CN202337949U - Bridge jacking device - Google Patents
Bridge jacking device Download PDFInfo
- Publication number
- CN202337949U CN202337949U CN201120455140XU CN201120455140U CN202337949U CN 202337949 U CN202337949 U CN 202337949U CN 201120455140X U CN201120455140X U CN 201120455140XU CN 201120455140 U CN201120455140 U CN 201120455140U CN 202337949 U CN202337949 U CN 202337949U
- Authority
- CN
- China
- Prior art keywords
- jacking
- bridge
- abutment
- counterforce device
- control system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model provides a bridge jacking device, which comprises a programmable logic controller (PLC) hydraulic synchronization jacking control system, a jack deployed by the PLC hydraulic synchronization jacking control system, and a jacking counterforce unit cooperating with the PLC hydraulic synchronization jacking control system to provide support for the jack. The bridge jacking device has the advantages that reliable bearing capacity, synchronism and the whole load bearing capability are provided for bridge jacking; and the jacking counterforce unit can be a metal structure pedant mounted on abutments to bear the jacking counterforce, so that the jacking counterforce unit is convenient to dismount, and is capable of being recycled and effectively saving resource and reducing the construction period.
Description
Technical field
The utility model relates to a kind of building jacking engineering support system, especially a kind of bridge jacking engineering support system.
Background technology
At present, job practices commonly used is to seek utilizable brace foundation in the bridge jacking engineering, adopts the jacking jack to carry out jacking by brace foundation.What generally the most often utilize is exactly the space on original basis or the abutment (abutment or pier stud); But tend to run into the cost that original basis is difficult to utilize or utilize is too high, the duration is long or abutment (abutment or pier stud) on the space too little, can not satisfy the condition that jack is laid.
In the case, a kind of can be imperative for the jacking jack provides the utility model of effective supporting plane and reaction of bearing jacking top bridge.
The utility model content
The technical problem that the utility model will solve is: overcome the deficiency that exists in the prior art; Provide a kind of and when the bridge tale quale can not be utilized, still can the oneself create virtual plane, thereby the bridge jacking apparatus and method of reliable assurance are provided for the bridge jacking engineering with effective support top jacking bridge.
The utility model is realized through following technical scheme:
That is: a kind of bridge jacking device; It comprises PLC Hydraulic Synchronizing jacking control system, the jack under the allotment of aforementioned PLC Hydraulic Synchronizing jacking control system; It is characterized in that it also comprises: matching with PLC Hydraulic Synchronizing jacking control system is combined into the jacking counterforce device that jack provides support.
Said jacking counterforce device is installed in the jacking counterforce device that carries the jacking counter-force on the abutment on original bridge abutment, planting reinforcing bar as jacking counter-force basic jacking counterforce device or metal construction suspension member.
The jacking counterforce device that said metal construction suspension member is installed in carrying jacking counter-force on the abutment is arranged under the plate seam of two adjacent plate-girders, and is connected with abutment through bar planting.Certainly, this bracket is applicable to the jacking of different types of rridges, is not limited to slab and girder, and its position is also not only in the plate seam of adjacent plate-girder.
Said jacking counterforce device can be removed.
A kind of bridge jacking method; It comprises PLC Hydraulic Synchronizing jacking control system, the jack under the allotment of aforementioned PLC Hydraulic Synchronizing jacking control system; Matching with PLC Hydraulic Synchronizing jacking control system is combined into the jacking counterforce device that jack provides support, and wherein its jacking step is following:
On bridge bent cap, pier stud or abutment, implant or install the jacking counterforce device;
The jacking counterforce device directly is installed or is used for fixing the jacking counterforce device at bridge bent cap (abutment or pier stud) end face in bridge bent cap (abutment or pier stud) side bar planting;
According to the jacking stroke jack that is fit to is placed in the jacking counterforce device;
Jacking content through PLC Hydraulic Synchronizing jacking control systematic unity allotment jack.
Said jacking counterforce device is directly to install or pass through at original bridge bent cap, abutment or pier stud end face to fix the metal structural component jacking counterforce device as jacking counter-force basis in bent cap, abutment or the bar planting of pier stud end face.
Said metal construction suspension member is installed on bent cap, abutment or the pier stud plate seam that the jacking counterforce device that carries the jacking counter-force is arranged in two adjacent plate-girders down, and through bar planting be connected.
Said jacking counterforce device can be removed and can reuse.
The utlity model has following beneficial effect:
For bridge jacking provides reliable bearing capacity, synchronism and whole stressed property;
The jacking counterforce device can be that the metal construction suspension member is installed in carrying jacking counter-force on the abutment, and convenient the dismounting and recycling can effectively be saved resource and reduction of erection time;
Description of drawings
Combine the description of its accompanying drawing through following embodiment, can further understand and use novel purpose, specific structural features and advantage in fact the utility model.Wherein, accompanying drawing is:
Fig. 1 be the utility model the jacking counterforce device install and use sketch map;
The specific embodiment
The utility model is jacking, the support system that is applied to building jacking engineering, especially a kind of bridge jacking engineering support system.Be to existing jacking, support system, comprise the significant improvement of making on the basis of shortcoming of bracing or strutting arrangement and method for supporting, have very important practice significance.
Below in conjunction with accompanying drawing and embodiment utility model is further specified:
The utility model provides a kind of bridge jacking device and raising method; Said bridge jacking device mainly comprise with PLC Hydraulic Synchronizing jacking control system, under the allotment of PLC Hydraulic Synchronizing jacking control system jack group and match with PLC Hydraulic Synchronizing jacking control system and to be combined into the jacking counterforce device 10 that jack 20 provides support.
Said jacking counterforce device 10 is for to plant reinforcing bar at original bridge bent cap (pier stud or abutment); Also can make concrete, jacking counterforce device or the metal construction suspension member basic as the jacking counter-force are installed in the jacking counterforce device that bent cap (pier stud or abutment) is gone up carrying jacking counter-force; The jacking counterforce device directly is installed or is used for fixing the jacking counterforce device at bridge bent cap (abutment or pier stud) end face in bridge bent cap (abutment or pier stud) side bar planting.Being installed in the last jacking counterforce device that carries the jacking counter-force of bent cap (pier stud or abutment) with the metal construction suspension member in the present embodiment serves as that the master carries out detailed description to jacking counterforce device 10:
The jacking counterforce device 10 of said metal construction suspension member can be any metal with strong hardness; For example steel, iron etc.; It is example that the utility model adopts the jacking counterforce device 10 of steel work suspension member; It is mounted on the abutment and carries the jacking counter-force, and its plate seam that is arranged in two adjacent plate-girders and is connected with bent cap (pier stud or abutment) through bar planting down.Certainly, this bracket is applicable to the jacking of different types of rridges, is not limited to slab and girder, and its position is also not only in the plate seam of adjacent plate-girder.Wherein, The similar bracket of jacking counterforce device 10 shapes; In the industry cycle also often be called as the jacking of bracket counter-force, be provided with in the middle and lower part of jacking counterforce device 10 one with the load plane 101 of the moulding of jacking counterforce device 10 one, be used for specifically carrying jack 20 and its.
In concrete jacking process, promptly be the raising method of main example with the bridge, wherein its jacking step is following:
According to calculating and design to the engineering bridge material; Be installed on the bent cap (pier stud or abutment) 30 of bridge shifting to an earlier date the ready some jacking counterforce devices 10 in back that machine; After before installation, cap being carried out levelling, the method that is employed in the cladding steel corbel of cap is as the counter-force basis.Steel corbel is connected with bent cap (pier stud or abutment) through bar planting;
Can adopt the jack 20 of different strokes according to the requirement of jacking stroke, promptly according to the jacking stroke jack that is fit to is placed in and rise in the counterforce device 10, jack is installed on the load plane 101.
Effectively provide under the prerequisite of carrying the basis at jacking counterforce device 10, the jacking content through PLC Hydraulic Synchronizing jacking control systematic unity allotment jack comprises the jacking synchronous error, jacking load, jacking displacement etc.
Popular says, the utility model is to adopt PLC Hydraulic Synchronizing jacking control system, in conjunction with multinomial technology such as bracket bar planting technology, spacing technology and jacking monitoring, on original bent cap (pier stud or abutment), plants bracket as the counter-force basis, and superstructure is carried out jacking.
Do the method on bracket counter-force basis after promptly adopting and carry out jacking.The jacking of bracket counter-force mainly comprises two kinds, the one, and on original bridge bent cap (pier stud or abutment), plant reinforcing bar and do concrete bracket carrying jacking counter-force basis; The 2nd, do steel work bracket suspension member and be directly installed on the method that bent cap (pier stud or abutment) is gone up carrying jacking counter-force.
Being employed in existing bent cap (pier stud or abutment) outside bar planting (expansion bolt) makes steel corbel and carries out jacking as the counter-force basis.Jack is arranged under the plate seam of two adjacent plate-girders, and the plate-girder bottom is provided with certain thickness steel plate to disperse concentrated stress.The bracket shearing resistance is mainly born by the anti-shear steel plate on top.Electric hammer punching is adopted in bar planting, not destroy the abutment reinforcing bar.
After jacking finishes steel corbel is removed, the reinforcing bar of implanting is cut, and the abutment surface is repaired.
The description of above-mentioned preferred embodiment makes those skilled in the art can make or use the utility model.The various modifications of these embodiment are conspicuous for a person skilled in the art, and the General Principle of definition can be applied among other embodiment and do not deviate from the spirit or the scope of the utility model here.Therefore, the embodiment that the utility model is not limited to illustrate here, and will meet and the principle and the novel feature the most wide in range consistent scope that disclose here.
Claims (4)
1. bridge jacking device; It comprises PLC Hydraulic Synchronizing jacking control system, the jack under the allotment of aforementioned PLC Hydraulic Synchronizing jacking control system; It is characterized in that it also comprises: matching with PLC Hydraulic Synchronizing jacking control system is combined into the jacking counterforce device that jack provides support.
2. bridge jacking device as claimed in claim 1; It is characterized in that said jacking counterforce device is installed in the jacking counterforce device that carries the jacking counter-force on the abutment on original bridge bent cap, pier stud or abutment, planting reinforcing bar as jacking counter-force basic jacking counterforce device or metal construction suspension member.
3. bridge jacking device as claimed in claim 2 is characterized in that, said metal construction suspension member is installed in the web position that the jacking counterforce device that carries the jacking counter-force on the abutment is arranged in the flank or the T beam of plate-girder, case beam, and is connected with abutment through bar planting.
4. like the arbitrary described bridge jacking device of claim 1-3, it is characterized in that said jacking counterforce device can be removed and use repeatedly.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201120455140XU CN202337949U (en) | 2011-11-17 | 2011-11-17 | Bridge jacking device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201120455140XU CN202337949U (en) | 2011-11-17 | 2011-11-17 | Bridge jacking device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202337949U true CN202337949U (en) | 2012-07-18 |
Family
ID=46486647
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201120455140XU Expired - Fee Related CN202337949U (en) | 2011-11-17 | 2011-11-17 | Bridge jacking device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202337949U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104328743A (en) * | 2014-11-24 | 2015-02-04 | 上海天演建筑物移位工程股份有限公司 | Bridge jacking temporary counter-force support device and counter-force support method |
CN110820605A (en) * | 2019-11-07 | 2020-02-21 | 北京中交桥宇科技有限公司 | Airtight nondestructive formula bridge jacking platform of hot melt adhesive |
-
2011
- 2011-11-17 CN CN201120455140XU patent/CN202337949U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104328743A (en) * | 2014-11-24 | 2015-02-04 | 上海天演建筑物移位工程股份有限公司 | Bridge jacking temporary counter-force support device and counter-force support method |
CN110820605A (en) * | 2019-11-07 | 2020-02-21 | 北京中交桥宇科技有限公司 | Airtight nondestructive formula bridge jacking platform of hot melt adhesive |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103216114A (en) | Translation construction method for building | |
CN202324606U (en) | U-shaped force bearing seat | |
CN202337949U (en) | Bridge jacking device | |
CN204960289U (en) | Builder's jack is encorbelmented whole combination of girder steel and can be had enough to meet need anchor assembly | |
CN102561392A (en) | Structure for supporting construction elevator foundation on basement top plate and construction method thereof | |
CN103552911A (en) | Movable hoisting apparatus and construction installation method used by same | |
CN206308702U (en) | A kind of portable basis of derrick crane | |
CN203213019U (en) | Long cantilever bent cap cast-in-place construction support system | |
CN101476330B (en) | Thick and large-volume concrete elastic base and construction method thereof | |
CN202298465U (en) | Bridge jacking system | |
CN202416339U (en) | Fixed base for tower crane | |
CN201381517Y (en) | Concrete elastic base for supporting large-scale gas turbine generator | |
CN213710401U (en) | Can dismantle bottom plate support of steel bar quilting frame building carrier plate | |
CN202644407U (en) | Demoulding device for bottom plate bracket of capping beam constructed by hoop method | |
CN204225503U (en) | Large span steel truss high altitude bulk conversion beam moulding bed | |
CN202000266U (en) | Supporting structure of bridge coping template | |
CN204238443U (en) | A kind of detachable suspension column fastening devices | |
CN204199323U (en) | For the positioning screw hole mould of pre-embedded bolt quick position | |
CN105480842A (en) | Post-cast equipment supporting beam and construction method thereof | |
CN104060819A (en) | Method for constructing shear wall by using typified forms and used typified forms | |
CN208792078U (en) | Temporarily driving passes through device at a kind of notch of novel bridge expansion joint | |
CN207209786U (en) | The cast-in-place boom support monoblock type automatic disassembling device of falsework | |
CN114687567A (en) | Ultrahigh heavy embedded part hanging construction tool and method | |
CN203247591U (en) | Deep foundation pit steel support | |
CN201288329Y (en) | Precision built-in steel mold of ultralong cluster anchor bolt |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120718 Termination date: 20141117 |
|
EXPY | Termination of patent right or utility model |