CN201962932U - Building construction segmented overhung outer scaffold - Google Patents

Building construction segmented overhung outer scaffold Download PDF

Info

Publication number
CN201962932U
CN201962932U CN2010206684469U CN201020668446U CN201962932U CN 201962932 U CN201962932 U CN 201962932U CN 2010206684469 U CN2010206684469 U CN 2010206684469U CN 201020668446 U CN201020668446 U CN 201020668446U CN 201962932 U CN201962932 U CN 201962932U
Authority
CN
China
Prior art keywords
encorbelmenting
overhung
vertical rod
building
segmented
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010206684469U
Other languages
Chinese (zh)
Inventor
周炳高
吴伟剑
周炳泉
丁华杰
沈洪辉
方磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
16TH CONSTRUCTION AND DEVELOPMENT Co Ltd JIANGSU NANTONG NO3 CONSTRUCTION GROUP Co Ltd
Original Assignee
16TH CONSTRUCTION AND DEVELOPMENT Co Ltd JIANGSU NANTONG NO3 CONSTRUCTION GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 16TH CONSTRUCTION AND DEVELOPMENT Co Ltd JIANGSU NANTONG NO3 CONSTRUCTION GROUP Co Ltd filed Critical 16TH CONSTRUCTION AND DEVELOPMENT Co Ltd JIANGSU NANTONG NO3 CONSTRUCTION GROUP Co Ltd
Priority to CN2010206684469U priority Critical patent/CN201962932U/en
Application granted granted Critical
Publication of CN201962932U publication Critical patent/CN201962932U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model relates to a building construction segmented overhung outer scaffold, which is erected by using five to eight floors of building floors as a segment and comprises a scaffold body, overhung sectional steel, an overhung fixed element and a wall connecting rod, wherein the scaffold body is a multi-layer long-shaped framework consisting of a vertical rod, and a small transverse rod and a large transverse rod. The building construction segmented overhung outer scaffold is characterized in that the length of the overhung end of the overhung sectional steel is determined according to the change dimension of the elevation of a building, so the vertical rod maintains the vertical state, and the distances from the vertical rod to the edge of each layer structure are different. The building construction segmented overhung outer scaffold has the following advantages that: 1. the outer scaffold meets the change requirement of gradual layer-by-layer extension and retraction of the edge overhung dimension of each layer structure in the section through the segmented change on the overhung dimension of the overhung sectional steel; and 2. an over-high outer frame is divided into a plurality of segments of mutually independent frame bodies through the segmented turning lapping construction, the investment of turnover materials is greatly reduced, so the construction cost is reduced.

Description

The building operations segmented external scaffolding of encorbelmenting
Technical field
The utility model relates to the scaffold that uses in a kind of building operations, particularly a kind of building operations segmented external scaffolding of encorbelmenting.
Background technology
Along with China's rapid development of economy, the quantity of highrise building is more and more, the moulding of facade also is various variation, local or all flexible for the outer facade plane size of highrise building, facade is the external form that distortion changes, the integral body of tradition use is at present drawn and is hung off-load or the construction technologies such as discharging type external scaffolding and attaching lifting outer climbing frame of encorbelmenting, and is difficult to be suitable for the set up requirement of this type of building operations with external scaffolding.
The utility model content
The purpose of this utility model is to propose a kind of working external scaffolding of encorbelmenting of fabric structure that can adapt to outer facade variation.
The encorbelment technical scheme of external scaffolding of a kind of building operations segmented of the utility model is as follows:
A kind of building operations segmented external scaffolding of encorbelmenting, being one section with building storey 5-8 layer sets up, comprise the scaffold body, the shaped steel of encorbelmenting, encorbelment fixture and wall connecting rod, the scaffold body is by vertical rod, the multilayer elongate frame that little cross bar and leger are formed, the fixture of encorbelmenting is embedded on this section first floor flooring in advance, the end of shaped steel of encorbelmenting is fixed in encorbelments fixture and the other end stretches out the end of encorbelmenting outside the flooring limit, the lower end of vertical rod is supported on the shaped steel of encorbelmenting also fixedly connected, little cross bar is connected in the vertical rod, leger is connected with little cross bar or vertical rod, some wall connecting rods are connected the scaffold body with metope or flooring, all are connected to releasable connection, it is characterized in that: the encorbelment end length of encorbelmenting of shaped steel of every section scaffold is determined according to the varying dimensions of outside vertical surface of building, vertical rod is kept vertically, and vertical rod is unequal from the distance of each layer structural edge.
The encorbelmenting of shaped steel of encorbelmenting held oblique rollering steel silk rope is set.
A kind of building operations segmented of the utility model external scaffolding of encorbelmenting has following advantage:
1, utilizes the segmentation gradual change form of encorbelmenting, external scaffolding sets up each section external scaffolding the easiest available all the time linear pattern by the size of encorbelmenting that segmentation changes the shaped steel of encorbelmenting, and satisfies the size of encorbelmenting of each layer structural edge in the section simultaneously again and successively one stretches the construction techniques that a variation of contracting, the distortion of outer facade change;
2, segmentation is turned over and is taken construction the outrigger of superelevation is divided into the relatively independent support body of plurality of sections, in the safety that has improved external scaffolding, has reduced the input of turnover material widely, thereby has reduced construction cost.
Description of drawings
Fig. 1 is the encorbelment basic structure schematic diagram of external scaffolding of a kind of building operations segmented of the utility model;
Fig. 2 is encorbelment a kind of schematic diagram of external scaffolding of a kind of building operations segmented of the utility model;
Fig. 3 is the encorbelment another kind of schematic diagram of external scaffolding of a kind of building operations segmented of the utility model.
The specific embodiment
A kind of building operations segmented of the utility model external scaffolding of encorbelmenting, the specific embodiment is:
As shown in Figure 1, a kind of building operations segmented of the utility model external scaffolding of encorbelmenting, being one section with building storey 5-8 layer sets up, include scaffold body 1, the shaped steel 2 of encorbelmenting, encorbelment fixture 3 and wall connecting rod 4, the scaffold body is by vertical rod 11, the microscler frame wadding of the multilayer that little cross bar 12 and leger 13 are formed, the fixture 3 of encorbelmenting is embedded on this section first floor flooring in advance, the end of shaped steel 2 of encorbelmenting is fixed in encorbelments fixture 3 and the other end stretches out the end of encorbelmenting outside the flooring limit, the lower end of vertical rod 11 is supported on the end of encorbelmenting of the shaped steel 2 of encorbelmenting and goes up also fixedly connected, little cross bar 12 is connected in the vertical rod 11, leger 13 is connected with little cross bar 12 or vertical rod 11, some wall connecting rods 4 are connected scaffold body 1 with metope or flooring, all are connected to releasable connection, it is characterized in that: the encorbelment end length of encorbelmenting of shaped steel 2 of every section scaffold is determined according to the outside vertical surface of building varying dimensions, make vertical rod 11 keep vertical state, the end of encorbelmenting of the shaped steel 2 of encorbelmenting is provided with oblique rollering steel silk rope 5.
As shown in Figure 2, a kind of building operations segmented of the utility model external scaffolding of encorbelmenting, be applied to the mode of setting up (building structure is for upwards gradual change successively is overhanging) of the complicated distortion highrise building of a kind of outer facade external scaffolding, the segmentation of outer facade situation of change is carried out, 5 layers every section, it is as follows that step is set up in concrete installation:
(1), designs the segmentation number of plies and the gradual change size of scaffold according to the variation characteristics of the outer facade of building structure;
(2), hypomere first floor structure construction, fixture 3 Embedment Construction of encorbelmenting are installed;
(3), hypomere is encorbelmented, and shaped steel 2 is installed and scaffold body 1 is erected on the shaped steel 2 of encorbelmenting, hypomere (5 floor height) is installed oblique rollering steel silk rope 5 when support body is set up 2 layers;
(4), hypomere scaffold top layer upwards prolong take a floor height interim single in protection wadding 6 go along with sb. to guard him as safety;
(5), epimere first floor structure construction, fixture 3 Embedment Construction of encorbelmenting are installed;
(6), epimere is encorbelmented, and shaped steel 2 is installed and support body 1 is set up (because the outer facade of this structure is from the bottom up to overhanging variation, make that upward impotence is encorbelmented shaped steel 2 than the protruding segment distance of hypomere scaffold body), remove the interim single interior protective frame 6 of step 4, epimere support body 1 is retouched oblique rollering steel silk rope 5 is installed when establishing 2 layers;
(7), remove hypomere steel pipe support body and proceed the epimere support body and set up, finish the epimere support body and set up, epimere becomes hypomere;
Above operation (4) one (7) repetitive cycling are carried out, until top section.
In above-mentioned steps, every section support body is independent scaffold system, the hypomere support body can be removed after epimere support body 1 is set up 2 layers to turn over to section and take.
In step 5, before building, floor to carry out the Embedment Construction of shaped steel fulcrum, inner end bearing anchor bar or through-flooring sleeve pipe, and the floor slab structure weak part can be set up and strengthen dark beam construction.
In step 6, the shaped steel of encorbelmenting needs to lay according to the size of layout plan, the type of encorbelmenting copper fulcrum and inner end bearing need be carried out the shaped steel construction of fixedly encorbelmenting, and the shaped steel anchoring of guaranteeing to encorbelment is firm: the bar dowel location and the welding procedure of fixing bracket body vertical rod need be carried out in the shaped steel outer end of encorbelmenting.
The round steel suspension hook by 16-20 is established in oblique rollering steel rope 5 upper ends, and suspension hook is anchored in the structure beam slab, and crotch need be established in round steel anchoring end; The interface point place of the vertical rod of oblique rollering steel silk rope lower end tension scaffolding steel pipe and the shaped steel of encorbelmenting, encorbelment shaped steel bottom surface welding short steel rod fixedly wire rope do not slide; Wire rope length adopts turnbuckle to regulate, and generally answers the pretension wire rope.
As shown in Figure 3, a kind of building operations segmented of the utility model external scaffolding of encorbelmenting, step is set up in the structure of Fig. 3 and installation and Fig. 2 is basic identical, the outer facade of structure that different is is the inwardly gradual change variation of shrinking from the bottom up, make epimere encorbelment shaped steel 2 than hypomere scaffold body to bias internal one segment distance.

Claims (2)

1. building operations segmented external scaffolding of encorbelmenting, being one section with building storey 5-8 layer sets up, comprise the scaffold body, the shaped steel of encorbelmenting, encorbelment fixture and wall connecting rod, the scaffold body is by vertical rod, the multilayer elongate frame that little cross bar and leger are formed, the fixture of encorbelmenting is embedded on this section first floor flooring in advance, the end of shaped steel of encorbelmenting is fixed in encorbelments fixture and the other end stretches out the end of encorbelmenting outside the flooring limit, the lower end of vertical rod is supported on the shaped steel of encorbelmenting also fixedly connected, little cross bar is connected in the vertical rod, leger is connected with little cross bar or vertical rod, some wall connecting rods are connected the scaffold body with metope or flooring, all are connected to releasable connection, it is characterized in that: the encorbelment end length of encorbelmenting of shaped steel of every section scaffold is determined according to the varying dimensions of outside vertical surface of building, vertical rod is kept vertically, and vertical rod is unequal from the distance of each layer structural edge.
2. a kind of building operations segmented according to claim 1 external scaffolding of encorbelmenting is characterized in that: the end of encorbelmenting of the shaped steel of encorbelmenting is provided with oblique rollering steel silk rope.
CN2010206684469U 2010-12-20 2010-12-20 Building construction segmented overhung outer scaffold Expired - Fee Related CN201962932U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010206684469U CN201962932U (en) 2010-12-20 2010-12-20 Building construction segmented overhung outer scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010206684469U CN201962932U (en) 2010-12-20 2010-12-20 Building construction segmented overhung outer scaffold

Publications (1)

Publication Number Publication Date
CN201962932U true CN201962932U (en) 2011-09-07

Family

ID=44525465

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010206684469U Expired - Fee Related CN201962932U (en) 2010-12-20 2010-12-20 Building construction segmented overhung outer scaffold

Country Status (1)

Country Link
CN (1) CN201962932U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102444271A (en) * 2011-11-01 2012-05-09 中建三局建设工程股份有限公司 Suspended scaffolding with cast-in-place concrete structure
CN103496431A (en) * 2013-09-23 2014-01-08 浙江海洋学院 Ship body section hanging plate
CN103821136A (en) * 2014-03-12 2014-05-28 中国建筑第八工程局有限公司 Suspended single row scaffold and construction method thereof
CN107227814A (en) * 2017-06-19 2017-10-03 中国建筑第二工程局有限公司 A kind of large cantilever concrete structure section construction method
CN109372240A (en) * 2018-12-06 2019-02-22 广州丰利达安防科技有限公司 All steel attachment type raise scaffold
CN109403610A (en) * 2018-12-27 2019-03-01 北京城建北方集团有限公司 Move back composite roof truss adhesion type hoisting frame under desk-top special-shaped operating condition
CN114592674A (en) * 2022-03-18 2022-06-07 中铁十一局集团有限公司 Overhanging scaffold and construction method thereof
CN114622710A (en) * 2022-04-11 2022-06-14 中铁建工集团有限公司 High-altitude staggered-layer cantilever structure and construction method thereof

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102444271A (en) * 2011-11-01 2012-05-09 中建三局建设工程股份有限公司 Suspended scaffolding with cast-in-place concrete structure
CN102444271B (en) * 2011-11-01 2015-12-09 中建三局建设工程股份有限公司 Suspended scaffolding
CN103496431A (en) * 2013-09-23 2014-01-08 浙江海洋学院 Ship body section hanging plate
CN103821136A (en) * 2014-03-12 2014-05-28 中国建筑第八工程局有限公司 Suspended single row scaffold and construction method thereof
CN107227814A (en) * 2017-06-19 2017-10-03 中国建筑第二工程局有限公司 A kind of large cantilever concrete structure section construction method
CN107227814B (en) * 2017-06-19 2019-05-03 中国建筑第二工程局有限公司 A kind of large cantilever concrete structure section construction method
CN109372240A (en) * 2018-12-06 2019-02-22 广州丰利达安防科技有限公司 All steel attachment type raise scaffold
CN109403610A (en) * 2018-12-27 2019-03-01 北京城建北方集团有限公司 Move back composite roof truss adhesion type hoisting frame under desk-top special-shaped operating condition
CN114592674A (en) * 2022-03-18 2022-06-07 中铁十一局集团有限公司 Overhanging scaffold and construction method thereof
CN114622710A (en) * 2022-04-11 2022-06-14 中铁建工集团有限公司 High-altitude staggered-layer cantilever structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN201962932U (en) Building construction segmented overhung outer scaffold
CN108643544B (en) High-altitude overhanging construction platform support system and construction method
CN101818570B (en) Method for constructing girder structure conversion layer of high-rise building
CN107100076A (en) A kind of Cast-in-place Bent Cap construction method
CN103643800B (en) The erection & lift system of buckling-restrained bracing member and construction method thereof
CN104131703A (en) Method for constructing core tube wall through self-climbing formwork and adopted self-climbing formwork
CN105133755B (en) A kind of construction method and shear wall structure of reinforcement welding rack composite shear wall
CN103195256A (en) Hanging column type steel structure jig frame construction method
CN103993735A (en) Support system of roof inclined beam and slab cantilever structure and construction method of support system
CN201288415Y (en) Subsection gradual change overhanging type external scaffold for tall building
CN104343214A (en) Bracket prefabricated reinforcement framework of pseudo-classic building, fabrication method of reinforcement framework, and construction method of reinforced concrete bracket of pseudo-classic building
CN105133754A (en) Prefabricated concrete shear wallboard counterbore guide type mounting device and method
CN106012863B (en) A kind of hoisting gate frame and its application method in special-shaped antisymmetry steel Construction of Pylon
CN106567542A (en) Super high-rise double tower building steel structure corridor assembling method
CN102561689B (en) Construction method for cantilever lifting scaffold
CN110847599A (en) Special-shaped column formwork filling reinforcement device and construction method thereof
CN102392532B (en) Construction method for built-in hanging scaffold of high-rise building
CN202023348U (en) Hanging-opening type scaffold
CN211666206U (en) Overhanging and landing dual-purpose scaffold
CN201190408Y (en) Tool type exterior scaffolding of section steel fastening tube
CN106150105A (en) A kind of stiffened column installation method
CN105370027B (en) The construction method of steel supporting platform structure is integrally lifted in high-rise hanging structure
CN104131706A (en) Vertical steel bar two-layer connecting structure of concrete framework structure and construction method of vertical steel bar two-layer connecting structure
CN209585576U (en) A kind of builder's jack
CN102635234A (en) Construction method for controlling thickness of upper-layer steel bar protection layer and board thickness of floorboard

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110907

Termination date: 20151220

EXPY Termination of patent right or utility model