CN201835524U - Pouring device for concrete beam with top embedded part - Google Patents

Pouring device for concrete beam with top embedded part Download PDF

Info

Publication number
CN201835524U
CN201835524U CN2010205924018U CN201020592401U CN201835524U CN 201835524 U CN201835524 U CN 201835524U CN 2010205924018 U CN2010205924018 U CN 2010205924018U CN 201020592401 U CN201020592401 U CN 201020592401U CN 201835524 U CN201835524 U CN 201835524U
Authority
CN
China
Prior art keywords
concrete
embedded part
concrete beam
grouting
pouring device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010205924018U
Other languages
Chinese (zh)
Inventor
赖晗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN2010205924018U priority Critical patent/CN201835524U/en
Application granted granted Critical
Publication of CN201835524U publication Critical patent/CN201835524U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a pouring device for a concrete beam with a top embedded part. The pouring device comprises a reinforced concrete beam (1), a template (2) and an embedded part (3), and more than one hopper-shaped concrete grouting vibrating hole (4) formed by a concrete grouting vibrating hole side baffle (5) and a concrete grouting vibrating hole inclined baffle (6) is arranged on the template (2) on the side surface of the reinforced concrete beam (1). Arranged on the side surface of the concrete column template (2), the hopper-shaped concrete grouting vibrating hole (4) is used for construction when concrete columns are poured and vibrated, thereby meeting the requirements of a design paper on the installation precision of the embedded part, improving the installation reliability of the top embedded part of the structural beam effectively, and facilitating the construction. The pouring device is applicable to the construction and the installation of the top embedded parts of various concrete beams.

Description

A kind of top has the apparatus for pouring of built-in fitting concrete beam
Technical field
The utility model relates to a kind of apparatus for pouring of concrete beam, particularly relates to the apparatus for pouring that a kind of top has the built-in fitting concrete beam.
Background technology
At present, in industrial construction, the top has the cast of built-in fitting concrete beam, generally be according to sequence of construction at first the colligation beam steel prop up beam forms, prop up beam forms then, fixing built-in fitting, last fluid concrete.There is following deficiency in this method in practical design and construction, when promptly not needing the beam of broad is set for the consideration economy, to cause embedded part width and beam width to differ little, the operating surface width is not enough, make concrete be difficult to cast, vibrating spear is difficult to stretch into, and can't guarantee the vibration compacting of beam, thereby will cause the destruction of beam.For avoiding above shortcoming, the normal processing method that adopts is to pour the beam concrete in the practice of construction, before concrete initial set, embedded part is pressed in the concrete.Handling the deficiency that exists like this is because the inconvenience of concrete resistance and operation often causes the embedded part out-of-flatness, the distortion of the damage of template or embedded part anchor bar, thus do not reach instructions for use from now on.
Summary of the invention
The problem that the utility model solves is: when having embedded part and embedded part big at concrete beam, utilize original device construction can cause the destruction of beam or embedded part not to reach instructions for use from now on, this practical apparatus for pouring that newly provides a kind of top to have the built-in fitting concrete beam.
The technical scheme that the utility model is realized: the utility model comprises concrete beam, template and built-in fitting, and the Side shuttering of concrete beam is provided with the above infundibulate grouting hole of vibrating.
The infundibulate grouting hole of vibrating is made of grouting hole side board and the grouting hole deviation baffle plate that vibrates that vibrates.
The utility model has guaranteed the vibration compacting of concrete beam, has improved the security reliability of concrete beam, makes that embedded part is smooth and has reached required precision to embedded part.
Description of drawings
Accompanying drawing 1 is a structural representation of the present utility model;
1. concrete beam among the figure, 2. concrete beam template, 3. built-in fitting, 4. vibrate hole 4,5. side board, 6. slanting baffle of infundibulate grouting.
The specific embodiment
Embodiment: the utility model such as Fig. 1, during concrete the construction, can be earlier according to the template 2 of the form of construction work strutbeam of no built-in fitting concrete beam 1, in the template 2 of concrete beam 1 the infundibulate grouting hole 4 of vibrating is set then, and according to the fixing back built-in fitting 3 of design drawing, mold forming is once propped up in concrete beam template 2, the grouting of back built-in fitting 3 and the infundibulate hole 4 of vibrating.The infundibulate grouting hole 4 of vibrating is provided with side board 5 and slanting baffle 6, during the concrete beam cast, the cast of no embedded part concrete beam and vibrate and to carry out according to conventional form of construction work, the top has embedded part, concrete can't be poured into a mould or vibrating spear can't stretch into the time, carries out concrete pouring and vibrates by the infundibulate grouting hole 4 of vibrating.Cast finishes after the form removal, and the infundibulate grouting formed concrete block in hole that vibrates is knocked out and gets final product.
Owing to taked this method, and being used of the structure of this method, the installation reliability of structure back embedded part can effectively be improved.

Claims (2)

1. a top has the apparatus for pouring of built-in fitting concrete beam, comprises concrete beam (1), template (2) and built-in fitting (3), it is characterized in that: the Side shuttering (2) of concrete beam (1) is provided with the above infundibulate grouting hole (4) of vibrating.
2. a kind of top according to claim 1 has the apparatus for pouring of built-in fitting concrete beam, it is characterized in that: infundibulate grouting is vibrated hole (4) by grouting hole side board (5) and grouting hole deviation baffle plate (6) formation of vibrating of vibrating.
CN2010205924018U 2010-11-05 2010-11-05 Pouring device for concrete beam with top embedded part Expired - Fee Related CN201835524U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010205924018U CN201835524U (en) 2010-11-05 2010-11-05 Pouring device for concrete beam with top embedded part

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010205924018U CN201835524U (en) 2010-11-05 2010-11-05 Pouring device for concrete beam with top embedded part

Publications (1)

Publication Number Publication Date
CN201835524U true CN201835524U (en) 2011-05-18

Family

ID=44005631

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010205924018U Expired - Fee Related CN201835524U (en) 2010-11-05 2010-11-05 Pouring device for concrete beam with top embedded part

Country Status (1)

Country Link
CN (1) CN201835524U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561692A (en) * 2010-12-22 2012-07-11 贵阳铝镁设计研究院有限公司 Method and template for pouring concrete beam or column with embedded part at top
CN103741948A (en) * 2013-11-29 2014-04-23 中交第四航务工程局有限公司 Grouting method of chamfering of embedded part
CN114961241A (en) * 2022-06-22 2022-08-30 江苏武进建工集团有限公司 Bare concrete V-shaped column formwork supporting system and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561692A (en) * 2010-12-22 2012-07-11 贵阳铝镁设计研究院有限公司 Method and template for pouring concrete beam or column with embedded part at top
CN103741948A (en) * 2013-11-29 2014-04-23 中交第四航务工程局有限公司 Grouting method of chamfering of embedded part
CN103741948B (en) * 2013-11-29 2016-03-30 中交第四航务工程局有限公司 The grouting method of built-in fitting chamfering
CN114961241A (en) * 2022-06-22 2022-08-30 江苏武进建工集团有限公司 Bare concrete V-shaped column formwork supporting system and construction method thereof

Similar Documents

Publication Publication Date Title
CN202644997U (en) Simple plugging device for wall-penetrating holes of wall
CN105926935A (en) Integral column formwork based on 3d printing and used for concrete pouring and column pouring method
CN102535849B (en) Constructional column top concreting method
CN203247600U (en) Equipment foundation bolt preformed hole die
CN206784951U (en) A kind of concreting floorslab thickness control device
CN201835524U (en) Pouring device for concrete beam with top embedded part
CN105952154B (en) A kind of concrete-pouring template stent
CN205012654U (en) Shedder and take shedder's template
CN106284428A (en) A kind of concrete column method for supporting of building structure post-cast strip
CN104727546A (en) Method for using aluminum alloy form board to pour concrete floor and transmission hole mould of method
CN105317230A (en) Fixing method of beam and wall pre-embedded horizontal sleeve
CN102912977A (en) Mold used for pouring shaped stair
CN210658959U (en) Constructional column concrete placement construction structures of smashing
CN201843347U (en) Pouring device provided with embedded part concrete column at top part
CN207268085U (en) Novel architecture through-wall bolt
CN207812625U (en) Special-shaped gutter template integrated apparatus
CN206815804U (en) A kind of new builder's jack girder steel built-in fitting
CN104908148A (en) Cable trough cover plate prefabricated template and construction method thereof
CN201962948U (en) Concrete beam pouring template with embedded part at top
CN205857707U (en) Stair step constructing device
CN102561692A (en) Method and template for pouring concrete beam or column with embedded part at top
CN202787992U (en) Constructional column top concrete pouring structure
CN201908437U (en) Concrete column casting die plate with embedded part at top
CN209723594U (en) A kind of positioning of assembled architecture reinforcing bar and check device
CN201915635U (en) Form erecting device free of bar planting for brickwork construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: GUIYANG ALUMINUM AND MAGNESIUM DESIGN INSTITUTE CO

Free format text: FORMER NAME: GUIYANG ALUMINIUM AND MAGNESIUM DESIGN INST.

CP03 Change of name, title or address

Address after: 550081 Guiyang Province, Jinyang New District, Zhu Zhu Road, No. 2

Patentee after: Guiyang Aluminum & Magnesium Design Institute Co., Ltd.

Address before: 550003 No. 208, Beijing Road, Guiyang, Guizhou

Patentee before: Guiyang Aluminium and Magnesium Design Inst.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110518

Termination date: 20151105

EXPY Termination of patent right or utility model