CN202482769U - Novel temporary support used in bridge construction - Google Patents
Novel temporary support used in bridge construction Download PDFInfo
- Publication number
- CN202482769U CN202482769U CN2011205628625U CN201120562862U CN202482769U CN 202482769 U CN202482769 U CN 202482769U CN 2011205628625 U CN2011205628625 U CN 2011205628625U CN 201120562862 U CN201120562862 U CN 201120562862U CN 202482769 U CN202482769 U CN 202482769U
- Authority
- CN
- China
- Prior art keywords
- temporary support
- bridge construction
- bearing block
- carrier layer
- novel temporary
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model relates to a novel temporary support used in bridge construction. The temporary support comprises a lower bearing block, an unloading layer and an upper bearing block, wherein the lower bearing block, the unloading layer and the upper bearing block are stacked in sequence. Liquid materials or solid materials prone to being melted and softened after the solid materials are heated and filled to form the unloading layer, and steel plate layers and rubber blocks are stacked and sticked to form the upper bearing block and the lower bearing block in an intersecting mode. The topmost steel plate of the lower bearing block extends all around and bends upwards to form a spacing side wall provided with a diversion bottom outlet. The temporary support is compressible to certain extent, and therefore overcomes the defects that a traditional temporary support cannot enable a load on a permanent support to gradually increase with the promotion of construction progress and increase of the load of a beam body, while the permanent support compresses and sinks since the permanent support bears the load, and fails to gradually and fully explore a supporting role. The novel temporary support used in the bridge construction also overcomes the defect that the traditional temporary support is disposable, cannot be reused, and the defect of waste of time and energy to remove the temporary support, and therefore can be broadly applied to the bridge construction.
Description
Technical field
The utility model relates to a kind of temporary support of bridge cantilever casting construction.
Background technology
At present, the continuous beam cantilever construction generally uses concrete block or steel pipe, shaped steel to fill up as interim, is equivalent to the effect of temporary support, and is easier for removing, and interim that has is provided with the sulphur-bonded mortar layer above the pad, and there is following defective in this interim pad:
1, materials such as concrete block, mortar, steel pipe, shaped steel all are non-yielding props to beam; Itself does not have compressibilty; This causes in the cantilever construction process, removes before the temporary consolidation; Beam body load in fact major part is all born by interim pad, and the load that permanent bearing bears can not progressively increase along with the increase of the propelling of constructing, beam body load, and the compression subsidence that permanent bearing produces because of bearing load can not progressively fully take place.The generation that forever compression subsidence of bearing just can be abundant, a large amount of after accomplishing cantilever construction, closing up, and this moment, the beam body belonged to statically-indeterminate structure, the compression subsidence of permanent bearing can let the beam body produce the inferior internal force of depression of supports.Though when design, considered the depression problem of permanent bearing; But because the complexity of structure stress; And the operation of removing temporary consolidation is difficult to symmetry and accurately accomplishes simultaneously, the consideration of depression of supports problem is difficult to thoughtfully and fully tally with the actual situation comprehensively; So continuous beam produces structure time internal force because of depression of supports problem still exists, and has the possibility of considerable influence.Produce bigger structure time internal force because of depression of supports and can cause the beam body crack to occur, have influence on the quality and the application life of bridge.If before removing temporary consolidation; Can let the compression subsidence of permanent bearing progressively take place along with the increase of the propelling of constructing, beam body load; Be unlikely to generations just abundant, a large amount of after closing up, the depression of supports that the beam body produces time internal force will be little many.
2, dismantling concrete props up quite trouble of pad temporarily, need be with the method that cuts, and the duration is propped up pad than long and steel pipe.
3, interim traditional pad is disposable use, can not have enough to meet the need use.
Based on this, the temporary support of seeking to overcome above-mentioned defective or reduce above-mentioned defective effect as far as possible is necessary.
The utility model content
The purpose of the utility model provides the novel temporary support that uses in a kind of bridge construction; Solve that existing interim pad peace torn inconvenience, disposable use open and because the Incoercibility of interim pad, cause load that permanent bearing bears can not be along with the increase of the propelling of construction speed and beam body load the problem of increase progressively; Can have enough to meet the need uses, the permanent compression subsidence of the bearing purpose that can progressively take place for reaching interim pad along with the increase of the propelling of construction speed and beam body load.
For realizing above-mentioned purpose, the utility model adopts following technical scheme:
The novel temporary support that uses in a kind of bridge construction; By under hold piece, unload carrier layer and on hold piece and stack gradually and form; Said unload carrier layer by have mobile material or be heated after be easy to melt, softening solid material fills and forms; Hold piece on said and hold down piece and form by steel plate layer and block rubber intersecting bonding, said hold piece down push up a block plate most to the extension of four limits and upwards be bent to form the spacing sidewall that unloads carrier layer, have the pod apertures of the filler outflow of being convenient to unload carrier layer on the said spacing sidewall; In use, guarantee the pod apertures sealing.
The said filler that unloads carrier layer be sand, liquid etc. have mobile material or be heated after be easy to melt, softening solid material.
Adopt when having mobile material when unloading carrier layer, unload between carrier layer and the spacing sidewall and do not reserve the space, and said spacing sidewall top edge exceeds and unloads the carrier layer end face as filler.
When unload carrier layer adopt be easy to after being heated to melt, softening solid material is during as filler; Unload between carrier layer and the spacing sidewall and reserve the space; And on the said spacing sidewall except having pod apertures, also have the power line hole in addition, spacing sidewall top edge is lower than and unloads the carrier layer end face.
Whole whole steel plate layers of parcel of said block rubber or part are wrapped up the steel plate layer.
Compared with prior art the utlity model has following characteristics and beneficial effect:
1, rubber layer is set and has guaranteed that this novel temporary support has certain compressibilty; Can be increased compression along with the increase of beam body load; The load that permanent bearing is born can progressively increase along with the propelling of cantilever casting construction progress; Thereby make the compression subsidence of permanent bearing progressively to take place, be unlikely to generations just abundant, a large amount of after closing up along with the increase of the propelling of construction speed, beam body load.
2, be provided with and unload carrier layer and guaranteed before accomplishing cantilever construction, closing up; Promptly can unload temporary support; Let beam body load bear by permanent bearing fully, solved traditional interim pad and can not before close up, unload, can only after closing up, could unload, can only after closing up, could let the defective of the abundant compression subsidence of permanent bearing.
3, remove quite conveniently, avoided cutting concrete and propped up pad temporarily, remove that steel pipe props up pad, shaped steel props up and fills up the sort of defective that wastes time and energy, effectively save duration and construction cost.
4, the utility model both can use in the bridge cantilever construction, also formerly used in the continuous bridge construction behind the freely-supported, had versatility.
The utility model can be widely used in bridge construction.
Description of drawings
Below in conjunction with accompanying drawing the utility model is done further detailed explanation.
Fig. 1 is the lateral view of the utility model embodiment one.
Fig. 2 is the vertical view of the utility model embodiment one.
Fig. 3 is the side perspective view of the utility model embodiment one.
Fig. 4 is the exploded view of the utility model embodiment one.
Fig. 5 is the A-A sectional view of Fig. 2.
Fig. 6 is the lateral view of the utility model embodiment two.
Fig. 7 is the vertical view of the utility model embodiment two.
Fig. 8 is the side perspective view of the utility model embodiment two.
Fig. 9 is the exploded view of the utility model embodiment two.
Figure 10 is the B-B sectional view of Fig. 7.
Figure 11 is the application sketch map of the utility model.
Figure 12 is the C-C sectional view of Figure 11.
Reference numeral: 1-is last to be held and holds the permanent bearing of cast-in-place sections, 7-, the 8-bridge pier pier shaft that piece, the spacing sidewall of 2.1-, 2.2-pod apertures, 2.3-power line hole, 3-unload carrier layer, 4-space, 5-overturning or slip resistance analysis pull bar, 6-beam body under piece, the 2-.
The specific embodiment
Embodiment one referring to Fig. 1 to shown in Figure 5, the novel temporary support that uses in a kind of bridge construction, by under hold piece 2, unload carrier layer 3 and on hold piece 1 and stack gradually and form.Hold piece 1 on said and hold piece 2 down and formed by steel plate layer and block rubber intersecting bonding, said block rubber is whole to be wrapped up whole steel plate layers or partly wraps up the steel plate layer.The said block plate that pushes up most that holds down piece 2 extends and upwards is bent to form the spacing sidewall 2.1 that unloads carrier layer to four limits, has the pod apertures 2.2 that the filler of being convenient to unload carrier layer flows out on the said spacing sidewall 2.1.This three part is relatively independent, during use, unload carrier layer can with on hold piece, hold that piece is bonding to become whole down.Said unload carrier layer 3 adopt sand or liquid etc. to have mobile material or be heated after be easy to melt, softening solid material is as discharged material.Spacing sidewall 2.1 top edges exceed and unload the carrier layer certain height.When unloading carrier layer when adopting sand etc. to have mobile solid matter as discharged material, discharged material directly is filled in unloads in the carrier layer groove.Adopt liquid as discharged material when unloading carrier layer, unload the cavity structure body that carrier layer adopts independent reservation plughole, inside fills the liquid discharged material; The material of this cavity structure body has suitable intensity, and material itself can not damaged by pressure by the beam body; Simultaneously, the cavity structure body can be compressed, shrivel after the removal discharged material by the beam body, can not stop the beam body to fall; During installation, the cavity structure body unloads carrier layer and is placed in down and holds the unloading in the carrier layer groove of piece, and the plughole that the cavity structure body is reserved is over against the pod apertures of holding down on the spacing sidewall of piece.
Embodiment two, and referring to Fig. 6 to Figure 10, different with embodiment one is, said unload carrier layer 3 adopt be easy to melt after being heated or monoblock solid material softening, that include heating wire as the unloading layer material.It is low that the aspect ratio of spacing sidewall is unloaded carrier layer, and spacing sidewall reserves certain gap with the side of unloading carrier layer, is compressed distortion with convenient unloading layer material after softening.The solid material that is easy to after being heated to melt and soften is certain plastics, sulphur-bonded mortar etc. for example.Said unloading reserved space 4 between carrier layer 3 and the spacing sidewall 2.1.Have power line hole 2.3 on the said spacing sidewall 2.1.Said spacing sidewall 2.1 top edges are lower than and unload carrier layer 3 end faces.
Being used for continuous beam cantilever constructs when using referring to Figure 11 and Figure 12; The utility model and overturning or slip resistance analysis pull bar 5 are used, and said overturning or slip resistance analysis pull bar 5 is the slender type rod member, and the one of which end is embedded in the bridge pier pier shaft 8 below the beam body; The other end is anchored in the cast-in-place sections 6 of beam body; Be supported with permanent bearing 7 between the bridge pier pier shaft 8 below the said beam body and the cast-in-place sections 6 of beam body, said temporary support and overturning or slip resistance analysis pull bar 5 are two rows, and temporary support, overturning or slip resistance analysis pull bar all are symmetrical in the suitable bridge of beam body to axis arranged; Simultaneously, also be symmetrical in the direction across bridge axis arranged of permanent bearing 7.Among the figure, the cuboid piece that is arranged on permanent bearing 7 both sides is the described temporary support of the utility model.
The utility model also can be used for the construction of beam continuous behind the first freely-supported, and this moment is without the overturning or slip resistance analysis pull bar.
The installation operation of this novel temporary support is following: at first, the cleaning pier top is measured the installation site; Secondly, lay down and hold piece 2, sealing pod apertures 2.2; Then, in the groove that the spacing sidewall that holds piece 2 tops down 2.1 forms, fill, lay the unloading layer material, form and unload carrier layer 3, then, lay and hold piece 1, last, the inspection installation quality.
The dismounting working procedure of this novel temporary support is following: at first, open pod apertures removal unloading layer material, need the energized line heating of energising, hold piece on confirming then and fall, hold piece on the artificial assistance in case of necessity; At last, take out whole temporary support, cleaning is used in order to turnover next time.
Claims (6)
1. the novel temporary support that uses in the bridge construction; By under hold piece (2), unload carrier layer (3) and on hold piece (1) and stack gradually and form; It is characterized in that: hold on said piece (1) and under hold piece (2) and form by steel plate layer and block rubber intersecting bonding; Said top one block plate that holds down piece (2) extends and upwards is bent to form spacing sidewall (2.1) to four limits, has pod apertures (2.2) on the said spacing sidewall (2.1).
2. the novel temporary support that uses in the bridge construction according to claim 1 is characterized in that: said unload carrier layer (3) by have mobile material or be heated after the solid matter filling that is easy to melt and soften form.
3. the novel temporary support that uses in the bridge construction according to claim 1 is characterized in that: said unloading between carrier layer (3) and the spacing sidewall (2.1) reserved space (4).
4. the novel temporary support that uses in the bridge construction according to claim 1 is characterized in that: have power line hole (2.3) on the said spacing sidewall (2.1).
5. the novel temporary support that uses in the bridge construction according to claim 1 is characterized in that: said spacing sidewall (2.1) top edge exceeds to unload carrier layer (3) end face or be lower than and unloads carrier layer (3) end face.
6. the novel temporary support that uses in the bridge construction according to claim 1 is characterized in that: whole whole steel plate layers of parcel of said block rubber or part are wrapped up the steel plate layer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011205628625U CN202482769U (en) | 2011-12-29 | 2011-12-29 | Novel temporary support used in bridge construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011205628625U CN202482769U (en) | 2011-12-29 | 2011-12-29 | Novel temporary support used in bridge construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202482769U true CN202482769U (en) | 2012-10-10 |
Family
ID=46957199
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011205628625U Expired - Lifetime CN202482769U (en) | 2011-12-29 | 2011-12-29 | Novel temporary support used in bridge construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202482769U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108166777A (en) * | 2017-12-17 | 2018-06-15 | 哈尔滨理工大学 | Green method for dismounting based on electrothermal way crushing technology |
CN110344322A (en) * | 2019-08-09 | 2019-10-18 | 河南省交通规划设计研究院股份有限公司 | A kind of temporary support and the method using support progress bridge conversion |
CN114164769A (en) * | 2021-12-28 | 2022-03-11 | 招商局重庆交通科研设计院有限公司 | Temporary support for bridge construction |
-
2011
- 2011-12-29 CN CN2011205628625U patent/CN202482769U/en not_active Expired - Lifetime
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108166777A (en) * | 2017-12-17 | 2018-06-15 | 哈尔滨理工大学 | Green method for dismounting based on electrothermal way crushing technology |
CN110344322A (en) * | 2019-08-09 | 2019-10-18 | 河南省交通规划设计研究院股份有限公司 | A kind of temporary support and the method using support progress bridge conversion |
CN110344322B (en) * | 2019-08-09 | 2024-02-06 | 河南省交通规划设计研究院股份有限公司 | Temporary support and method for converting bridge structural system by adopting same |
CN114164769A (en) * | 2021-12-28 | 2022-03-11 | 招商局重庆交通科研设计院有限公司 | Temporary support for bridge construction |
CN114164769B (en) * | 2021-12-28 | 2023-04-14 | 招商局重庆交通科研设计院有限公司 | Temporary support for bridge construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102433845B (en) | Novel temporary solidification system used for continuous beam cantilever construction | |
CN202482769U (en) | Novel temporary support used in bridge construction | |
CN102518046B (en) | Method for eliminating secondary internal force of sinking of support saddle of continuous beam during cantilever construction | |
CN203705266U (en) | Static load testing device for testing engineering pile | |
CN201447670U (en) | Multi-jack synchronous linkage jacking device for bridges | |
CN108589748B (en) | Prefabrication and installation method for shallow water underwater structure | |
CN203008160U (en) | Wall body for top filling of filling wall under beam slab | |
CN110524714A (en) | A kind of super-large diameter UHPC tubular pole production technology and horizontal prefab-form system | |
CN203514260U (en) | Geomembrane anchoring impervious structure | |
CN103276728A (en) | Method for mending and reinforcing pile head | |
CN208633089U (en) | A kind of embedded Monitoring on Earth Pressure device | |
CN212561119U (en) | Consolidate single-column pier case roof beam | |
CN202482777U (en) | Novel temporary solidification system for bridge construction | |
CN206359906U (en) | A kind of floating of overall pulling down old concrete arch bridge removes platform | |
CN209873811U (en) | Subway major structure medium plate also serves as temporary supporting structure | |
CN101906872A (en) | Slip form device and construction process | |
CN209260588U (en) | A kind of Bridge Crack filling clamping device | |
CN106902911A (en) | A kind of hydraulic engineering breaker | |
CN104612016B (en) | One is town road emergency repair method efficiently | |
CN205399216U (en) | Mould is demolishd in step to ballastless track precast box girder end mould | |
CN204679074U (en) | Novel surface observation pier structure | |
CN204551470U (en) | A kind of envelope stake device of anchor jacked pile of improvement | |
CN211036737U (en) | Road and bridge crack reinforcing apparatus | |
CN211228129U (en) | Prefabricated roof beam hoist and mount hole block structure of assembling of festival section | |
CN221456286U (en) | Frame template curing means for cushion cap concrete |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20201022 Address after: 501-2, 1261 Panyu Avenue North, Dalong street, Panyu District, Guangzhou City, Guangdong Province Patentee after: Guangdong Guandi Construction Co., Ltd Address before: Tianhe District Tianrun road Guangzhou City, Guangdong province 510635 No. 445 8 floor Patentee before: GUANGDONG GUANYUE HIGHWAY & BRIDGE Co.,Ltd. |
|
TR01 | Transfer of patent right | ||
CX01 | Expiry of patent term |
Granted publication date: 20121010 |
|
CX01 | Expiry of patent term |