CN201345512Y - 220KV double-circuit overhead tower-sharing circuit high-voltage strong-electric-field special tool - Google Patents

220KV double-circuit overhead tower-sharing circuit high-voltage strong-electric-field special tool Download PDF

Info

Publication number
CN201345512Y
CN201345512Y CNU2008201994743U CN200820199474U CN201345512Y CN 201345512 Y CN201345512 Y CN 201345512Y CN U2008201994743 U CNU2008201994743 U CN U2008201994743U CN 200820199474 U CN200820199474 U CN 200820199474U CN 201345512 Y CN201345512 Y CN 201345512Y
Authority
CN
China
Prior art keywords
card
pairs
equipotential
tower
electric field
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2008201994743U
Other languages
Chinese (zh)
Inventor
聂新华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGXI JIAN POWER SUPPLY Co Ltd
State Grid Corp of China SGCC
Original Assignee
JIANGXI JIAN POWER SUPPLY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGXI JIAN POWER SUPPLY Co Ltd filed Critical JIANGXI JIAN POWER SUPPLY Co Ltd
Priority to CNU2008201994743U priority Critical patent/CN201345512Y/en
Application granted granted Critical
Publication of CN201345512Y publication Critical patent/CN201345512Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

本实用新型公开了一种220KV双回共塔线路高压强电场专用工具,包括两付固定卡、导轨、两付以上可沿导轨上移动的移动卡及绝缘梯,两付固定卡下端分别固定于导轨两端,移动卡下端联接绝缘梯。所述固定卡上下端设有安装孔。移动卡上下端设有上、下眼孔。采用本实用新型进入强电场即能保持等电位人员的组合间隙要求,而且人体可以在绝缘梯上直接进行等电位作业,无需登上导线,其安全带可系于绝缘梯上,后备保护绳系于杆塔上,即使发生掉线事故,人体仍能稳定站立在绝缘梯上,与掉线无关系,充分保证了等电位人员作业时的人身安全。本实用新型结构简单、方便实用、安全可靠、成本低廉,适用于220KV线路等电位操作半径为0.5m内的作业项目。

Figure 200820199474

The utility model discloses a special tool for a 220KV double-circuit common-tower line with high voltage and strong electric field, which comprises two pairs of fixed cards, guide rails, more than two pairs of mobile cards that can move along the guide rails, and an insulating ladder. The lower ends of the two pairs of fixed cards are respectively fixed on At both ends of the guide rail, the lower end of the mobile card is connected to the insulation ladder. The upper and lower ends of the fixed card are provided with mounting holes. The upper and lower ends of the mobile card are provided with upper and lower eye holes. Adopting the utility model to enter the strong electric field can maintain the combination gap requirements of equipotential personnel, and the human body can directly perform equipotential work on the insulating ladder without the need to board the wire, and the safety belt can be tied to the insulating ladder, and the backup protection rope is tied. On the tower, even if there is a disconnection accident, the human body can still stand stably on the insulating ladder, which has nothing to do with the disconnection, which fully guarantees the personal safety of the equipotential personnel during operation. The utility model has the advantages of simple structure, convenience and practicality, safety and reliability, and low cost, and is suitable for operation items within a 0.5m radius of equipotential operation of 220KV lines.

Figure 200820199474

Description

The two tower circuit High Voltage electric field specific purpose tools altogether that return of 220KV
Technical field
The utility model relates to the two tower circuit High Voltage electric field specific purpose tools altogether that return of a kind of 220KV, belongs to transmission line equipotential live line working technical field.
Background technology
Up to now, China's transmission line operational method of entering 220KV circuit highfield generally has following several: 1, the equipotential personnel utilize the rope ladder method to enter highfield from the ground climbing; 2, the equipotential personnel enter highfield along the hard ladder of level insulation; 3, the equipotential personnel enter strain insulator shaft tower highfield along insulator string by the method for " stride two short three "; 4, the equipotential personnel take hanging basket and enter the straight line pole highfield; 5, the equipotential personnel utilize " parachuting method " to enter highfield.
Take above several method to enter 220KV circuit highfield, following shortcoming is arranged: 1, utilize the rope ladder method to enter highfield: utilizing this method to enter highfield, be applicable to all 220KV single loop shaft towers, is maximum method of using at present.But be not suitable for two returning with the tower circuit, because two times mostly are vertical arrangement greatly (as the fermented soya beans, salted or other wise type with tower circuit three-phase conducting wire, positive umbellate form, inversed umbrella type), enter, in during the phase conductor electric field, must be through lower wire, combinational gap is difficult to reach the requirement that 2.5m among the 8.3.3 of company's " electric power safety working regulation " circuit pack requirement nets in state when at first being the process lower wire, it is excessive that next is that personnel climb on more than the 30 meter high lead physical demands from ground, also be that the most important is at last, stipulate according to " live line working technology guide rule ", should not carry out the hanging ladder operation with the tower circuit two times, and rope ladder is hung on two returning with on the tower lead, against stipulating in " live line working technology guide rule ".Also have big crossover tower to be triangularly arranged, but big crossover tower cross-arm apart from the ground vertical range higher (exhale claim high for 50m and more than), it is unpractical from ground to the high-altitude of 50m that personnel climb rope ladder.2; enter highfield along the hard ladder of level insulation: take this method no matter be straight line pole or strain insulator shaft tower; all require hard terraced intensity high; and bending resistance is strong; particularly reach 5m and when above when cross-arm length; hard terraced length also need reach more than the 5m; equipotential personnel are when hard ladder is central; because the flexibility of insulating material; swing up and down greatlyyer, the equal potential working personnel are difficult to control balance, have the danger of falling; and human body enters in the process of strain insulator shaft tower electric field along the hard ladder of level; its combinational gap does not reach the requirement of 2.1m, because calculate with a string strain insulator string (14, total length is 2m) length deduction human body width (being about 40cm); its combinational gap is 1.6m; less than 2.1m,, must install the protection gap additional if adopt this method.3, method along insulator string enters strain insulator shaft tower highfield: adopt this method to enter highfield (using in Shanxi), its combinational gap does not reach the requirement of 2.1m, because human body (insulator in the supposition insulator string is qualified insulator) on insulator string needs three insulators of short circuit, its combinational gap is at 1.6m and following, if have null value or low resistance insulator in the insulator string, then good insulation sheet number is difficult to satisfy among the table 8-3 that state net company's " electric power safety working regulation " circuit pack requires 9 requirement in the insulator string, and this operational method is extremely dangerous.4, take hanging basket and enter the straight line pole highfield: take this method to enter highfield, it is many to reach the ground support staff on the required tower, and support staff and equipotential personnel are if cooperation is bad, and hanging basket is turned on one's side easily, cause personal falling accident, be absolutely unsafe.When on straight line pole, carrying out equal potential working, equipotential personnel can not be seated at operation on the lead, because the 220KV circuit mostly is single conductor or double bundle conductor greatly, human body is seated on the lead, because the height (being about 0.9m) of upper half of human body, will make the air gap of electrified body and cross-arm be contracted to 1.1m, not satisfy the requirement of 2.1m far away.At this moment, human body can only be seated at operation in the hanging basket, and human body operation in hanging basket will be very difficult.5, utilize " parachuting method " to enter highfield: this is a kind of novel technology, also exclude in the GB, adopt this method, require the lead phase spacing bigger, be mainly used in 500KV and above circuit, and 220KV line conductor phase spacing can not show a candle to the 500KV circuit, so it is when using, need the control of stabilizer pole, and higher to equipotential personnel and support staff's specification requirement, the load of bearing during equipotential personnel's operation is heavier, operates when being unfavorable for equipotential.
Summary of the invention
The purpose of this utility model is: provide a kind of simple in structure, convenient and practical, with low cost, can guarantee that the equipotential personnel enter the two specific purpose tools of tower circuit High Voltage electric fields altogether that return of 220KV of highfield safety operation.
The purpose of this utility model realizes by following scheme: comprise two pairs of fixed card, guide rail, can be along the mobile card and the insulating ladder that move on the guide rail more than two pairs, two pairs of fixed card lower ends are individually fixed in the guide rail two ends, move the card lower end and connect insulating ladder.
The utility model also comprises the operations chair that flexibly connects with the insulating ladder tail end.
Fixed card upper and lower side described in the utility model is provided with installing hole.Move the card upper and lower side and be provided with upper and lower eyelet.
Last eyelet buried bearing on the mobile card described in the utility model, and be connected on the guide rail moving to link with threading a needle.
Adopt the utility model to take to insulate method that slide or insulation pivoted arm ladder enter highfield; the combinational gap requirement that can keep the equipotential personnel; and human body can directly carry out equal potential working on insulating ladder; need not to climb up lead; its safety belt can lie on the insulating ladder; the backup protection rope lies on the shaft tower; effectively avoided above five kinds of methods to need safety belt is tied up on the lead; and reserve protection rope need tie up on the hanging ladder or on the shaft tower; if fall the accident that string causes lead to drop in case tool failure or insulator occur, human body just has the danger of falling or being torn by lead and cross-arm with lead.And safety belt is lain on the insulating ladder, the backup protection rope lies on the shaft tower, even the accident of going offline, human body still can be stablized and stand on the insulating ladder, with go offline irrelevant, the personal safety when fully having guaranteed equipotential personnel's operation.The utility model is simple in structure, convenient and practical, safe and reliable, with low cost, be applicable to that 220KV circuit equipotential operative radius is the events in operation in the 0.5m: as change suspension insulator string, change suspension clamp or wire clamp inspections of uncapping, change grading ring, change stockbridge damper, repairing lead on the lead between stockbridge damper and the suspension clamp, change operations such as jumper clamp, repairing wire jumper.
Description of drawings
Fig. 1 is the utility model structural representation;
Fig. 2 moves card, insulating ladder and operations chair connecting relation schematic diagram for the utility model;
Fig. 3 is mobile card and the insulating ladder user mode schematic diagram of the utility model more than two pairs.
Embodiment
Below in conjunction with embodiment and contrast accompanying drawing the utility model is elaborated.
Present embodiment comprises two pairs of operations chairs 5 of making by Hot-dip zinc-coated flat steel sheet or steel alloy that fixed card 1, one are made insulating ladder 4 that metal exclusive guideway 2, two pairs can make along the mobile card 3 that moves on the guide rail 2, by the polyethylene epoxy resin insulation material by the rectangle steel alloy and flexibly connecting with insulating ladder 4 tail ends and made by metal frame and batten.Two pairs of fixed card 1 lower ends are individually fixed in guide rail 2 two ends by bolt, and fixed card 1 upper and lower side is provided with installing hole 11,12.Installing hole 11 is used for fixing card 1 upper end and is connected with cross-arm master material 6.Move card 3 lower ends and connect insulating ladder 4, move card 3 upper and lower sides and be provided with upper and lower eyelet 21,22, last eyelet 21 buried bearings 23, and block 3 and be connected on the guide rail 2 mobile with threading a needle.
During use, at first fixed card is connected in cross-arm by the ground staff, it is vertically hung on shaft tower, and (hanging position of insulated sling must keep the air gap with 2.5 meters of live wires, to be insulated by earth potential personnel on the tower, (front end is installed on the cross-arm end to the firm hook of slide fixed card on the master of cross-arm lower floor material, be the yoke plate rear portion), and with the two ends set bolt metal part firmly is installed on the shaft tower cross-arm, remove lifting rope subsequently; The ground staff will connect insulating ladder and operations chair again, hang on the shaft tower cross-arm, and earth potential electric insulation ladder is installed on the active card of two pulleys on the tower, connects with bolt, removes insulated sling subsequently and gets final product.Also can be earlier the complete set slide that insulate be assembled by the ground staff, after hanging on the shaft tower cross-arm, cooperate the slide that to insulate firmly to be installed on the cross-arm by two electricians on the tower, take the method for this integral hoisting, insulated sling must hang on mobile jib or the main material, the ground staff should control tail rope well, and the metal guide rail two ends are kept and each phase line 2.1 meter ampere full distance.The earth potential electrician slide that will insulate moves to guide rail rear end (being the shaft tower side); equipotential electrician after fastening insulation backup protection rope on the shaft tower along insulating ladder down to the operations chair place; and seated (head should be contour with live wire); safety belt is lain on the insulating ladder; again by the earth potential electrician will insulate slide connect the people together average rate move to the lead side, equipotential electrician can carry out all kinds of equal potential workings on insulating ladder.

Claims (5)

1, a kind of two specific purpose tool of tower circuit High Voltage electric field altogether that returns, it is characterized in that: comprise two pairs of fixed card (1), guide rail (2), two pairs of mobile card (3) and insulating ladders (4) that move with upper edge guide rail (2), two pairs of fixed card (1) lower end is individually fixed in guide rail (2) two ends, moves card (3) lower end and connects insulating ladder (4).
2, two specific purpose tool of tower circuit High Voltage electric field altogether that returns according to claim 1 is characterized in that: also comprise the operations chair (5) that flexibly connects with insulating ladder (4) tail end.
3, two specific purpose tool of tower circuit High Voltage electric field altogether that returns according to claim 1 and 2, it is characterized in that: fixed card (1) upper and lower side is provided with installing hole (11,12).
4, two specific purpose tool of tower circuit High Voltage electric field altogether that returns according to claim 1 and 2 is characterized in that: move card (3) upper and lower side and be provided with upper and lower eyelet (21,22).
5, two specific purpose tool of tower circuit High Voltage electric field altogether that returns according to claim 4 is characterized in that: move last eyelet (21) buried bearing (23) on the card (3), and be connected on the guide rail (2) moving card (3) with threading a needle.
CNU2008201994743U 2008-12-11 2008-12-11 220KV double-circuit overhead tower-sharing circuit high-voltage strong-electric-field special tool Expired - Fee Related CN201345512Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008201994743U CN201345512Y (en) 2008-12-11 2008-12-11 220KV double-circuit overhead tower-sharing circuit high-voltage strong-electric-field special tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008201994743U CN201345512Y (en) 2008-12-11 2008-12-11 220KV double-circuit overhead tower-sharing circuit high-voltage strong-electric-field special tool

Publications (1)

Publication Number Publication Date
CN201345512Y true CN201345512Y (en) 2009-11-11

Family

ID=41277095

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008201994743U Expired - Fee Related CN201345512Y (en) 2008-12-11 2008-12-11 220KV double-circuit overhead tower-sharing circuit high-voltage strong-electric-field special tool

Country Status (1)

Country Link
CN (1) CN201345512Y (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102623930A (en) * 2012-04-17 2012-08-01 邯郸供电公司 Replacing the hanging string combination tool
CN102684083A (en) * 2012-04-21 2012-09-19 石家庄供电公司 Convenient-to-use high-altitude structure walkabout for hanging double rope
CN107332154A (en) * 2017-06-20 2017-11-07 国网福建省电力有限公司泉州供电公司 Power line tension bar intelligence outgoing line device control circuit
CN109787149A (en) * 2019-03-07 2019-05-21 国网湖北省电力公司咸宁供电公司 A kind of special hard ladder used for jumper line maintenance and using method thereof
CN110499951A (en) * 2019-09-17 2019-11-26 国网辽宁省电力有限公司辽阳供电公司 A suspension point extension device for iron tower cross-arm ladder and its application
CN111509647A (en) * 2020-04-27 2020-08-07 东北电力大学 Automatic short circuit joint control device for direct-current deicing of transmission conductor

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102623930A (en) * 2012-04-17 2012-08-01 邯郸供电公司 Replacing the hanging string combination tool
CN102623930B (en) * 2012-04-17 2017-08-25 国家电网公司 String combination tool is hung in replacing
CN102684083A (en) * 2012-04-21 2012-09-19 石家庄供电公司 Convenient-to-use high-altitude structure walkabout for hanging double rope
CN102684083B (en) * 2012-04-21 2014-12-10 国家电网公司 Convenient-to-use high-altitude structure walkabout for hanging double rope
CN107332154A (en) * 2017-06-20 2017-11-07 国网福建省电力有限公司泉州供电公司 Power line tension bar intelligence outgoing line device control circuit
CN109787149A (en) * 2019-03-07 2019-05-21 国网湖北省电力公司咸宁供电公司 A kind of special hard ladder used for jumper line maintenance and using method thereof
CN110499951A (en) * 2019-09-17 2019-11-26 国网辽宁省电力有限公司辽阳供电公司 A suspension point extension device for iron tower cross-arm ladder and its application
CN110499951B (en) * 2019-09-17 2024-04-19 国网辽宁省电力有限公司辽阳供电公司 Iron tower cross arm rope ladder hanging point extension device and application
CN111509647A (en) * 2020-04-27 2020-08-07 东北电力大学 Automatic short circuit joint control device for direct-current deicing of transmission conductor

Similar Documents

Publication Publication Date Title
CN201345512Y (en) 220KV double-circuit overhead tower-sharing circuit high-voltage strong-electric-field special tool
CN102623926B (en) Distant equipotential tackle and method for realizing charged equipotential access by using same
CN102664358B (en) Live replacement method for static contact of 220 kV flexible busbar
CN203367865U (en) Auxiliary bracket for maintaining power transmission line
CN109256721A (en) A kind of helicopter live-line maintenance operation hanging basket
CN203352053U (en) Chain-type ladder used for maintenance of straight line tower of power transmission line
CN106207885B (en) The short circuit fixture and method of charged for replacement 220kV pipe bus telescoping wire clamps
CN202611568U (en) Insulation trestle ladder
CN201717173U (en) 220KV vertically-opened disconnecting switch shunt device
CN206379675U (en) Yoke plate card for live-line replacement of V-string insulator wire of tangent tower
CN103500966B (en) 66kv disconnecting switch is to pipe bus charged disconnecting lead-in wire method
CN201584691U (en) Special tool for 220KV double-circuit common-tower line accessing tension-resistance high-pressure high-electric field
CN205882560U (en) Special circulation cord rack device of distribution live working earth potential
CN107575081B (en) A kind of transposition tower and its interchanging method
CN103532052A (en) Live erection of simple crossing structure on ADSS (all-dielectric self-supporting optic fiber cable) and implementation method
CN206237109U (en) A lightning protection wire connection mechanism in a substation
CN203909070U (en) Current transformer polarity test rod
CN105888353B (en) A kind of single-phase bracing wire anchor support and its application
CN204850643U (en) Steel pipe pole is more bored to trigeminy
CN210490269U (en) Rotary transposition line ladder
CN207368624U (en) A kind of transposition tower
CN203707676U (en) Isolation net for replacement of high voltage iron tower lightning wire or composite ground wire
CN205908091U (en) Exchange two tangent towers that return
CN116742528B (en) Cross 10kV overhead line stringing device
CN206947826U (en) A kind of safety belt support bar

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Effective date: 20130206

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 336000 JI AN, JIANGXI PROVINCE TO: 343000 JI AN, JIANGXI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20130206

Address after: 251 No. 343000 Ji'an province Jiangxi City Qingyuan District Qingyuan Road

Patentee after: Jiangxi Jian Power Supply Co., Ltd.

Patentee after: State Grid Corporation of China

Address before: 251 No. 336000 Ji'an province Jiangxi City Qingyuan District Road

Patentee before: Jiangxi Jian Power Supply Co., Ltd.

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20091111

Termination date: 20131211