CN201447670U - Multi-jack synchronous linkage jacking device for bridges - Google Patents

Multi-jack synchronous linkage jacking device for bridges Download PDF

Info

Publication number
CN201447670U
CN201447670U CN2009200568584U CN200920056858U CN201447670U CN 201447670 U CN201447670 U CN 201447670U CN 2009200568584 U CN2009200568584 U CN 2009200568584U CN 200920056858 U CN200920056858 U CN 200920056858U CN 201447670 U CN201447670 U CN 201447670U
Authority
CN
China
Prior art keywords
jack
high pressure
oil pump
jacking
flow divider
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2009200568584U
Other languages
Chinese (zh)
Inventor
辛绪权
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANTOU DAHAO MUNICIPAL CONSTRUCTION CO Ltd
Original Assignee
SHANTOU DAHAO MUNICIPAL CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANTOU DAHAO MUNICIPAL CONSTRUCTION CO Ltd filed Critical SHANTOU DAHAO MUNICIPAL CONSTRUCTION CO Ltd
Priority to CN2009200568584U priority Critical patent/CN201447670U/en
Application granted granted Critical
Publication of CN201447670U publication Critical patent/CN201447670U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model discloses a multi-jack synchronous linkage jacking device for bridges. The jacking device comprises an oil pump, a high pressure diverter valve, a high pressure oil pipe and jacks. The oil pump is connected with the high pressure diverter valve by the high pressure oil pipe. At least two jacks are connected with the high pressure diverter valve in parallel, and the oil pump uniformly provides oil for the jacks. The jacks are self-locked jacks. The multi-jack synchronous linkage jacking device for bridges has the advantages of simple structure, simple operation technique and little popularization and application difficulty.

Description

A kind of many tops synchronous interaction bridge jacking device
Technical field
The utility model relates to the bridge construction equipment technical field.
Background technology
It is current job practices commonly used that bridge pad is changed, and it adopts ordinary jack that beam slab jack-up is come, and removes the damage bearing, settles new bearing again.Recently some engineerings have adopted more advanced synchronization of jacking up constructure scheme, utilize computer control that bridge is carried out integral body (particularly direction across bridge) jacking synchronously, accelerated construction speed, particularly farthest reduced the additional internal force that beam slab is produced because of unique relatively, guarantee the quality of beam body, but must break off a friendship during construction; If continuous beam must disconnect continuous part during jacking, could construct.And current each high-speed transit amount is all very big, and bring very big pressure will for owner, road administration and traffic police a couple of days that suspends traffic.If engineering continues for some time, the economic loss and the social influence that bring are inestimable.
Therefore, demand a kind of bridge jacking device of not breaking off a friendship urgently, to overcome above-mentioned defective.
The utility model content
At above-mentioned the deficiencies in the prior art, the purpose of this utility model provides a kind of bridge jacking device, and described bridge jacking apparatus structure is uncomplicated, and operating procedure is simple, and it is little to apply difficulty.
To achieve these goals, the utility model provides a kind of many tops synchronous interaction bridge jacking device, comprise oil pump, high pressure flow divider, high-pressure oil pipe and jack, described oil pump links to each other with described high pressure flow divider by high-pressure oil pipe, and described high pressure flow divider links to each other with described jack by described high-pressure oil pipe; Described jack is more than two, and described jack is unified fuel feeding by the parallel connection of described high pressure flow divider by described oil pump, and described jack is the self-locking jack.
Preferably, described high pressure flow divider equates to the tubing length of each jack.
The beneficial effects of the utility model are: the device construction that the utility model provides is simple, and operation is relatively easily convenient, can operate through certain training, and it is little to apply difficulty; And, use the utility model device and change bearing, the vehicle that can avoid close traffic to bring blocks up, alleviate vehicle and dredge, shunt the pressure that brings, simultaneously, short construction period can be the Construction Party and saves great amount of investment, bring very big economic benefit and social benefit, thereby well solved ubiquitous problem in the present construction technology.
Description of drawings
Fig. 1 is that many tops synchronous interaction bridge jacking device constitutes schematic diagram.
Fig. 2 is the elevation that jack is arranged at pier location.
Fig. 3 is the plan view that jack is arranged at pier location.
The specific embodiment
Below in conjunction with the accompanying drawing of the utility model embodiment, the technical scheme among the utility model embodiment is clearly and completely described, obviously, described embodiment only is the utility model part embodiment, rather than whole embodiment.
With reference to figure 1, many tops synchronous interaction bridge jacking device of the present utility model, comprise oil pump 1, high pressure flow divider 2, high- pressure oil pipe 3,5 and 5 ' and jack 4,4 ', described oil pump 1 links to each other with described high pressure flow divider 2 by high-pressure oil pipe 3, described jack 4 links to each other with 5 ' one end with high-pressure oil pipe 5 respectively with 4 ', and described high-pressure oil pipe 5 is connected with described high pressure flow divider 2 respectively with 5 ' the other end; Described jack is more than two, and described jack 4 and 4 ' is realized in parallel by high pressure flow divider 2, unify fuel feeding by described oil pump.Particularly, described high-pressure oil pipe 5 and 5 ' equal in length.
This jack 4 and 4 ' is the self-locking jack, and described jack 4 comprises self-locking nut 43, piston 42 and oil cylinder 41, and described piston 42 can be installed with up or down in oil cylinder 41; Described jack 4 ' comprises self-locking nut 43 ', piston 42 ' and oil cylinder 41 ', and described piston 42 ' can be installed with in oil cylinder 41 ' up or down.Adopt the mechanical self-latching type jack, the classification jacking, self-locking synchronously, stressed after the self-locking by the self-locking device instead of piston, thoroughly avoided the asynchronous damage that causes lateral ties of beam body.In the jacking process, constantly screw self-locking nut, when above situation occurs, the power that acts on the piston is transferred on the jack cylinder body by self-locking nut, thereby can not damage beam slab or cause the damage of lateral ties.
Embodiment 1: the application of many tops synchronous interaction bridge jacking device
Present embodiment is connected in parallel on the jack of same model on the isobaric flow divider, by same oil pump feed, has realized that each jack top lift is identical.Self-locking nut rotates with piston stroke when jacking or the beam that falls (plate), guaranteed under various rough sledding jack synchronously, self-locking jack-up system safety, reliable synchronously.Concrete example is as follows:
1, lectotype selection
1) top lifting height of jack requires: the overall height according to bridge pinner and bearing is about 25 centimetres, the height of single jack is 18 centimetres, and the stroke of jack is 5 centimetres, and the jacking overall height of jack is 23 centimetres, at jack each pading plate up and down, can satisfy construction requirement again.
2) the jacking Capability Requirement of jack: the beam slab weight of pressing bridge is calculated, and gets the safety guarantee of 4 times of jack top power, and selecting single jacking ability for use is the 1000KN jack.
3) quantitative requirement of jack: arranging that by the width of cloth about every beam (plate) principle of a jack selects the number of jack, is 14 20 meters long hollow beam slab according to the wideest bridge of required processing, and getting 28 jack can meet the demands.
4) supporting facility: as oil pump, high pressure flow divider, high-pressure oil pipe etc.
2, construction technology:
1) jacking is prepared
Between beam body bottom and bent cap, enough headroom cracks are arranged, can hold jack, can set up support 13; As some local bearing pad stone insufficient height of bridge, cause bent cap 17 and beam body 10 bottom spacing headroom minimum, can't put ordinary jack, will under bridge, set up support 13, or set up bracing frame by pier 14, place jack 15 thereon.Shrinkage joint, bridge floor be residual a large amount of building wastes on bent cap in construction or when maintenance continuously, remove the building waste on the bent cap.On bent cap, reserve the jack position, irregular bent cap end face is carried out preliminary chipping, again with the levelling of polishing of angle grinding machine, until checking that with spirit level planeness is qualified.
2) connection of jack
The lift-up device of top synchronous interaction more than of selecting for use 28 slim jack of a cover to form, be connected with oil pump with oil pipe one end earlier, the other end is connected with the high pressure flow divider, and 28 oil-outs of flow divider are connected with each jack 15 by 28 isometric high-pressure oil pipes.During connection, each interface of scrutiny can not have oil leakage phenomenon, finds to have leakage of oil, connect again.
3) jack is installed
For jack 15 center and the bridge superstructure center of making a concerted effort of making a concerted effort is overlapped, superstructure is stressed again little, should as close as possible bearing 12 installations when placing jack, but to avoid that 12 replacings impact to bearing.Vertically upward stressed when making jacking, jack 15 bottom surfaces must level.
On abutment/bridge pier 14, place earlier a thickness from the position of beam-ends 30cm and be 20 centimetres steel plate 11 in bottom, beam slab termination, on steel plate 11, put jack 15, place a same steel plate 11 on the jack 15 again, if jack 15 and hollowcore slab contact surface 10 also has the space, just add steel plate 11 again and level up and pad; Two width of cloth are all installed jack about abutment/material successively, check one by one whether jack is in place, and starts oil pump, carry out synchronous classification jacking.
4) synchronization of jacking up
The beginning jacking makes jack 15 contact with soffit 10, fastens oil pump, again jack is checked one by one, to not positive adjusting is installed, start oil pump again, so that the steel plate 11 on the jack contacts fully with soffit 10, stop and measure the height of jack, continue jacking again, beam slab 10 and bearing 12 are disengaged, the height of jacking this moment can not be above 6 millimeters, the oil pump that stops, the adjustment of beginning bearing with change operation.
Many tops of the utility model synchronous interaction bridge jacking device creatively combines synchronization of jacking up with the self-locking jack, a kind of isolated plant of not close traffic jacking bridge is provided.The device construction that this utility model provides is simple, and operation is relatively easily convenient, can operate through certain training, and it is little to apply difficulty; And, to use the utility model device and change bearing, the vehicle that can avoid close traffic to bring blocks up, and alleviate vehicle and dredge, shunt the pressure that brings, and short construction period, bring good society and economic benefit.
Above disclosed only is preferred embodiment of the present utility model, can not limit the interest field of the utility model certainly with this, and therefore the equivalent variations of being done according to the utility model claim still belongs to the scope that the utility model is contained.

Claims (2)

1. the bridge jacking of top synchronous interaction more than kind device, comprise oil pump, high pressure flow divider, high-pressure oil pipe and jack, described oil pump links to each other with described high pressure flow divider by high-pressure oil pipe, it is characterized in that: described jack is more than two, described jack is by the parallel connection of described high pressure flow divider, unify fuel feeding by described oil pump, described jack is the self-locking jack.
2. many tops synchronous interaction bridge jacking device according to claim 1 is characterized in that: described high pressure flow divider equates to the tubing length of each jack.
CN2009200568584U 2009-05-19 2009-05-19 Multi-jack synchronous linkage jacking device for bridges Expired - Lifetime CN201447670U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009200568584U CN201447670U (en) 2009-05-19 2009-05-19 Multi-jack synchronous linkage jacking device for bridges

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009200568584U CN201447670U (en) 2009-05-19 2009-05-19 Multi-jack synchronous linkage jacking device for bridges

Publications (1)

Publication Number Publication Date
CN201447670U true CN201447670U (en) 2010-05-05

Family

ID=42552386

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009200568584U Expired - Lifetime CN201447670U (en) 2009-05-19 2009-05-19 Multi-jack synchronous linkage jacking device for bridges

Country Status (1)

Country Link
CN (1) CN201447670U (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892636A (en) * 2010-08-12 2010-11-24 上海先为土木工程有限公司 Integral lifting reconstruction method for high-span overweight continuous box girder
CN102180426A (en) * 2011-04-28 2011-09-14 上海城建(集团)公司 Follow-up supporting device and method
CN102505642A (en) * 2011-10-29 2012-06-20 中铁一局集团有限公司 Control system for integrated synchronous jacking of cut pier and control method
CN106320193A (en) * 2016-11-09 2017-01-11 郑州航空工业管理学院 Method for leveling bridge support during replacement and new installation
CN106567339A (en) * 2016-11-09 2017-04-19 中交路桥华东工程有限公司 Pi-shaped superposed beam reverse jacking system
CN108004938A (en) * 2017-12-29 2018-05-08 上海市机械施工集团有限公司 Control structure and method for the hydraulic jack of U beams installation
CN109826107A (en) * 2019-03-25 2019-05-31 中国十九冶集团有限公司 Component support system and its application method
CN110181650A (en) * 2019-06-03 2019-08-30 中国铁道科学研究院集团有限公司铁道建筑研究所 A kind of prefabricated case beam template synchronous jacking system and its control method
CN111908362A (en) * 2020-08-31 2020-11-10 广西桂冠电力股份有限公司大化水力发电总厂 Main transformer jacking method and device

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892636A (en) * 2010-08-12 2010-11-24 上海先为土木工程有限公司 Integral lifting reconstruction method for high-span overweight continuous box girder
CN102180426A (en) * 2011-04-28 2011-09-14 上海城建(集团)公司 Follow-up supporting device and method
CN102180426B (en) * 2011-04-28 2015-04-22 上海城建(集团)公司 Follow-up supporting device and method
CN102505642A (en) * 2011-10-29 2012-06-20 中铁一局集团有限公司 Control system for integrated synchronous jacking of cut pier and control method
CN102505642B (en) * 2011-10-29 2013-11-13 中铁一局集团有限公司 Control system for integrated synchronous jacking of cut pier and control method
CN106320193A (en) * 2016-11-09 2017-01-11 郑州航空工业管理学院 Method for leveling bridge support during replacement and new installation
CN106567339A (en) * 2016-11-09 2017-04-19 中交路桥华东工程有限公司 Pi-shaped superposed beam reverse jacking system
CN108004938A (en) * 2017-12-29 2018-05-08 上海市机械施工集团有限公司 Control structure and method for the hydraulic jack of U beams installation
CN109826107A (en) * 2019-03-25 2019-05-31 中国十九冶集团有限公司 Component support system and its application method
CN109826107B (en) * 2019-03-25 2020-06-16 中国十九冶集团有限公司 Component support system and method of use
CN110181650A (en) * 2019-06-03 2019-08-30 中国铁道科学研究院集团有限公司铁道建筑研究所 A kind of prefabricated case beam template synchronous jacking system and its control method
CN111908362A (en) * 2020-08-31 2020-11-10 广西桂冠电力股份有限公司大化水力发电总厂 Main transformer jacking method and device

Similar Documents

Publication Publication Date Title
CN201447670U (en) Multi-jack synchronous linkage jacking device for bridges
CN106087757B (en) A high position in box beam erection falls beam construction method
CN100540809C (en) The replacing supporters for continuous beam without breaking off traffic method
CN205676785U (en) Leveling block formwork for placing device at the bottom of a kind of Bridge Support Replacement beam
CN105201219B (en) A kind of structure synchronization discharge mechanism and its construction method
CN203498758U (en) Lever-type prepressing bracket device
CN201198166Y (en) Track plate steel mould
CN201990944U (en) Bridge surface continuous device with combined structure
CN206800220U (en) One kind is used for across highway old bridge removal Fast Installation adjustable support
CN218560124U (en) Track roof beam stock is changed and is used sideslip device
CN107059574A (en) A kind of method of concrete structure and its prefabricated assembled cement concrete pavement of leveling
CN105297643A (en) Method for replacing support of hollow slab type bridge
CN201648890U (en) Displacement resisting control frame for construction of curve segment of track slab
CN201989219U (en) Lifting jack for demoulding steel formwork
CN105155482A (en) Hydraulic dam with built-in driving and supporting mechanism and application method of hydraulic dam
CN213013958U (en) Tamping device for road and bridge construction
CN205088644U (en) Built -in drive supporting mechanism hydraulic pressure dam
CN203307837U (en) Foundation bolt pouring positioning device
CN209277586U (en) A kind of concrete column core cushion block for building jacking increasing layer
CN206986701U (en) A kind of steel box girder bridge Program for structural Transformation system
CN210368464U (en) Ballastless track structure with embedded lifting device
CN203004055U (en) Sleeper line mould overturning structure
CN206901725U (en) A kind of work manhole cover plate electric open device
CN204343245U (en) Harbour transfer station differential settlement levelling device
CN216690431U (en) Steel pipe stand elevation adjusting device under finite space

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20100505

CX01 Expiry of patent term