CN202787992U - Constructional column top concrete pouring structure - Google Patents

Constructional column top concrete pouring structure Download PDF

Info

Publication number
CN202787992U
CN202787992U CN 201220048566 CN201220048566U CN202787992U CN 202787992 U CN202787992 U CN 202787992U CN 201220048566 CN201220048566 CN 201220048566 CN 201220048566 U CN201220048566 U CN 201220048566U CN 202787992 U CN202787992 U CN 202787992U
Authority
CN
China
Prior art keywords
constructional column
concrete pouring
sleeve pipe
stack
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220048566
Other languages
Chinese (zh)
Inventor
张鹏
唐碧波
郑文科
阎杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Original Assignee
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Engineering Co Ltd of China Construction Third Engineering Division filed Critical Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority to CN 201220048566 priority Critical patent/CN202787992U/en
Application granted granted Critical
Publication of CN202787992U publication Critical patent/CN202787992U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to a constructional column top concrete pouring structure, comprising a casing pipe and an exhaust pipe, the constructional column top concrete pouring structure is characterized in that, the casing pipe is pre-embedded at an upper layer floor of the position of a constructional column, the exhaust pipe is pre-embedded beside the casing pipe, and column top concrete is poured via the pre-embedded casing pipe during construction of the constructional column. The heights of the casing pipe and the exhaust pipe are the height of a structural beam or the thickness of a structural plate. The constructional column top concrete pouring structure is advantaged by convenient installation, convenient concrete pouring, and improvement of constructional column concrete pouring quality, and solves the problem of non-density of constructional column top concrete pouring.

Description

Constructional column capital concrete pouring structure
Technical field
The utility model belongs to engineering field, and particularly constructional column capital concrete pouring structure is applicable to secondary structure constructional column and stem stem.
Background technology
For secondary structure constructional column capital concrete pouring construction technology be at present: constructional column capital template adopts the angle formwork, and concrete is built by angle, rejecting angle part concrete after finishing.The shortcoming of technique is: one, constructional column angle template is complicated, and it is large to support difficulty, and it is large to support difficulty when particularly floor height is higher.Two, structure capital concrete can't vibrate, and is mobile and conduct oneself with dignity that can not to guarantee that the capital concrete contacts with floor closely knit near concrete itself.Three, angle place concrete is rejected after form removal, causes the concrete waste.
Summary of the invention
Problem and defective that the purpose of this utility model exists in order to overcome prior art provide a kind of constructional column capital concrete pouring structure, guarantee secondary structure constructional column capital concrete construction quality.The utility model need not too much input, reduces constructional column formwork erection difficulty, shortens construction period, guarantees simultaneously constructional column capital concrete construction quality.
The technical scheme that its technical problem that solves the utility model adopts is:
Constructional column capital concrete pouring structure comprises sleeve pipe and stack, it is characterized in that: sleeve pipe is pre-buried at floor place, the upper strata of constructional column position, and at the other pre-buried stack of sleeve pipe, the capital concrete is built by pre-buried sleeve pipe during Constructional Col-umn Construction.
The height of described sleeve pipe and stack is structure deck-molding or structure thickness of slab.
Described sleeve pipe and stack adopt steel pipe, iron pipe and plastics material pipe.
Make pre-buried sleeve pipe and stack according to structure thickness of slab or structure deck-molding, when floor slab structure construct that sleeve pipe and stack and constructional column reinforcing bar while is pre-buried, and stack is embedded in by the sleeve pipe.When the secondary structure Constructional Col-umn Construction, build constructional column capital concrete by pre-buried concreting with sleeve pipe, discharge air by pre-buried stack.The utility model is equally applicable to the concreting of stem stem capital.
Description of drawings
Fig. 1 is for installing structural representation of the present utility model.
Fig. 2 is for building the structural representation of constructional column capital by the utility model.
The specific embodiment
The utility model is described in further detail for the structure accompanying drawing.
As shown in Figure 1, the utility model comprises sleeve pipe 1 and stack 2, it is characterized in that: sleeve pipe 1 is pre-buried at floor place, the upper strata of constructional column position, and at sleeve pipe 1 other pre-buried stack 2, the capital concrete is built constructional column capital concrete by pre-buried sleeve pipe 1 during Constructional Col-umn Construction, discharges air by pre-buried stack 2.The height of described sleeve pipe and stack is structure deck-molding or structure thickness of slab, and described sleeve pipe and stack can adopt steel pipe, iron pipe or plastics material pipe.
As shown in Figure 2, install the constructional column template, build constructional column capital concrete by pre-buried sleeve pipe 1, discharge air in the constructional column templates by pre-buried stack 2, after constructional column concreting is finished with sleeve pipe 1 and stack 2 concrete shutoff.

Claims (3)

1. constructional column capital concrete pouring structure comprises sleeve pipe and stack, it is characterized in that: sleeve pipe is pre-buried at floor place, the upper strata of constructional column position, and at the other pre-buried stack of sleeve pipe, the capital concrete is built by pre-buried sleeve pipe during Constructional Col-umn Construction.
2. constructional column capital concrete pouring structure according to claim 1, it is characterized in that: the height of described sleeve pipe and stack is structure deck-molding or structure thickness of slab.
3. constructional column capital concrete pouring structure according to claim 1 is characterized in that: described sleeve pipe and stack employing steel pipe, iron pipe or plastics material pipe.
CN 201220048566 2012-02-15 2012-02-15 Constructional column top concrete pouring structure Expired - Fee Related CN202787992U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220048566 CN202787992U (en) 2012-02-15 2012-02-15 Constructional column top concrete pouring structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220048566 CN202787992U (en) 2012-02-15 2012-02-15 Constructional column top concrete pouring structure

Publications (1)

Publication Number Publication Date
CN202787992U true CN202787992U (en) 2013-03-13

Family

ID=47815270

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220048566 Expired - Fee Related CN202787992U (en) 2012-02-15 2012-02-15 Constructional column top concrete pouring structure

Country Status (1)

Country Link
CN (1) CN202787992U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535849A (en) * 2012-02-15 2012-07-04 中建三局第二建设工程有限责任公司 Constructional column top concreting method
CN105155669A (en) * 2015-09-15 2015-12-16 成都市第四建筑工程公司 Hidden beam floor constructional column structure and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535849A (en) * 2012-02-15 2012-07-04 中建三局第二建设工程有限责任公司 Constructional column top concreting method
CN102535849B (en) * 2012-02-15 2014-06-25 中建三局第二建设工程有限责任公司 Constructional column top concreting method
CN105155669A (en) * 2015-09-15 2015-12-16 成都市第四建筑工程公司 Hidden beam floor constructional column structure and construction method thereof
CN105155669B (en) * 2015-09-15 2017-12-12 成都市第四建筑工程公司 Concealed beam floor framing rod structure construction method

Similar Documents

Publication Publication Date Title
CN202194317U (en) Guide rail structure for cast-in-site concrete slope surface
CN102535849B (en) Constructional column top concreting method
CN104060760B (en) High Rise Building Transfer Floor Structure concrete super large beam construction in layer method
CN103306463B (en) Metal liner concrete air channel construction method
CN204126263U (en) A kind of beam, the pre-buried horizontal case fastening devices of wall
CN103615063A (en) Construction method for pouring pitched roof concrete and steel bar structure used in method
CN202787992U (en) Constructional column top concrete pouring structure
CN103334771A (en) Concrete pouring method of side wall and joint of middle plate and vault by means of underground excavation reverse construction method
CN203668894U (en) Concrete prefabricated form structure allowing rapid installation
CN107386638B (en) The construction method of cast-in-place Decorative hanging board structure under a kind of beam
CN201835524U (en) Pouring device for concrete beam with top embedded part
CN204080820U (en) A kind of concrete structure foundation ditch support replacement device
CN204001214U (en) High accuracy capital embedded board
CN202450539U (en) Cement prefabricated tyre template
CN206769245U (en) A kind of combination construction component for strengthening Sloping roof construction quality
CN202440851U (en) Structure for supporting construction elevator foundation on basement top plate
CN202164555U (en) Bottom support of concrete box culvert template bracket post
CN102220808A (en) Beam lowering construction method of frame structure
CN202284291U (en) Concrete overflowing surface template shaped like Chinese character ba
CN206359993U (en) Stud structure for main transformer fire wall
CN103758092B (en) Quick construction method of concrete dam gallery
CN103469954A (en) Hollow floor box, hollow floor plate column and processing method of hollow floor plate column
CN204510812U (en) A kind of New Type Bracket column template
CN203238980U (en) Section steel support module structure
CN203891193U (en) Reinforced building block framework structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130313

Termination date: 20140215