-01-01 广东电白建设集团有限公司 Method for assembling and disassembling wheel-buckled type supporting frame high and large formwork

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102628319A (en) * 2012-04-27 2012-08-08 南通海洲建设集团有限公司 Early-dismantling formwork system
CN103485541A (en) * 2013-10-11 2014-01-01 广东电白建设集团有限公司 Method for assembling and disassembling wheel-buckled type supporting frame high and large formwork

Similar Documents

Publication Publication Date Title
CN208009467U (en) A kind of foundation bolt installation control device
CN202731297U (en) Adjustable beam form support jacking bracket apparatus
CN202380730U (en) Supporting and strengthening device for beam formworks
CN107448689A (en) A kind of hoisting bracket of horizontal pipeline
CN204899947U (en) Subway station formworking jumbo
CN201896365U (en) Installing and fixing device for flat plate pre-embedded piece on surface of concrete
CN103306208A (en) Formwork creeping method for novel 1.6 parabola-shaped four-column type hollow variable section high pier
CN103967273A (en) Concrete formwork supporting device for floor slab concreting
CN202544394U (en) Early-dismounting template system
CN205243006U (en) Side form supports top and holds in palm
CN203175052U (en) Leveler for building floor beam slab construction
CN202347843U (en) Building construction beam frame
CN202081427U (en) Embedded bolt positioning device for tower crane foundation
CN102628319A (en) Early-dismantling formwork system
CN204510842U (en) A kind of steel crane beam installed height mark adjusting device
CN203834370U (en) Arch ring steel formwork trolley for circular arch culvert
CN105114102A (en) Subway station formwork trolley
CN203905488U (en) Concrete formwork supporting device for slab pouring
CN203334192U (en) Steel truss girder jointing rod piece height difference adjusting device
CN203347249U (en) Perpendicularity adjusting device applied to steel column mounting
CN202627494U (en) Device for locating and supporting prefabricated concrete structure laminated slab
CN103088997A (en) Channel steel guide rail for controlling floor elevation and method
CN202194392U (en) Floorslab thickness control device
CN201679232U (en) Adjustable support template mandril
CN204163356U (en) A kind of equipment installing inner wall panel

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Sun Xingchun

Inventor after: Su Yuan

Inventor before: Sun Xingxiang

Inventor before: Su Yuan

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: SUN XINGXIANG SU YUAN TO: SUN XINGCHUN SU YUAN

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121121

Termination date: 20140427