CN201437492U - 具有柔性基础和柔性附着的输电线路铁塔组立塔式起重机 - Google Patents
具有柔性基础和柔性附着的输电线路铁塔组立塔式起重机 Download PDFInfo
- Publication number
- CN201437492U CN201437492U CN2009201729795U CN200920172979U CN201437492U CN 201437492 U CN201437492 U CN 201437492U CN 2009201729795 U CN2009201729795 U CN 2009201729795U CN 200920172979 U CN200920172979 U CN 200920172979U CN 201437492 U CN201437492 U CN 201437492U
- Authority
- CN
- China
- Prior art keywords
- tower
- hoisting crane
- crane
- flexible
- foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 title claims abstract description 90
- 229910052742 iron Inorganic materials 0.000 title claims abstract description 46
- 230000005540 biological transmission Effects 0.000 title claims abstract description 15
- 239000000463 material Substances 0.000 claims abstract description 8
- 241001669679 Eleotris Species 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 18
- 239000000725 suspension Substances 0.000 abstract 1
- 238000009434 installation Methods 0.000 description 8
- 229910000831 Steel Inorganic materials 0.000 description 2
- 230000007423 decrease Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 239000006096 absorbing agent Substances 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000002950 deficient Effects 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000035939 shock Effects 0.000 description 1
Images
Landscapes
- Jib Cranes (AREA)
Abstract
Description
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009201729795U CN201437492U (zh) | 2009-08-21 | 2009-08-21 | 具有柔性基础和柔性附着的输电线路铁塔组立塔式起重机 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009201729795U CN201437492U (zh) | 2009-08-21 | 2009-08-21 | 具有柔性基础和柔性附着的输电线路铁塔组立塔式起重机 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201437492U true CN201437492U (zh) | 2010-04-14 |
Family
ID=42399469
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009201729795U Expired - Lifetime CN201437492U (zh) | 2009-08-21 | 2009-08-21 | 具有柔性基础和柔性附着的输电线路铁塔组立塔式起重机 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201437492U (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2015042945A1 (zh) * | 2013-09-29 | 2015-04-02 | 国家电网公司 | 一种安装有可移动式平衡重系统的组塔塔式起重机 |
CN115434558A (zh) * | 2022-10-12 | 2022-12-06 | 国网四川电力送变电建设有限公司 | 一种悬浮抱杆组塔腿部转向滑车实验用工装 |
-
2009
- 2009-08-21 CN CN2009201729795U patent/CN201437492U/zh not_active Expired - Lifetime
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2015042945A1 (zh) * | 2013-09-29 | 2015-04-02 | 国家电网公司 | 一种安装有可移动式平衡重系统的组塔塔式起重机 |
CN115434558A (zh) * | 2022-10-12 | 2022-12-06 | 国网四川电力送变电建设有限公司 | 一种悬浮抱杆组塔腿部转向滑车实验用工装 |
CN115434558B (zh) * | 2022-10-12 | 2023-08-25 | 国网四川电力送变电建设有限公司 | 一种悬浮抱杆组塔腿部转向滑车实验用工装 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101670985B (zh) | 具有柔性基础和柔性附着的输电线路铁塔组立塔式起重机 | |
CN202132187U (zh) | 风力发电机组拉索式塔架结构 | |
CN201783769U (zh) | 风力发电铁塔筒节翻转装置 | |
CN202358849U (zh) | 一种小型悬臂吊 | |
CN109236012B (zh) | 一种输电线路干字型拉线塔吊装方法 | |
CN105836594B (zh) | 一种自爬升式大型风力机通用维护吊装装置及其使用方法 | |
CN113966435A (zh) | 风力发电机安装和拆卸装置及利用此装置的施工方法 | |
CN108946509A (zh) | 一种大型风力发电机自升塔吊施工方法 | |
CN114751316A (zh) | 一种内爬式双平臂抱杆 | |
CN201437492U (zh) | 具有柔性基础和柔性附着的输电线路铁塔组立塔式起重机 | |
CN101633483A (zh) | 一种钢结构网架整体提升装置 | |
CN2761563Y (zh) | 超高、捆绑、自升式风力发电机专用塔吊 | |
CN209503282U (zh) | 一种用于焊接风电基础塔筒的旋转式工作平台 | |
JP3700306B2 (ja) | 風力発電装置の建設方法 | |
CN211777820U (zh) | 一种钢管混凝土塔架 | |
CN205114897U (zh) | 塔机内置内爬式支撑系统的自倒运装置 | |
CN101362577A (zh) | 全液压汽车塔式起重机 | |
CN201195670Y (zh) | 全液压汽车塔式起重机 | |
CN210084786U (zh) | 起重扒杆 | |
CN209276035U (zh) | 一种自立式超高吊装系统 | |
CN210457249U (zh) | 机身自顶升的电力抱杆结构 | |
CN207244453U (zh) | 一种悬索桥轻型锚碇门架装置 | |
CN201694777U (zh) | 水轮机蜗壳自吊装装置 | |
CN201534972U (zh) | 主杆调平门架式强夯机 | |
CN215168617U (zh) | 大型事故水塔蓄水池提升支架 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
ASS | Succession or assignment of patent right |
Owner name: CHINA ELECTRIC POWER RESEARCH INSTITUTE Effective date: 20140307 Owner name: STATE GRID CORPORATION OF CHINA Free format text: FORMER OWNER: CHINA ELECTRIC POWER RESEARCH INSTITUTE Effective date: 20140307 |
|
COR | Change of bibliographic data |
Free format text: CORRECT: ADDRESS; FROM: 100192 HAIDIAN, BEIJING TO: 100031 XICHENG, BEIJING |
|
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20140307 Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing Patentee after: State Grid Corporation of China Patentee after: China Electric Power Research Institute Address before: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15 Patentee before: China Electric Power Research Institute |
|
CX01 | Expiry of patent term | ||
CX01 | Expiry of patent term |
Granted publication date: 20100414 |