CN201553992U - 一种对箱梁整体顶升的装置 - Google Patents

一种对箱梁整体顶升的装置 Download PDF

Info

Publication number
CN201553992U
CN201553992U CN2009202027446U CN200920202744U CN201553992U CN 201553992 U CN201553992 U CN 201553992U CN 2009202027446 U CN2009202027446 U CN 2009202027446U CN 200920202744 U CN200920202744 U CN 200920202744U CN 201553992 U CN201553992 U CN 201553992U
Authority
CN
China
Prior art keywords
anchor ear
box girder
jack
jacking
bridge
Prior art date
Application number
CN2009202027446U
Other languages
English (en)
Inventor
陈军
周松国
郭国良
周永福
Original Assignee
杭州市市政工程集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 杭州市市政工程集团有限公司 filed Critical 杭州市市政工程集团有限公司
Priority to CN2009202027446U priority Critical patent/CN201553992U/zh
Application granted granted Critical
Publication of CN201553992U publication Critical patent/CN201553992U/zh

Links

Abstract

本实用新型涉及桥梁工程中需要对箱梁进行纠偏或更换支座等行为时的装置,旨在提供一种对箱梁整体顶升的装置。该装置包括一立柱抱箍装置,该抱箍装置上配备有千斤顶,抱箍装置为紧贴现有立柱安装,千斤顶设在该抱箍装置的顶面,并与抱箍装置有稳固装置作固定。本实用新型的装置能整体顶升现有桥梁上的箱梁,对现有箱梁进行纠偏或支座更换,从而确保桥梁结构的正常使用,消灭了桥梁的安全隐患,延长了桥梁的使用寿命;而且本装置操作方便,安全可靠。

Description

一种对箱梁整体顶升的装置
技术领域
[0001] 本实用新型涉及桥梁工程中需要对箱梁进行纠偏或更换支座等行为时的装置,更 具体地说,是一种对箱梁整体顶升的装置。
背景技术
[0002] 随着城市高架、立交桥梁的日益增多,交通车流辆的越来越大,许多早年建设的桥 梁都发生了局部偏位或者支座损坏等现象,为了延长桥梁的使用寿命,就需要对箱梁结构 的桥梁进行整体顶升,然后再进行纠偏复位或者支座更换等修复工作,因此现阶段迫切需 要一种切实可行的装置来完成上述工作。 实用新型内容
[0003] 本实用新型的目的在于克服现有技术中的不足,提供一种对箱梁整体顶升的装置。
[0004] 为了解决上述技术问题,本实用新型是通过以下技术方案实现的:
[0005] 一种对箱梁整体顶升的装置,包括一立柱抱箍装置,该抱箍装置上配备有千斤顶。
[0006] 作为本实用新型的一种改进,所述抱箍装置为紧贴现有立柱安装;所述千斤顶设 在该抱箍装置的顶面,并与抱箍装置有稳固装置作固定。
[0007] 作为本实用新型的一种改进,所述抱箍装置为钢板和微膨胀砼构成,并由高强螺 栓与所述立柱作紧贴固定。
[0008] 作为本实用新型的一种改进,所述抱箍装置高度为60〜100cm。
[0009] 作为本实用新型的一种改进,所述抱箍装置单侧宽度为50〜70cm。
[0010] 作为本实用新型的一种改进,所述千斤顶连接着高压油泵。
[0011] 作为本实用新型的一种改进,所述千斤顶为超薄型油压千斤顶。
[0012] 本实用新型的有益之处在于:该装置能整体顶升现有桥梁上的箱梁,对现有箱梁 进行纠偏或支座更换,从而确保桥梁结构的正常使用,消灭了桥梁的安全隐患,延长了桥梁 的使用寿命;本装置操作方便,安全可靠。
附图说明
[0013] 图1为本实用新型的实施例的纵桥向结构示意图。
[0014] 图2为本实用新型的实施例的横桥向结构示意图
[0015] 图3为本实用新型的实施例的俯视图。
具体实施方式
[0016] 下面结合附图和具体实施例对本实用新型作进一步详细的描述:
[0017] 如图1、图2和图3所示,本实用新型的对箱梁整体顶升的装置包括一立柱抱箍5, 该抱箍5为紧贴现有立柱3安装;立柱抱箍5的高度60〜100cm,单侧宽度50〜70cm(为立柱3的边长加宽宽度);立柱抱箍5的顶面上安装有4个工作吨位为20吨的超薄型油压 千斤顶4,并有稳固装置作固定;千斤顶4可以选用江苏泰州超薄型油压千斤顶,并连接着 高压油泵。
[0018] 使用时,先在立柱3的周边用冲击钻钻孔,孔的个数以及螺栓个数满足箱梁整体 顶升的力学要求,并且用高强螺栓将立柱抱箍5与立柱3紧贴,立柱抱箍5外侧为钢板,内 侧用微膨胀砼灌满,然后在立柱抱箍5上安装千斤顶4,连接高压油泵开动千斤顶4,对箱梁 1进行整体同步分级顶升,直至顶升的设计允许位置。
[0019] 顶升力作用在了箱梁1底部的支座2的周边底板部位,顶升的位移量以千斤顶的 行程计算,以箱梁1顶升高度作为控制指标。顶升力达到计算值后,完成所需要的桥梁维修 (支座更换或纠偏工作)工作,然后进行卸荷。
[0020] 最后,还需要注意的是,以上列举的仅是本实用新型的具体实施例子。显然,本实 用新型不限于以上实施例子,还可以有许多变形。本领域的普通技术人员能从本实用新型 公开的内容直接导出或联想到的 所有变形,均应认为是本实用新型的保护范围。

Claims (7)

  1. 一种对箱梁整体顶升的装置,其特征在于:包括一立柱抱箍装置,该抱箍装置上配备有千斤顶。
  2. 2.根据权利要求1所述对箱梁整体顶升的装置,其特征在于:所述抱箍装置为紧贴现 有立柱安装;所述千斤顶设在该抱箍装置的顶面,并与抱箍装置有稳固装置作固定。
  3. 3.根据权利要求2所述的对箱梁整体顶升的装置,其特征在于:所述抱箍装置为钢板 和微膨胀砼构成,并由高强螺栓与所述立柱作紧贴固定。
  4. 4.根据权利要求1至3中任一项所述的对箱梁整体顶升的装置,其特征在于:所述抱 箍装置高度为60〜100cm。
  5. 5.根据权利要求4所述的对箱梁整体顶升的装置,其特征在于:所述抱箍装置单侧宽 度为50〜70cm。
  6. 6.根据权利要求1所述的对箱梁整体顶升的装置,其特征在于:所述千斤顶连接着高 压油泵。
  7. 7.根据权利要求6所述的对箱梁整体顶升的装置,其特征在于:所述千斤顶为超薄型 油压千斤顶。
CN2009202027446U 2009-12-17 2009-12-17 一种对箱梁整体顶升的装置 CN201553992U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009202027446U CN201553992U (zh) 2009-12-17 2009-12-17 一种对箱梁整体顶升的装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009202027446U CN201553992U (zh) 2009-12-17 2009-12-17 一种对箱梁整体顶升的装置

Publications (1)

Publication Number Publication Date
CN201553992U true CN201553992U (zh) 2010-08-18

Family

ID=42613669

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009202027446U CN201553992U (zh) 2009-12-17 2009-12-17 一种对箱梁整体顶升的装置

Country Status (1)

Country Link
CN (1) CN201553992U (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102102343A (zh) * 2010-12-17 2011-06-22 杭州市市政工程集团有限公司 一种对连续箱梁弯桥纠扭的方法
CN102518050A (zh) * 2011-12-29 2012-06-27 江苏华通工程检测有限公司 一种桥梁支座更换操作平台
CN102979042A (zh) * 2012-12-03 2013-03-20 河海大学 桥梁顶升过程中的桥墩连接装置及其施工方法
CN103437304A (zh) * 2013-09-04 2013-12-11 北京中交桥宇科技有限公司 一种增大桥墩截面更换盆式支座的方法
CN104846750A (zh) * 2015-04-20 2015-08-19 上海同罡建筑工程有限公司 一种带缝预应力摩擦型抱柱梁托换方法
CN104988853A (zh) * 2015-05-26 2015-10-21 上海同罡建筑工程有限公司 支座更换维修方法
CN106320193A (zh) * 2016-11-09 2017-01-11 郑州航空工业管理学院 一种桥梁支座更换和新安装时的调平方法
CN108797382A (zh) * 2018-04-28 2018-11-13 广西驰胜农业科技有限公司 旧桥整体同步顶升加高施工方法
CN110924305A (zh) * 2019-11-01 2020-03-27 中交第二航务工程局有限公司 一种预制盖梁安装定位系统的施工方法

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102102343A (zh) * 2010-12-17 2011-06-22 杭州市市政工程集团有限公司 一种对连续箱梁弯桥纠扭的方法
CN102518050A (zh) * 2011-12-29 2012-06-27 江苏华通工程检测有限公司 一种桥梁支座更换操作平台
CN102979042A (zh) * 2012-12-03 2013-03-20 河海大学 桥梁顶升过程中的桥墩连接装置及其施工方法
CN102979042B (zh) * 2012-12-03 2015-07-01 河海大学 桥梁顶升过程中的桥墩连接装置及其施工方法
CN103437304A (zh) * 2013-09-04 2013-12-11 北京中交桥宇科技有限公司 一种增大桥墩截面更换盆式支座的方法
CN103437304B (zh) * 2013-09-04 2016-04-13 北京中交桥宇科技有限公司 一种增大桥墩截面更换盆式支座的方法
CN104846750A (zh) * 2015-04-20 2015-08-19 上海同罡建筑工程有限公司 一种带缝预应力摩擦型抱柱梁托换方法
CN104988853A (zh) * 2015-05-26 2015-10-21 上海同罡建筑工程有限公司 支座更换维修方法
CN104988853B (zh) * 2015-05-26 2016-09-07 上海同罡建筑工程有限公司 支座更换维修方法
CN106320193A (zh) * 2016-11-09 2017-01-11 郑州航空工业管理学院 一种桥梁支座更换和新安装时的调平方法
CN108797382A (zh) * 2018-04-28 2018-11-13 广西驰胜农业科技有限公司 旧桥整体同步顶升加高施工方法
CN110924305A (zh) * 2019-11-01 2020-03-27 中交第二航务工程局有限公司 一种预制盖梁安装定位系统的施工方法

Similar Documents

Publication Publication Date Title
CN101684639B (zh) 钢构悬索桥施工的工艺方法及其专用轻型缆载吊机
CN102080356B (zh) 一种箱梁定位临时支座及箱梁定位施工方法
CN106835951A (zh) 一种可替换式预制装配式组合梁结构及制造工艺
CN201825671U (zh) 轨道板吊装小车
CN201635012U (zh) 箱梁架桥机
CN103334381B (zh) 安装钢箱梁的全支架轨道台车驮移装置及施工方法
CN206667037U (zh) 可替换式预制装配式组合梁结构
CN201221322Y (zh) 新型石油钻井提升系统及井架
CN103086282B (zh) 一种重型建筑起重机智能预警外爬系统
CN104099871A (zh) 高大跨度桥梁贝雷梁的成拱结构及其施工方法
CN104060540B (zh) 一种空间缆索悬索桥临时横撑及其吊装施工方法
CN101537976B (zh) 双塔桅巨型自升降起重设备及其跟携吊装方法
CN202164546U (zh) 高墩桥梁施工平台
CN201961944U (zh) 中间支撑装置
CN201010406Y (zh) 曳引机固定装置
CN102733615B (zh) 非对称整体提升施工方法
CN104131519B (zh) 一种桥梁拆除设备施工方法
CN201882763U (zh) 一种双机抬吊专用扁担梁
CN102530732A (zh) 大型压力机部件液压提升滑移就位方法及设备
CN103437563B (zh) 一种用于大型钢结构厂房钢骨架的安装方法
CN203284042U (zh) 辊盘式磨煤机磨辊吊装工具
CN201943007U (zh) 活动支架不变幅架梁吊机
CN201962607U (zh) 高架桥挑臂吊装用可移动式提升装置
CN102619174A (zh) 大跨度连续钢桁梁带拱顶推装置
CN101210418A (zh) 悬索桥塔架横梁无落地支架施工方法

Legal Events

Date Code Title Description
GR01 Patent grant
C14 Grant of patent or utility model
CX01 Expiry of patent term

Granted publication date: 20100818

CX01 Expiry of patent term