CN209873811U - Subway major structure medium plate also serves as temporary supporting structure - Google Patents

Subway major structure medium plate also serves as temporary supporting structure Download PDF

Info

Publication number
CN209873811U
CN209873811U CN201822270591.0U CN201822270591U CN209873811U CN 209873811 U CN209873811 U CN 209873811U CN 201822270591 U CN201822270591 U CN 201822270591U CN 209873811 U CN209873811 U CN 209873811U
Authority
CN
China
Prior art keywords
continuous wall
middle plate
plate
reserved
subway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822270591.0U
Other languages
Chinese (zh)
Inventor
罗伟
欧阳院平
颜昌伟
游中琼
刘嫦娥
陈来发
朱敏
韩煊
李哲旭
余婧杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changjiang Institute of Survey Planning Design and Research Co Ltd
Original Assignee
Changjiang Institute of Survey Planning Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changjiang Institute of Survey Planning Design and Research Co Ltd filed Critical Changjiang Institute of Survey Planning Design and Research Co Ltd
Priority to CN201822270591.0U priority Critical patent/CN209873811U/en
Application granted granted Critical
Publication of CN209873811U publication Critical patent/CN209873811U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model belongs to the technical field of the subway engineering construction, specifically be a hold temporary support structure with subway major structure medium plate concurrently. The utility model comprises a middle plate, a continuous wall, side walls and lattice columns, wherein both ends of the middle plate are connected with the continuous wall through the reserved steel bars of the continuous wall and the oblique lacing wires of the middle plate; the middle part of the middle plate is supported by a horizontal tray and a supporting tray batten plate welded on the lattice column; a small section of the side wall is arranged above and below the joint of the middle plate and the continuous wall; reserving a transverse grouting pipe on the side wall close to the continuous wall; and a reserved vertical grouting pipe is connected with the transverse grouting pipe. The utility model discloses the one side can reduce one and support to twice concrete, shortens construction period greatly, saves the investment, and on the other hand, medium plate structure rigidity is big, and is favorable to foundation ditch retaining structure safety, can effectively improve foundation ditch overall stability, reduces foundation ditch construction risk.

Description

Subway major structure medium plate also serves as temporary supporting structure
Technical Field
The utility model belongs to the technical field of the subway engineering construction, specifically a subway major structure medium plate double as interim bearing structure.
Background
The conventional subway foundation pit construction is that a building enclosure structure (a continuous wall or a cast-in-place pile and the like) is firstly constructed, then supports of all the ways are gradually excavated and constructed, a station bottom plate is poured after the supports are excavated to the bottom of a foundation pit, then an upper support is dismantled, a side wall and a middle plate are poured, and a main structure is gradually poured upwards. The temporary support in the subway foundation pit construction is large in investment, but the service cycle is short, and the temporary support can be removed after being used for several months, so that a large amount of manpower and material resources are consumed for pouring and removing, a large amount of construction period is consumed for waiting for the concrete setting period and chiseling and removing, and the environment is also adversely affected by treating the construction waste.
SUMMERY OF THE UTILITY MODEL
To the above problem, the utility model provides a subway major structure medium plate is as interim bearing structure concurrently, is under construction with the major structure medium plate earlier in the subway engineering construction, does interim support with the major structure medium plate concurrently.
The utility model relates to a subway main structure medium plate which is used as a temporary supporting structure, comprising a medium plate, a continuous wall, a side wall and a lattice column; two ends of the middle plate are connected with the continuous wall through reserved steel bars of the continuous wall and the middle plate inclined lacing bars; the middle part of the middle plate is supported by a horizontal tray and a supporting tray batten plate welded on the lattice column; a small section of the side wall is arranged above and below the joint of the middle plate and the continuous wall; reserving a transverse grouting pipe on the side wall close to the continuous wall; and a reserved vertical grouting pipe is connected with the transverse grouting pipe.
Furthermore, the reserved steel bars of the continuous wall are reserved steel bars of the continuous wall; and the middle plate oblique lacing wire is welded with the main rib of the continuous wall.
Furthermore, the height of the horizontal tray is equal to the height of the bottom surface of the middle plate.
Furthermore, the reserved surface at the lower end of the side wall is an inclined surface facing the foundation pit.
Furthermore, main body side wall steel bars, a steel bar connector and a water stop steel plate are reserved in the side walls.
Furthermore, the vertical grouting pipes are connected with the transverse grouting pipes every 3 m.
Station major structure medium plate rigidity is big, and the position is close with the supported position, the utility model discloses a change the work procedure, be under construction earlier with the station major structure medium plate, it is big to utilize station medium plate rigidity, and the suitable characteristics in position replace the second with the medium plate and say or support with the third. One can reduce one like this and support to the twice, shorten construction period greatly and save the investment, on the other hand, medium plate rigidity is big, can effectively improve foundation ditch overall stability, reduces foundation ditch construction risk.
The utility model discloses follow decrement (Reduce) principle in resource recycling economy's 3R principle, realized that concrete support decrement uses among the interim envelope, had following advantage: firstly, the pouring and dismantling cost of the temporary structure is reduced, the discharge of construction waste is reduced, and the environmental pollution is reduced; secondly, concrete support pouring, a waiting setting period and a concrete dismantling period are saved, and the construction period can be effectively saved; and the medium plate structure has high rigidity, is safe and beneficial to the foundation pit support structure, and can effectively reduce the foundation pit excavation risk. The utility model has the advantages of easy operation, can bring better economic benefits and social.
Drawings
Fig. 1 is a schematic cross-sectional view of a conventional foundation pit support.
Fig. 2 is a schematic view of a main structure of a subway station.
Figure 3 is the utility model discloses a excavation supporting section schematic diagram.
Fig. 4 is a schematic view of the connection between the middle plate and the continuous wall.
Fig. 5 is a schematic diagram of a middle plate and a lattice column node.
Fig. 6 is a schematic diagram of a lattice column pallet node.
Wherein: 1. the concrete wall comprises a middle plate, 2 continuous walls, 3 concrete supports, 4 reinforcing steel bar connectors, 5 main body side wall reinforcing steel bars, 6 side walls, 7 water stop steel plates, 8 vertical grouting pipes, 9 transverse grouting pipes, 10 continuous wall reserved reinforcing steel bars, 11 middle plate inclined lacing bars, 12 latticed columns, 13 support tray batten plates, 14 horizontal trays, 15 bottom plates and 16 top plates.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings and specific embodiments. The embodiment is implemented on the premise of the technical solution of the present invention, and a detailed implementation manner and a specific operation process are given, but the scope of the present invention is not limited to the following embodiments.
As shown in fig. 1-2, in the conventional subway foundation pit construction, a building enclosure structure such as a continuous wall 2 is firstly constructed, then concrete supports 3 are gradually excavated and constructed, a station bottom plate 15 is poured after the concrete supports 3 are excavated to the bottom of the foundation pit, then the upper concrete supports 3 are removed, side walls 6 and a middle plate 1 are poured, and a main structure is gradually poured upwards.
As shown in fig. 3, the utility model discloses a subway major structure medium plate doubles as interim bearing structure is through changing the work progress, with station major structure medium plate 1 first construction, utilizes 1 rigidity of station medium plate big, the suitable characteristics in position, replaces the second with medium plate 1 or supports 3 with third concrete.
As shown in fig. 2 to 6, the middle plate of the subway main structure also serves as a temporary support structure, and comprises a middle plate 1, a continuous wall 2, side walls 6 and lattice columns 12; two ends of the middle plate 1 are connected with the continuous wall 2 through reserved continuous wall steel bars 10 and middle plate oblique lacing wires 11; the middle part of the middle plate 1 is supported by a horizontal tray 14 and a support tray batten plate 13 which are welded on the lattice column 12; a small section of the side wall 6 is arranged above and below the joint of the middle plate 1 and the continuous wall 2; a transverse grouting pipe 9 is reserved on the side, close to the continuous wall 2, of the side wall 6; reserved vertical grouting pipes 8 are connected with the horizontal grouting pipes 9 every 3 m.
The reserved steel bars 10 of the continuous wall are reserved steel bars of the continuous wall 2; the middle plate inclined lacing wire 11 is welded with the main rib of the continuous wall 2.
The height of the horizontal tray 14 is equal to the height of the bottom surface of the middle plate 1.
The upper reserved surface and the lower reserved surface of the side wall 6 both need to be roughened, and the lower reserved surface is an inclined surface towards the foundation pit. The side wall 6 needs to reserve the main body side wall steel bars 5 and the steel bar connector 4 according to design requirements, and needs to pre-embed a water stop steel plate 7 in the side wall 6.
The utility model discloses to construct earlier the major structure medium plate of back construction originally, replace the concrete support in the excavation supporting system originally, through certain constructional measures, solve medium plate structure load, side wall concreting and the waterproof scheduling problem of construction joint that medium plate structure construction earlier arouses, embody as follows specifically:
(1) when a temporary enclosure structure (a continuous wall or an enclosure pile) is constructed, a continuous wall reserved steel bar 10 is required to be reserved and used as a connecting steel bar of the main structure middle plate 1 to bear the structural load of the middle plate 1;
(2) besides the supporting function of the connecting part of the two ends of the middle plate 1 and the enclosure structure, the lattice column 12 in the existing foundation pit or the newly arranged upright column is generally used for supporting the structural load of the middle plate 1;
(3) constructing a small section of side wall 6 above and below the middle plate 1 at the joint of the middle plate 1 and the continuous wall 2 respectively, and adopting special structural measures to ensure the later-stage dense concrete pouring and convenient construction of the side wall and ensure the construction quality of a main structure;
(4) grouting construction measures need to be reserved at the joints of the side walls 6 so as to ensure effective water resistance of later construction joints.
Details not described in this specification are within the skill of the art that are well known to those skilled in the art.

Claims (6)

1. Subway major structure medium plate doubles as interim bearing structure, including medium plate (1), continuous wall (2), side wall (6), lattice column (12), its characterized in that: two ends of the middle plate (1) are connected with the continuous wall (2) through reserved continuous wall steel bars (10) and middle plate oblique lacing wires (11); the middle part of the middle plate (1) is supported by a horizontal tray (14) and a supporting tray batten plate (13) which are welded on the lattice column (12); a small section of the side wall (6) is arranged above and below the joint of the middle plate (1) and the continuous wall (2); a transverse grouting pipe (9) is reserved on the side, close to the continuous wall (2), of the side wall (6); a reserved vertical grouting pipe (8) is connected with a transverse grouting pipe (9).
2. The slab doubling as a temporary support structure in a subway main body structure as claimed in claim 1, wherein: the reserved steel bars (10) of the continuous wall are reserved steel bars of the continuous wall (2); the middle plate inclined lacing wire (11) is welded with the main rib of the continuous wall (2).
3. The slab doubling as a temporary support structure in a subway main body structure as claimed in claim 1 or 2, wherein: the height of the horizontal tray (14) is equal to the height of the bottom surface of the middle plate (1).
4. The slab doubling as a temporary support structure in a subway main body structure as claimed in claim 2, wherein: the reserved surface at the lower end of the side wall (6) is an inclined surface facing the foundation pit.
5. The slab doubling as a temporary support structure in a subway main body structure as claimed in claim 4, wherein: and main side wall steel bars (5), a steel bar connector (4) and a water stop steel plate (7) are reserved in the side wall (6).
6. The slab doubling as a temporary support structure in a subway main body structure as claimed in claim 5, wherein: the vertical grouting pipes (8) are connected with the transverse grouting pipes (9) every 3 m.
CN201822270591.0U 2018-12-29 2018-12-29 Subway major structure medium plate also serves as temporary supporting structure Active CN209873811U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822270591.0U CN209873811U (en) 2018-12-29 2018-12-29 Subway major structure medium plate also serves as temporary supporting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822270591.0U CN209873811U (en) 2018-12-29 2018-12-29 Subway major structure medium plate also serves as temporary supporting structure

Publications (1)

Publication Number Publication Date
CN209873811U true CN209873811U (en) 2019-12-31

Family

ID=68950345

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822270591.0U Active CN209873811U (en) 2018-12-29 2018-12-29 Subway major structure medium plate also serves as temporary supporting structure

Country Status (1)

Country Link
CN (1) CN209873811U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109555130A (en) * 2018-12-29 2019-04-02 长江勘测规划设计研究有限责任公司 Plate doubles as temporary support structure and construction method in subway main body structure
CN113463639A (en) * 2021-07-07 2021-10-01 南京东土建设科技有限公司 Underground continuous wall distributed grouting system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109555130A (en) * 2018-12-29 2019-04-02 长江勘测规划设计研究有限责任公司 Plate doubles as temporary support structure and construction method in subway main body structure
CN109555130B (en) * 2018-12-29 2024-01-05 长江勘测规划设计研究有限责任公司 Middle plate of subway main body structure and temporary supporting structure and construction method
CN113463639A (en) * 2021-07-07 2021-10-01 南京东土建设科技有限公司 Underground continuous wall distributed grouting system

Similar Documents

Publication Publication Date Title
CN107419824A (en) The full precast shear wall structural system of regenerative steel skeleton and construction method
CN209873811U (en) Subway major structure medium plate also serves as temporary supporting structure
CN109812620A (en) Primary concreting large-diameter steel pipe concrete pack method
CN201648978U (en) Tied arch support of bridge location cast-in-situ prestressed concrete continuous beam
CN212866371U (en) Reverse construction method anchoring steel bar type first floor beam column connecting node
CN101906757A (en) Assembly method for replacing plate type rubber support on abutment of highway bridge
CN104762967A (en) Improved anchor rod static pressure pile sealing device and construction method
CN109555130B (en) Middle plate of subway main body structure and temporary supporting structure and construction method
CN217299956U (en) Hollow floor supporting mechanism
CN215594046U (en) Asynchronous construction roof of depth foundation ditch trades and props structure
CN212506301U (en) Support system in combination assembled forever
CN111894036B (en) Construction method for additionally arranging basement on strip-shaped foundation building
CN212175798U (en) Whole strutting arrangement of deep basal pit
CN204551470U (en) A kind of envelope stake device of anchor jacked pile of improvement
CN211922707U (en) Special-shaped deformation joint template for bottom plate of underground comprehensive pipe gallery
CN109778806B (en) Construction method for integrally sliding and lifting pier wall with connecting beam
CN206359993U (en) Stud structure for main transformer fire wall
CN216339318U (en) Template device is consolidated to bank protection for hydraulic construction engineering
CN204126345U (en) A kind of indoor coal storage yard
CN219327318U (en) Water tank type template with narrow groove structure
CN211948320U (en) Structure of steel pipe square and round transition section
CN217378995U (en) Basement outer wall semi-reverse construction method construction structure
CN218522366U (en) Bearing 2000T wine jar overhauls ditch
CN218373902U (en) Building foundation ditch angle brace device
CN217897380U (en) Box type steel pipe reinforced concrete frame beam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant