CN201190408Y - Tool type exterior scaffolding of section steel fastening tube - Google Patents

Tool type exterior scaffolding of section steel fastening tube Download PDF

Info

Publication number
CN201190408Y
CN201190408Y CNU200820300696XU CN200820300696U CN201190408Y CN 201190408 Y CN201190408 Y CN 201190408Y CN U200820300696X U CNU200820300696X U CN U200820300696XU CN 200820300696 U CN200820300696 U CN 200820300696U CN 201190408 Y CN201190408 Y CN 201190408Y
Authority
CN
China
Prior art keywords
section steel
building
scaffold
steel beam
tube outer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU200820300696XU
Other languages
Chinese (zh)
Inventor
罗进元
向贵荣
吴晓凤
冯小卫
张光建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Huaxi Group Co Ltd 12th Construction Engineering Co
Original Assignee
Sichuan Huaxi Group Co Ltd 12th Construction Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Huaxi Group Co Ltd 12th Construction Engineering Co filed Critical Sichuan Huaxi Group Co Ltd 12th Construction Engineering Co
Priority to CNU200820300696XU priority Critical patent/CN201190408Y/en
Application granted granted Critical
Publication of CN201190408Y publication Critical patent/CN201190408Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model discloses a steel tube external scaffold for a tool type shaped steel fastener, which is used in building construction. The steel tube external scaffold is more economical, and has wider application range under the premise of ensuring safety. The external scaffold is positioned and supported on a shaped steel beam; one end of the shaped steel beam is fixed on a structural body of a building, and the other end of the shaped steel beam is fixed and connected with the structural body of the building by shearing a wire cable upwards. The structure has the advantages of repeated use and flexible combination, forms the tool type whole set of scaffold system, realizes subsection building and loading, improves the safety factor of the scaffold structure, ensures the construction quality of the scaffold, can increase construction speed, can save construction period and can ensure the successful process of subsequent work. The shaped steel beam is used as a constructional member, and the formed shaped steel beam can be used repeatedly, so the construction cost is greatly reduced. The utility model has favorable economic benefit, and can be popularized and used in the existing building construction.

Description

Tools type section steel fastener steel tube outer scaffold
Technical field
The utility model relates to the external scaffolding that uses in a kind of building operations.
Background technology
At present, along with the continuous development of builing industry and the needs of market economy, highrise building is more and more, and the requirement of external scaffolding also increases thereupon.Existing external scaffolding adopts component and fittings such as steel pipe, fastener, wall-connecting piece, scaffold floor, foot guard plate, safety net and lightning protection to assemble as required to set up usually and forms, steel pipe is divided into cross bar and vertical rod, fastener steel tube outer scaffold after setting up is connected it by wall-connecting piece with major structure of construction, this traditional external scaffolding is generally two-row structure, be also referred to as the console mode external scaffolding, its construction must (JGJ130-2001) require to set up in strict accordance with " building operations fastener type steel pipe scaffold technical specification of security ", has characteristics reusable, flexible combination.For present highrise building, console mode external scaffolding consumption is big, it is long to take the cycle, strengthened the cost of building operations, in addition, existing console mode external scaffolding is narrow and small or be subjected to the local inapplicable of condition restriction for building periphery place, for example: 1, engineering foundation or basement construction are not finished and are not possessed basic acceptance condition and do not carry out the basic earthwork backfill, and engineering must be set up external scaffolding again and carry out major project when rising; When 2, around the agent structure podium being arranged; 3, building is high level or superelevation layer, in the time of should not adopting the console mode external scaffolding.How accomplishing under the premise that security is guaranteed that setting up of external scaffolding is more economical, suitable, easy, is the difficult problem of present builing industry.
The utility model content
Technical problem to be solved in the utility model provides a kind of more economical under the premise that security is guaranteed, tools type section steel fastener steel tube outer scaffold that the scope of application is wider.
The technical scheme that its technical problem that solves the utility model adopts is: tools type section steel fastener steel tube outer scaffold, comprise the external scaffolding that cross bar, vertical rod, fastener, wall-connecting piece and scaffold floor combination are set up, external scaffolding is connected it by wall-connecting piece with the agent structure of building, it is characterized in that: the external scaffolding positioning supports is on section steel beam, one end of section steel beam is fixed on the structure of building, and the other end of section steel beam draws on the structure that is fixedly connected on building by wire rope is upward.
Further be, section steel beam is provided with spacer bars, hanger and baffle plate, section steel beam is fixed by baffle plate and the anchor ring on the structure that is embedded in building, the vertical rod cover of external scaffolding is through on the spacer bars, one end of wire rope is fixed on the hanger, the other end of wire rope is fixed on the ring through walls, and ring through walls is fixed on the structure of building.
Further be that the axial line of section steel beam and wire rope is in the same perpendicular.
Further be many continuous upward the drawing on the structure that is fixedly connected on building of wire rope.
The beneficial effects of the utility model are: reusable, the flexible combination of this external scaffolding, and form a complete set of scaffold system of tool-type, and can realize that segmentation is set up, the segmentation off-load, increased the safety factor of scaffolding structure, guaranteed the scaffold construction quality.Can when not influencing the agent structure rising, in time provide work plane to intert and carry out basic backfill and other work, thereby accelerate speed of application like this from setting up more than two layers, saved the duration, guaranteed carrying out smoothly of follow-up work.Adopt section steel beam to make load-carrying member, the section steel beam of making moulding can be repeatedly used, and greatly reduces engineering cost, and favorable economic benefit is arranged, and can promote the use of in existing building operations.
Description of drawings
Fig. 1 is the structural representation of section steel beam in the utility model.
Fig. 2 is the schematic diagram of a kind of embodiment of the present utility model.
Fig. 3 is the schematic diagram after another kind of embodiment of the present utility model is removed scaffold.
Fig. 4 is the scheme of installation of scissors strut in the utility model.
Be labeled as among the figure: cross bar 1, vertical rod 2, wall-connecting piece 3, scaffold floor 4, section steel beam 6, wire rope 7, spacer bars 8, hanger 9, baffle plate 10, anchor ring 11, ring through walls 12, scissors strut 13, sealing underframe 14.
The specific embodiment
Below in conjunction with drawings and Examples the utility model is further specified.
As Fig. 1~shown in Figure 4, tools type section steel fastener steel tube outer scaffold of the present utility model, set up the formation external scaffolding by combinations such as cross bar 1, vertical rod 2, fastener, wall-connecting piece 3 and scaffold floors 4, external scaffolding is connected it by wall-connecting piece 3 with the agent structure of building, scaffold building height≤24m is safe and reliable to guarantee.The external scaffolding positioning supports can be produced corresponding location structure on section steel beam 6 on section steel beam 6, its external scaffolding can not moved on section steel beam 6.One end of section steel beam 6 is fixed on the structure of building, and the other end of section steel beam 6 is by wire rope 7 upward drawing on the structure that is fixedly connected on building.Because section steel beam 6 is the main support parts, so section steel beam 6 preferably adopts i iron to make.Cross bar 1 and vertical rod 2 can be adopted the steel pipe of φ 48 * 3.5mm, thereby form the double external scaffolding of fastener type steel pipe.Cross bar 1 is divided into long cross bar 1 and short cross bar 1 usually, and long cross bar 1 is roughly parallel to the setting of building external surface, and short cross bar 1 is approximately perpendicular to the setting of building external surface.The setting that this external scaffolding can adopt the vertical rod 2 in vertical rod advance 1.8m, vertical rod transfer 1.0m, scaffold step pitch 1.8m, the outside to build 350mm apart from section steel beam outer end 50mm, inboard vertical rod 2 distances, increase by one flak jacket railing in the middle of 2 per steps of vertical rod in the outside, vertical rod 2 inboards in the outside completely hang the green close order safety net of 2000 orders.The length of section steel beam 6 determines by designing requirement, outer beam segment length 1400mm, 2000mm of building wherein, and installation length should meet design requirement in the building.
For satisfy the external scaffolding positioning supports on the requirement on the section steel beam 6, the structure of convenience type girder steel 6 at building installing and locating and convenient on section steel beam 6 fixing wire rope 7, section steel beam 6 is provided with spacer bars 8, hanger 9 and baffle plate 10.Baffle plate 10 leans against on the wall face of building, section steel beam 6 is by baffle plate 10 and be embedded in anchor ring 11 stationary positioned on the structure of building, vertical rod 2 covers of external scaffolding are through on the spacer bars 8, one end of wire rope 7 is fixed on the hanger 9, the other end of wire rope 7 is fixed on the ring 12 through walls, and ring 12 through walls is fixed on the structure of building.
Initial when setting up floor concreting, design outside the building around the wall pre-buried anchor ring 11 built-in fittings such as grade, hole to be provided on the structure by the scaffold layout, anchor ring 11 can adopt reinforcement fabrication.The effect of anchor ring 11 is exactly the erection support end of fixed girder steel 6, and after section steel beam 6 passed in the ring of anchor ring 11, hard-wood wedge ecto-entad jam-pack can be used in its gap.During installation, should make the section steel beam outer end than inner (being the erection support end) high certain distance, constantly set up rising at external scaffolding, after load continues to increase, when wire rope 7 is tightened up gradually, can produce a spot of displacement deformation, but the decline displacement that distance balance rope 7 distortion that the outer end is enhanced during so initial mount type girder steel 6 are produced, make section steel beam 6 be adjusted to level, when setting up design height with assurance external scaffolding system, connection system for guide rail can not form the flare phenomenon.
When section steel beam 6 is installed, because upper floor does not also form, the work of the wire rope 7 that tiltedly draws can't be finished, so the outer end of section steel beam 6 can only utilize the external scaffolding of lower floor to set up the interim support fixation of elongated horizon bar, section steel beam 6 strong points should be tried one's best near vertical rod 2 places of lower floor's external scaffolding.The interim support of elongated horizon bar should treat that the wire rope 7 that tiltedly draws installs the back and removes.
When external scaffolding was set up, double that sets up 3 vertical rods 2 earlier formed the parent frame, and this parent frame is set up the bar of sweeping the floor together, two step horizon bars, and the place of keeping at a certain distance away sets up the scissors strut 13 of level to guarantee the stability of parent frame on the end face of section steel beam 6.Extend the whole external scaffolding system that sets up from parent frame two ends to both sides then.These all should set up, repeat no more here in strict accordance with " building operations button steel pipe scaffold technical specification of security " JGJ130.
In order to reach best stressed effect, section steel beam 6 preferably is in the same perpendicular with the axial line of wire rope 7.
In order to alleviate the stressed of cross bar 1 and vertical rod 2, can adopt the mode of drawing unloading on the wire rope 7 that adds, i.e. many wire rope 7 continuous upward drawing on the structure that is fixedly connected on building at stressed weakness in position such as the corner of building, balconies.
Integrally-built stable in order to strengthen, be provided with vertical scissors strut 13 in opening part, two ends and the horizontal linear distance of scaffold less than the 15m place, scissors strut 13 is fixed in the vertical rod 2.Vertical scissors strut 13 cross over 6 vertical rods 2 and with horizontal plane at 45~60 ° of angles set up continuously.
Same reason, integrally-built stable in order to strengthen, the end face of section steel beam 6 is provided with the scissors strut 13 and the sealing underframe 14 of level, also sets up continuously in the vertical rod 2 of both sides inside and outside the two ends of the scissors strut 13 of level are connected to.Scissors strut 13 is fixed on the short cross bar 1, with the monolithic stability of reinforcement support body and the job safety of operation layer, prevents that work layer from having people or thing to fall.In section steel beam 6 superolateral vertical rods 2 and sweep the floor and between bar and first long cross bar 1 vertical scissors strut 13 can be set also.
In order to strengthen overall construction intensity, wall-connecting piece 3 can be striden setting by two steps three, and the cross bar 1 in promptly every interval, three vertical rods 2 in interval are provided with a wall-connecting piece 3.
Scaffold floor 4 can all be provided with in per step, but for economical with materials, at operation layer scaffold floor 4 is set usually.
Whole external scaffolding system (JGJ130-2001) requires to set up in strict accordance with " building operations fastener type steel pipe scaffold technical specification of security ", and close order safety net, safe plain net, lightning protection etc. are set.Shelf is set up and is finished, and carries out closure construction with qualified close order safety net, and satisfactory blanket net is set, and work layer is divided into layer net.

Claims (10)

1. tools type section steel fastener steel tube outer scaffold, comprise the external scaffolding that cross bar (1), vertical rod (2), fastener, wall-connecting piece (3) and scaffold floor (4) combination are set up, external scaffolding is connected it by wall-connecting piece (3) with the agent structure of building, it is characterized in that: the external scaffolding positioning supports is on section steel beam (6), one end of section steel beam (6) is fixed on the structure of building, and the other end of section steel beam (6) draws on the structure that is fixedly connected on building by wire rope (7) is upward.
2. tools type section steel fastener steel tube outer scaffold as claimed in claim 1, it is characterized in that: section steel beam (6) is provided with spacer bars (8), hanger (9) and baffle plate (10), section steel beam (6) is fixing by baffle plate (10) and the anchor ring (11) that is embedded on the structure of building, the vertical rod of external scaffolding (2) cover is through on the spacer bars (8), one end of wire rope (7) is fixed on the hanger (9), the other end of wire rope (7) is fixed on the ring through walls (12), and ring through walls (12) is fixed on the structure of building.
3. tools type section steel fastener steel tube outer scaffold as claimed in claim 1 or 2 is characterized in that: section steel beam (6) is in the same perpendicular with the axial line of wire rope (7).
4. tools type section steel fastener steel tube outer scaffold as claimed in claim 1 or 2 is characterized in that: many wire rope (7) are upward drawing on the structure that is fixedly connected on building continuously.
5. tools type section steel fastener steel tube outer scaffold as claimed in claim 1 or 2, it is characterized in that: opening part, two ends and horizontal linear distance at scaffold are provided with vertical scissors strut (13) less than the 15m place, and scissors strut (13) is fixed in the vertical rod (2).
6. tools type section steel fastener steel tube outer scaffold as claimed in claim 5 is characterized in that: vertical scissors strut (13) cross over 6 vertical rods (2) and with horizontal plane at 45~60 ° of angles set up continuously.
7. tools type section steel fastener steel tube outer scaffold as claimed in claim 1 or 2, it is characterized in that: the scissors strut (13) of the level that is provided with that keeps at a certain distance away on the end face of section steel beam (6) and sealing underframe (14), scissors strut (13) is fixed on the short cross bar (1).
8. tools type section steel fastener steel tube outer scaffold as claimed in claim 7 is characterized in that: the two ends of the scissors strut (13) of level are connected to the vertical rod (2) of inside and outside both sides and go up and set up continuously.
9. tools type section steel fastener steel tube outer scaffold as claimed in claim 1 or 2 is characterized in that: wall-connecting piece (3) is striden setting by two steps three.
10. tools type section steel fastener steel tube outer scaffold as claimed in claim 1 or 2 is characterized in that: scaffold floor (4) is arranged on operation layer.
CNU200820300696XU 2008-05-08 2008-05-08 Tool type exterior scaffolding of section steel fastening tube Expired - Fee Related CN201190408Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU200820300696XU CN201190408Y (en) 2008-05-08 2008-05-08 Tool type exterior scaffolding of section steel fastening tube

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU200820300696XU CN201190408Y (en) 2008-05-08 2008-05-08 Tool type exterior scaffolding of section steel fastening tube

Publications (1)

Publication Number Publication Date
CN201190408Y true CN201190408Y (en) 2009-02-04

Family

ID=40334567

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU200820300696XU Expired - Fee Related CN201190408Y (en) 2008-05-08 2008-05-08 Tool type exterior scaffolding of section steel fastening tube

Country Status (1)

Country Link
CN (1) CN201190408Y (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101736893B (en) * 2009-12-16 2011-06-22 通广建工集团有限公司 Overhanging type scaffold supporting system
CN103452302A (en) * 2013-08-20 2013-12-18 广西建工集团第三建筑工程有限责任公司 Safety pre-erecting method of cantilever outer frame
CN111321878A (en) * 2020-02-28 2020-06-23 中国建筑第八工程局有限公司 Conversion construction method for double-layer breathing type curtain wall frame body system
CN113482377A (en) * 2021-06-21 2021-10-08 湖北全洲扬子江建设工程有限公司 Building engineering outward-projecting net device with guiding and sliding functions
CN113482308A (en) * 2021-07-01 2021-10-08 广西建工集团控股有限公司 Construction method of assembled type adjustable overhanging I-steel rigid pull rod outer scaffold

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101736893B (en) * 2009-12-16 2011-06-22 通广建工集团有限公司 Overhanging type scaffold supporting system
CN103452302A (en) * 2013-08-20 2013-12-18 广西建工集团第三建筑工程有限责任公司 Safety pre-erecting method of cantilever outer frame
CN103452302B (en) * 2013-08-20 2015-07-01 广西建工集团第三建筑工程有限责任公司 Safety pre-erecting method of cantilever outer frame
CN111321878A (en) * 2020-02-28 2020-06-23 中国建筑第八工程局有限公司 Conversion construction method for double-layer breathing type curtain wall frame body system
CN113482377A (en) * 2021-06-21 2021-10-08 湖北全洲扬子江建设工程有限公司 Building engineering outward-projecting net device with guiding and sliding functions
CN113482377B (en) * 2021-06-21 2022-06-28 湖北全洲扬子江建设工程有限公司 Building engineering outward-projecting net device with guiding and sliding functions
CN113482308A (en) * 2021-07-01 2021-10-08 广西建工集团控股有限公司 Construction method of assembled type adjustable overhanging I-steel rigid pull rod outer scaffold

Similar Documents

Publication Publication Date Title
CN101265748B (en) Tools type section steel fastener steel tube outer scaffold
CN101736893B (en) Overhanging type scaffold supporting system
CN204662736U (en) Gas concrete out-hung panel slippage node
CN101818570B (en) Method for constructing girder structure conversion layer of high-rise building
CN211447708U (en) Super high-rise building construction elevator feeding platform support system that encorbelments
CN203808484U (en) Integrated cantilevered and attached external scaffolding
CN201190408Y (en) Tool type exterior scaffolding of section steel fastening tube
CN101457572A (en) Fastening strip and fastening network framework
CN109555300A (en) Overhanging scaffold
CN203961238U (en) Bolt anchor slab adjustable tool formula builder's jack
CN206289945U (en) A kind of assembled Portable safety crosshead
CN204001650U (en) Overhanging scaffold for building
CN204299145U (en) For the operating platform that external climbing tower crane support frame is installed
CN103603494A (en) Ultra-thin steel truss inclined wall construction method and formwork structure
CN204456810U (en) A kind of gaily decorated basket pull bar suspension scaffold
CN202731104U (en) Novel reinforcing mesh sheet support structure
CN204960289U (en) Builder's jack is encorbelmented whole combination of girder steel and can be had enough to meet need anchor assembly
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN206634889U (en) Elevator hoistways ins and outs
CN206319597U (en) A kind of cantilever steel girder erecting device
CN211228607U (en) Integrally formed construction structure of outer wall and bottom plate of cast-in-place concrete structure of structure
CN209585576U (en) Overhanging scaffold
CN103615103A (en) Hanging type assembled movable platform
CN203640257U (en) Support of overhanging type scaffold
CN216476335U (en) Inclined frame concrete cylindrical formwork reinforcing system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090204